Request IR-4: Refer to M12782, Exhibit N-1(i), the 2025 Report Appendix A, and the two tabs entitled "2025 CNMP Applications" and "2025 CNMP In Progress" and answer the following questions: - a) Please confirm that as of today only one pro...
AI summary Request IR-4 seeks clarification on battery storage projects in NS Power's 2025 CNMP applications, the status of Active Interconnected BES, impacts on DGIP timelines, the meaning of 'Applying Aggregation,' and feeder status relative to past problem feeders. Questions focus on project specifics, procedural impacts, and compliance with infrastructure planning.
Request IR-5: Refer to M12782, Exhibit N-1, the 2025 Report, page 13 of 13 at lines 11 -16, which states: The CNMP estimated contribution to 2025 RES and a RECs status update (i.e. number of opt-ins and annual REC volumes) is provided in A...
AI summary The text references M12782, Exhibit N-1, and the 2025 Report, discussing the exclusion of interconnection requests without CNMP applications, particularly for Class 2 applicants. It raises three questions about program options for Class 2 applicants, the meaning of 'consistent with prior reports,' and the impact of RES and RECs on peak demand and other customer classes.