22, 2025 filing, the cyberincident impacted the Company's GIS system, which is critical to pole ownership reconciliation and settlement, and consequently delayed finalization of the formal agreement. NS Power confirms that a finalized JUA...
AI summary A cyberincident disrupted NS Power's GIS system, delaying the finalization of a JUA with Bell. NS Power confirms the LOI remains in effect, and the parties continue to operate under its terms. GIS data is expected to be current by Q3 2026, with the first Point of Construction settlement anticipated in Q4 2026. A finalized JUA is unlikely before Q1/Q2 2027. NS Power will comply with the Board's Decision and Order in M12149.