Matter: Procurement Administrator - Power Advisory - Application for Approval of the Green Choice Power Purchase Agreement
2 passages 2 documents

Environmental Goals And Climate Change Reduction Act across all matters →

P-1-(v)Appendix E - Draft Green Choice Program Procurement Request for Proposals (RFP) 1 passage
Scored Criteria Points Environmental Risk p. p. 28
Scored Criteria Points Environmental Risk Available 7 points The Project Configuration receives a score of 4.0 on the Environmental Risk Questionnaire OR The Primary Project Configuration has received EA approval with conditions on or befo...

AI summary The document outlines a scoring system for environmental risk based on the Environmental Risk Questionnaire, with specific scores corresponding to different levels of points. It also notes that projects with EA approval with conditions do not need to submit the questionnaire.

103964Reply Comments - Power Advisory 1 passage
Requirement for the Scheduled Commercial Operation and Commencement Date p. p. 0
Requirement for the Scheduled Commercial Operation and Commencement Date The Early Completion Incentive is provided to encourage the Seller to have its Facility achieve Commercial Operation before 2030 to meet a policy objective, which is...

AI summary The text discusses the requirement for the Scheduled Commercial Operation and Commencement Date under the Renewable Electricity Regulations and the Environmental Goals and Climate Change Reduction Act. These regulations mandate that 80% of electricity supplied to customers must be renewable by 2030, and projects must be operational by December 31, 2029 to support system planning and clean energy goals.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →