Matter: P-188 - NSPI Regulation 3.6 - Net Metering - Request approval of the revised Regulation 3.6Enhanced net metering service, in compliance with recent legislative changes to the Electricity Act.
7 passages 4 documents

Generator Interconnection across all matters →

N-1Letter, Application and Evidence filed by NSPI 11/1/2010 2 passages
Preamble p. p. 0
n to the distribution system. 30 31 All distribution connected generation of 100 kW or greater currently falls into 32 NSPI's distribution interconnection process. As such, net metered generators of

AI summary The text discusses the distribution interconnection process for generators of 100 kW or greater within NSPI's system, highlighting that net metered generators are subject to this process.

3.6 NET METERING SERVICE p. pp. 16-21
3.6 NET METERING SERVICE - c) To receive the net metering service the customer must submit an Application and execute the "Net Metering Interconnection Agreement" with NSPI. - d) The generating facility and all wiring, equipment and device...

AI summary The net metering service requires customers to submit an application and sign an interconnection agreement with NSPI. The generating facility must comply with NSPI's interconnection guidelines. Voluntary termination of the service results in a 12-month non-renewal period.

N-2NSPI IR Responses HRWC 1/26/2011 1 passage
\ \ The general service area is a summary and does not describe all areas served.
\ \ The general service area is a summary and does not describe all areas served. 1 Request IR-2: 15 This is identical for any low carbon and carbon free energy source that displaces 16 conventional carbon intensive energy whether through...

AI summary The text discusses the lack of mechanisms in Nova Scotia to define or value emission credits and the potential for such credits to reduce fuel costs for NSPI's customers. It also addresses the interconnection process for distribution-connected generation of 100 kW or greater and whether NSPI is considering streamlining the application process for Class 2 projects.

N-6NSPI Reply Submission 2/23/2011 1 passage
5. GET YOUR PROJECT CONNECTED p. p. 46
5. GET YOUR PROJECT CONNECTED Once a project is approved through the One Window Committee process, an applicant will need to contact NSPI to receive permission to officially enter the distribution interconnection queue. A series of studies...

AI summary After project approval through the One Window Committee, applicants must contact NSPI to enter the interconnection queue. NSPI is streamlining its process for COMFIT, and a standard PPA will be provided for completed projects.

06113Information Requests (IR-1 to IR-8) issued by HRWC to NSPI 1/12/2011 3 passages
Section 4 p. p. 0
of facility requirements before interconnecting."

AI summary The text references the need to meet facility requirements before interconnecting, likely relating to generator interconnection processes and infrastructure planning.

NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 90 (a) For the Class 2 projects, will the process follow the current interconnection process or is 91 NSPI considering other ways to streamline the application process and any system 93 (b) Please explain in detail why app...

AI summary The text discusses the interconnection process for Class 2 projects and the eligibility of certain renewable energy generation methods, such as capturing excess energy from pressure reducing valve chambers and the combustion of biodiesel, for Net Metering. It also references the amended Electricity Act and its provisions on meter aggregation within a distribution zone.

NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 152 feeding the energy produced, or alternatively as long as the Nova Scotia Power System 153 Operator deems it acceptable based on the load on the distribution zone where the 154 generator is located and other factors; an...

AI summary The text outlines criteria for connecting generators to the Nova Scotia Power System, specifying conditions under which a Class 1 or Class 2 generator may be connected based on load conditions and other factors. It also includes contact information for Jeff Larsen of Mcinnes Cooper.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →