HomeGrid ModernizationM11307Evidence
Topic/Matter Intersection

Topic:"Grid Modernization" in M11307

Matter: P-884 - Nova Scotia Power Inc. - 2023 Evergreen  Integrated Resource Plan (IRP) -  Action Plan and Roadmap
74 passages 9 documents

Grid Modernization across all matters →

N-1Evergreen IRP - Update to IRP Action Plan and Roadmap - 2023 3 passages
KEY FINDINGS p. pp. 4-5
KEY FINDINGS Based on the common themes observed, the following are the key guiding principles to inform the Action Plan and Roadmap Items: - Variable renewable capacity additions are required to meet the 2030 targets. Up to 1500MW of addi...

AI summary Key findings emphasize the need for 1500MW additional wind, 200MW solar, and 100-900MW firm capacity by 2030. Battery storage (≥100MW) and the Reliability Tie are critical across scenarios. The Atlantic Loop reduces costs/emissions with government support. Synchronous condensers and SMRs (late 2030s) address system reliability and decarbonization. NS Power updated its 2020 IRP based on 2023 modeling.

Item 2c: Electrification Impacts – Transmission and Distribution System p. pp. 14-15
Item 2c: Electrification Impacts – Transmission and Distribution System Address electrification impacts on the Transmission & Distribution system as additional experience and data become available. This will include an analysis of availabl...

AI summary The document outlines plans to analyze electrification impacts on Nova Scotia's transmission and distribution systems, including T&D capacity assessments, mitigation strategies, and cost estimates. It emphasizes leveraging data from NS Power's AMI implementation as it becomes available.

Item 3g: Synchronous Condensers p. p. 16
Item 3g: Synchronous Condensers Complete generator site-specific system impact studies for new variable renewable generation to assess the need for synchronous condenser support. Progress the development of 100 - 200MVA of synchronous cond...

AI summary The document outlines the need to conduct site-specific system impact studies for new variable renewable generation and to develop 100-200MVA of synchronous condensers by 2030 to ensure grid reliability and stability as renewable energy penetration increases.

N-4Report of John D. Wilson, Grid Strategies LLC and Paul L. Chernick, Resource Insig... 1 passage
2. Overview p. p. 0
2. Overview NS Power's Evergreen IRP represents substanfial forward progress in the ufility's planning acfivifies. Many of the concerns that we had at the conclusion of the 2020 IRP have been addressed in a reasonable manner. The range of...

AI summary NS Power's Evergreen IRP shows progress but delays key projects due to investment limits, risking higher costs. The ACE Plan acknowledges urgency for ECEI projects by 2030, yet they're excluded from 5-year capital forecasts. Grid-enhancing technologies and dynamic line ratings are deferred, while economic dispatch software is slated for 2024–2025 to support clean energy transition.

N-5Reply Submission - NSPI 1 passage
will be released to stakeholders for their review and NS Power will request feedback on the findings. p. p. 11
will be released to stakeholders for their review and NS Power will request feedback on the findings. will be evaluated by further study work (Updated Ac�on Plan page 7), including generator site– specific system impact studies for new var...

AI summary The document discusses the need for further study on the impact of adding synchronous condensers to the grid, particularly in relation to new variable renewable generation. It highlights the potential costs and system-wide benefits of synchronous condensers and suggests a more comprehensive, system-wide review rather than a generator site-specific approach.

N-6Refiled Reply Submission Appendix A - NSPI 2 passages
The study should also ask whether energy to meet those peak demands should be stored in a batery, a tank, a lake or in a regionally linked, diversified e
that correctly iden�fying the need for capacity is paramount for all subsequent IRP runs. The study should also ask whether energy to meet those peak demands should be stored in a batery, a tank, a lake or in a regionally linked, diversifi...

AI summary The text emphasizes the importance of correctly identifying capacity needs for Integrated Resource Plan (IRP) runs. It also discusses the need to evaluate energy storage options for meeting peak demands and how customer behavior may shift with increasing carbon prices and heat pump adoption. NS Power's Smart Grid Nova Scotia (SGNS) Project is highlighted as progressing toward providing a final report to the NSUARB by year-end 2023.

will be released to stakeholders for their review and NS Power will request feedback on the findings.
will be released to stakeholders for their review and NS Power will request feedback on the findings. will be evaluated by further study work (Updated Ac�on Plan page 7), including generator site– specific system impact studies for new var...

AI summary The document discusses the need for further study on the impact of adding synchronous condensers to the grid, emphasizing the importance of a comprehensive and system-wide approach rather than a generator site-specific evaluation, as more renewable energy sources are integrated into the system.

N-7Wind Integration Study 48 passages
Large Scale Integration of Inverter Based Resources in Nova Scotia p. p. 0
Large Scale Integration of Inverter Based Resources in Nova Scotia Frequency Control and System Strength Assessment Initial Findings and Recommendations Report Number: 083-2023-TSMG October 23, 2023 Manitoba Hydro International Ltd. Nova S...

AI summary This report, titled 'Large Scale Integration of Inverter Based Resources in Nova Scotia,' focuses on assessing frequency control and system strength for integrating inverter-based resources into the grid. It is authored by Manitoba Hydro International Ltd. and Nova Scotia Power Inc., highlighting technical and operational considerations for grid reliability.

Executive Summary p. pp. 0-2
Executive Summary Nova Scotia is on a path to build a cleaner, greener future for the province, phasing out coal and working towards 80% renewable energy by 2030. Inverter-based generation will displace conventional synchronous machine-bas...

AI summary Nova Scotia aims for 80% renewable energy by 2030, transitioning from coal and conventional generation to inverter-based systems. This shift requires addressing technical challenges through system studies, including EMT analyses. Initial findings were released due to delays in plant models, with an updated report pending. Mitigation measures are emphasized to ensure grid reliability.

Primary Finding p. p. 2
Primary Finding NSPI can incorporate renewables, in particular inverter-based resources (IBRs) such as wind, limited only by the load to be served and the best economic dispatch to meet environmental requirements. There will be technical c...

AI summary NSPI can integrate renewable energy, particularly inverter-based resources like wind, constrained by load demands and economic dispatch. Technical challenges and grid support are necessary as legacy thermal plants phase out. The conclusion is that this integration is achievable with current and evolving technologies.

Recommendations p. p. 2
Recommendations Stable and Reliable Integration of Renewables - Verify network response for high Rate of Frequency (RoCoF) system disturbances through EMT simulations. Based on study to date, there are significant concerns for the ability...

AI summary The recommendations focus on ensuring stable integration of renewables by addressing RoCoF risks, upgrading grid interconnection standards, and conducting detailed studies. Concerns include existing RoCoF limits potentially causing cascade tripping, the need for IEEE 1547-2018 alignment, and MHI's proposals for grid study updates. NSPI is urged to review system guidelines and perform incremental studies for each generation/load wave.

Good Planning Practices to Integrate Renewables in Nova Scotia p. p. 2
Good Planning Practices to Integrate Renewables in Nova Scotia • Perform an annual assessment of NSPI System Inertia and Strength in the 10-year horizon to identify potential issues. See Section [2.2.](#page-18-0) Include FOR and planned m...

AI summary The document outlines planning practices for integrating renewables in Nova Scotia, emphasizing annual system inertia assessments, model requirements for grid connections, system studies for western Nova Scotia's load and hydro generation, and maintaining SCMVA levels to ensure grid reliability.

System Operator Support to Transition to High IBR Grid p. p. 2
System Operator Support to Transition to High IBR Grid - Develop a methodology to estimate the minimum SCMVA and SCR online prior to the addition of additional IBR (WEC, BESS, HVDC etc.) to the NSPI grid. - Develop a methodology to estimat...

AI summary The document outlines the need to develop methodologies for estimating SCMVA, SCR, and inertia online to ensure grid stability before integrating additional IBR (e.g., WEC, BESS, HVDC) into the NSPI grid. It also emphasizes updating operating guidelines and conducting EMT studies to address fault ride-through, control interactions, and system oscillations from expanded IBR interconnections.

Acronyms p. pp. 6-8
Acronyms Acronym Term 7.2.2 Resource Planning for High IBR Penetration 44 7.2.3 Good Planning Practice 45 7.2.4 System Operator Transition to High IBR Grid 45 7.2.5 Black Start Restoration Planning 46 8 Refere ences 47 Appendix A: SCMVA Be...

AI summary The text outlines sections related to resource planning for high IBR penetration, good planning practices, system operator transition to high IBR grid, black start restoration planning, and references. It also mentions an appendix with SCMVA benchmark values.

List of Tables and Figures p. pp. 8-9
List of Tables and Figures Table 1: Minimum Inertia for Frequency Control, First Iteration15 Table 2: Minimum Inertia and FFR Required for Frequency Control 17 Table 3: Most Severe RoCoF, 2023 Grid18 Table 4: First Iteration for 2030 RoCoF...

AI summary The document provides a list of tables and figures related to frequency control, inertia requirements, and grid stability, including tables on minimum inertia, FFR support, and RoCoF, as well as figures illustrating voltage waveforms, simulation results, and frequency response. The introduction section is referenced but not detailed in this chunk.

1.1 Background p. p. 9
1.1 Background Most power systems in North America, Europe, Australia, and the Middle East have seen increased penetration of renewable energy-based generation of from 10% to 30% over the past decade. In 2021, close to 30% of NSPI electric...

AI summary The document discusses the increasing penetration of renewable energy, particularly inverter-based generation, and its technical challenges on power systems. NSPI aims for 80% renewable electricity by 2030, but this may reduce system inertia, short circuit levels, and cause instability issues like fault recovery and torsional oscillations, requiring mitigation measures.

1.1.2 System Strength p. p. 10
eactive power sources) may have to be installed to support the voltage in local regions as there are some challenges with using numerous IBR units to mange System Strength. In addition to IBR support, - IBRs are designed to operate to at m...

