Accordingly, NERC initially considered a 20 MW and 60 kV threshold would include a majority of entities contributing to the reliability risk posed by the connection of computational loads to the BPS. After further analysis and consideratio...
AI summary The text discusses North American Electric Reliability Corporation (NERC) deliberations regarding the threshold for including computational loads in reliability risk assessments. NERC proposed a 50 MW and 100 kV threshold, balancing the inclusion of significant computational load while excluding smaller entities. Data analysis indicates approximately 79,502 MW of data center load will be active by the end of 2027, with most entities at or above the 50 MW threshold likely connecting at 100 kV or higher due to physical and reliability constraints.