Topic/Matter Intersection

Topic:"Financial Instruments" in M12593

Matter: Nova Scotia Power Inc. - CI C0053696 – ECC Wind Integration - $4,428,335
1 passage 1 document

Financial Instruments across all matters →

N-2NSPI (NSEB) RIR 1 to 22 - Redacted 1 passage
CONFIDENTIAL (Attachment Only) p. p. 33
CONFIDENTIAL (Attachment Only) 1 Request IR-17: 2 3 (a) Please provide details about the NRCan funding, including any conditions, and 4 indicate whether NS Power has already received the funding. 5 6 (b) If NS Power has not yet received th...

AI summary NS Power has received 100% reimbursement of eligible costs from NRCan for a project, representing 33% of total project costs. The funding was available until March 31, 2025, and was fully received in July 2025. If the Board denies the application, the company would need to review the decision to assess impacts.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →