CONFIDENTIAL (Attachment Only) 1 Request IR-6: 2 3 (a) Please provide more details about NRCan funding, including all conditions. Has NS 4 Power received the funding already? 5 6 (b) What would be the impact on the overall project if the B...
AI summary The response to IR-6 outlines that NSPI received 71% of total project costs through NRCan funding, which was available until March 31, 2025. Eligible costs included project-specific expenses, but overhead was not eligible. If the Board denies the application, the company would need to review the decision to assess impacts.