Matter: CI# 28098 - P-128.07 - NSPI WO -  Authority to Overspend the Tufts Cove 6 Waste Heat Recovery Project - $8,699,864Approximate value for approval of $8.5 million.
1 passage 1 document

Generator Interconnection across all matters →

N-3Redacted NSPI (NSUARB) IR-1 to IR-20 7/16/2010 1 passage
Option 1 p. p. 212
Option 1 NSPI accept the proposed generator temperature rise limit change from Class B to Class F which allows MELCO to maintain the current generator frame size and design (Reference attached MELCO Technical Correspondence Sheet HWLT01-G0...

AI summary NSPI accepts a proposal to change the generator temperature rise limit from Class B to Class F, allowing MELCO to keep the current generator frame size and design. The design will include larger oil coolers, with an additional cost of $25,000.00 CAD.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →