Topic/Matter Intersection

Topic:"Fuel Cost Adjustment" in M12420

Matter: Nova Scotia Power Inc. - CI C0067183 – TUC Wharf Access Bridge Replacement - $2,426,669 (U&U)
1 passage 1 document

Fuel Cost Adjustment across all matters →

N-1Application - CI C0067183 - TUC Wharf Access Bridge Replacement - Redacted 1 passage
Why do this project? p. p. 5
Why do this project? The wharf must be operable to accept deliveries of heavy fuel oil. In addition to fuel used at Tufts Cove, this facility accepts delivery of the heavy fuel oil that is used at Lingan, Trenton, and Point Tupper plants....

AI summary The wharf needs to be replaced as it is no longer suitable for safe operation and must be operable to accept deliveries of heavy fuel oil to multiple plants including Tufts Cove, Lingan, Trenton, and Point Tupper.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →