Matter: CI# 28098 - P-128.07 - NSPI WO -  Authority to Overspend the Tufts Cove 6 Waste Heat Recovery Project - $8,699,864Approximate value for approval of $8.5 million.
2 passages 2 documents

Grid Modernization across all matters →

05797Board Decision 1 passage
Preamble p. p. 0
the Generating Station to residences. In response to Board IR-13b, NSPI explained that a by-pass system was required to eliminate extended use of atmospheric vents during "hot" starts. NSPI said that: - b) ... Minimizing the use of vents i...

AI summary NSPI explained the need for a bypass system to reduce noise from atmospheric vents during hot starts at Tufts Cove Generating Station. Increased automation led to higher costs and changes in plant design, including condenser modifications and larger cooling water pumps. NSPI provided an economic analysis showing a net present value benefit of $2.3 million from automation.

05797Board Decision 1 passage
Preamble p. p. 0
the Generating Station to residences. In response to Board IR-13b, NSPI explained that a by-pass system was required to eliminate extended use of atmospheric vents during "hot" starts. NSPI said that: - b) ... Minimizing the use of vents i...

AI summary NSPI explained the need for a bypass system to reduce noise from atmospheric vents during hot starts at the Generating Station. Increased automation also led to higher costs, but NSPI argued that the economic benefits of automation outweighed these costs, citing a net present value benefit of $2.3 million.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →