Matter: NSP Maritime Link Inc. (NSPML) - 2026 Q1 Quarterly Report
2 passages 2 documents

Generation Grid Resources across all matters →

N-1Report - Redacted 1 passage
1 engineering and planning activities progressed in order to prepare for the upcoming p. pp. 6-8
Recommendation number 1 is closed. 1 engineering and planning activities progressed in order to prepare for the upcoming 30 All three units are available and operating normally as required and as dispatched by the 31 NLSO subject to normal...

AI summary Engineering and planning activities are progressing to prepare for upcoming operations. Unit 2 is scheduled for a 17-week major inspection from May to August 2026. The Labrador Island Link (LIL) successfully completed high-power testing and is being prepared for full operation. The Muskrat Falls Project is fully operational, providing benefits to customers in Nova Scotia and Newfoundland & Labrador.

102327Board letter re: Accepted as file with duther updates to be included in the next report 1 passage
M12808 - NSP Maritime Link Inc. - Q1 2026 Quarterly Report p. p. 0
submission to the NL System Operator. Upon submission and acceptance, the LIL will be released for full operation up to 900 MW. The Board notes the following from its review of this quarterly report:

AI summary The submission to the NL System Operator regarding the LIL project has been accepted, allowing the LIL to operate at full capacity up to 900 MW. The Board has reviewed the quarterly report and noted relevant information.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →