Matter: CI# 40425 - P-510 - NSPI WO - Kempt Road Transformer - $1,093,699Zero dollars spent to date
1 passage 1 document

Grid Modernization across all matters →

N-2Responses to Information Requests IR-1 to IR-14 1/27/2011 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-14: 2 3 Please discuss the other alternatives and provide a justification that an immediate purchase 4 of a new transformer is the lowest cost option. 5 6 Response IR-14: 7 8 As provided in the response to IR-...

AI summary NSPI justifies immediate purchase of a spare transformer over constructing underground feeders, citing higher costs for duct banks and feeders. Congestion in Halifax Peninsula and 2010 ACE Plan cost data support the transformer option as lower-cost.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →