6.2PM2 Vacuum Blower Power Reduction Project According to the INITIAL REPORT, one of 4 blowers was shut down on PM2 vacuum system in the fall of 2010 and significant changes were made to the suction system. In fact this project took place...
AI summary The document discusses the PM2 Vacuum Blower Power Reduction Project, which involved shutting down one of four blowers on the PM2 vacuum system in 2010. The project was completed in July 2009, allowing the mill to operate sustainably with three blowers. Photos of the vacuum pump and motor nameplate are included.