Matter: Nova Scotia Power Inc. - CI C0053295 - L5004 Kearney Lake Structure Replacement - $6,836,784 (ATO)
1 passage 1 document

Environmental Compliance across all matters →

N-2NSPI (NSEB) RIR 1 to 4 1 passage
Section 4
Please note that internal NS Power labour is required to prepare, submit, coordinate, and obtain approvals for each permit application and regulatory request noted above. Based on previous experience, each request typically requires approx...

AI summary The document outlines the time and labor required for NS Power to handle permit applications and regulatory requests, estimating 6 to 8 hours per request. It also notes that the removal of pole butts in a lake requires approval from the Nova Scotia Department of Natural Resources and must be done in an environmentally responsible manner.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →