Topic/Matter Intersection

Topic:"Ev Charging Control" in M13050

Matter: Town of Mahone Bay Electric Utility - Edgewater Project $2,650,000
2 passages 1 document

Ev Charging Control across all matters →

M-2-(i)Project Drawings 2 passages
PARK AREA DISTRIBUTION:
PARK AREA DISTRIBUTION: THE PARK AREA NEAR THE CHURCHES HAS BEEN IDENTIFIED AS EVENT SPACE. IT IS UNDERSTOOD THAT THE TOWN OF MAHONE BAY WOULD LIKE TO SUPPORT THE FOLLOWING LOADS: STREET LIGHTING, EV CHARGERS, VARIOUS RECEPTACLES FOR TEMPO...

AI summary The park area near the churches is designated as an event space. The Town of Mahone Bay seeks to support street lighting, EV chargers, and temporary services like food trucks and Christmas lighting. However, EV charger supply and installation are not included in the current scope.

Section 115
TOWN OF MAHONE BAY EDGEWATER STREET IMPROVEMENTS ELECTRICAL PARK DISTRIBUTION DETAILS 1 OF 2 CBCL No 241016.00 Date OCT 2024 Designed VS Checked LO'K Sheet No 12 Ocntract No Contract No Accorded AS NOTED Drawn VS MF Approved LO'K JAB Drawi...

AI summary The document outlines specifications for the installation of Level-2 EV charger pedestals as part of Edgewater Street improvements in Mahone Bay. It requires coordination with the manufacturer, submission of shop drawings for approval, and structural engineering stamps for pedestal foundation bases.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →