NON-CONFIDENTIAL 1 Response IR-5: 2 3 (a-c) Please refer to Section 3.2.7 in the 2025 10-Year System Outlook for an update on the 4 generation capacity.1 status and timing of the fast-acting 5 6 (d) NS Power has not pursued updates since t...
AI summary NS Power has not updated its generation capacity plans since the project was transferred in September 2024, as outlined in M12012. They are not currently re-evaluating investment between resources for 2030 targets but will do so as part of the next Integrated Resource Plan (IRP) conducted by the NSIESO. Fast-acting generation is highlighted for its firm capacity value in enabling coal unit retirement.