AI summary The text discusses challenges with integrating Inverter-Based Resources (IBRs) into the Nova Scotia Power Inc. (NSPI) grid, including risks of low Short Circuit Ratio (SCR), protection relay failures due to reduced fault current, voltage instability from multiple IBR interactions, and difficulties in maintaining voltage levels with weak grid conditions. These issues highlight the need for reactive power support and grid strengthening measures.

1.2.2 System Strength p. p. 14
1.2.2 System Strength - Perform a screening level assessment to benchmark 2023 SCMVA levels at 69, 138 and 230 KV buses. - Document minimum SCMVA at load sensitive locations. - Document minimum SCR at all Wind Plants, SVC and HVDC location...

AI summary The document outlines a system strength assessment for Nova Scotia's grid, focusing on benchmarking SCMVA/SCR levels, identifying IBR connection issues, and recommending support measures like BESS or synchronous condensers to maintain reliability by 2030. Initial findings are published ahead of full EMT study results.

2 Assessment Metrics and Methodologies p. pp. 14-16
2 Assessment Metrics and Methodologies The metrics and methodologies described below are utilized for this study. The assessment is looking at 2030 and aims to identify any deficiencies in frequency and voltage control due to the changing...

AI summary The study assesses 2030 system challenges in frequency and voltage control due to evolving generation fleets, applying Nova Scotia UARB standards. Traditional methods like load flow and short circuit analysis are combined with new methodologies for IBR integration.

2.2 System Strength p. p. 18
or poorly damped oscillations due to interaction with other plants near by. - Inability to operate to Grid Code requirements (fast power recovery following faults). - Difficult to control bus voltage. Accordingly, points of interconnection...

AI summary The text discusses challenges with weak grid connections (SCR <3), requiring detailed EMT studies to ensure fault recovery, voltage stability, and control interactions. Low inertia from IBR generation impacts voltage angle dynamics and PE device fault ride-through. System planning must address protection system performance under reduced fault currents and inertia distribution.

2.3 Iterative Assessment p. pp. 18-21
2.3 Iterative Assessment The initial assessment and metrics used for these studies follow the traditional load flow and dynamics methodologies with the intent to then take critical cases into PSCADTM for EMT analysis. Upon examination of t...

AI summary The text discusses an iterative assessment process for grid stability, focusing on the challenges of maintaining system inertia and frequency response with the integration of inverter-based resources (IBR). It highlights the need to decouple frequency control requirements from system strength requirements and outlines a multi-step approach to ensure system reliability.

3.1 Frequency Excursion Damping p. p. 23
3.1 Frequency Excursion Damping Boundary cases for light load and peak load for the 2030 load conditions, with maximum renewables online, were run. Simulations were run iteratively to get the online synchronous generation dispatched to the...

AI summary Simulations were conducted to assess frequency excursion damping under light and peak load conditions for 2030, with maximum renewable energy online. Cases were iteratively evaluated, and ten cases met basic criteria for further assessment, focusing on grid requirements for frequency control.

Table 1: Minimum Inertia for Frequency Control, First Iteration p. p. 23
Table 1: Minimum Inertia for Frequency Control, First Iteration Case Dispatch Thermal Units or Equivalent Dispatch Notes 1 Light Load 4 TUP, TR6, TUC2 & ML, Biomass / existing wind 2 Light Load 3 TUP, TR6 & TUC2/ existing wind 3 Light Load...

AI summary The table presents different cases for minimum inertia requirements in frequency control under various load conditions, including light load and winter peak scenarios, with varying combinations of thermal units, renewable energy sources, and energy storage systems.

Section 44 p. p. 23
- The light load cases were run with 6 variations. In light load, NSPI has sufficient wind and imports to serve load with 100% renewable energy. Hydro resources are offline. Variations of FFR and inertia were simulated with the goal of tak...

AI summary The text discusses simulations of light load and winter peak scenarios in Nova Scotia's power system, analyzing the use of wind, hydro, and battery energy storage systems (BESS) for stability and inertia. It also examines the impact of losing the New Brunswick tieline with high Nova Scotia imports.

Section 45 p. p. 23
o meet the load, while reducing the thermal units, new wind and BESS was added to the simulation cases. Load Flow and Dynamic assessment was performed for the loss of NB tieline with high NS imports. Case 5, with a low amount of inertia on...

AI summary The document discusses grid simulations analyzing the impact of reducing thermal units and adding renewable resources like wind and BESS. It highlights voltage issues under winter peak load conditions and the potential of FFR from IBRs to reduce reliance on synchronous resources for frequency control in the 2030 grid.

3.2 RoCoF p. pp. 25-26
3.2 RoCoF Historically, there have been RoCoF requirements for generation facilities and some protection devices to ensure they function as expected during frequency swings. The requirements are as needed to stay online for a grid with goo...

AI summary The document discusses the Rate of Change of Frequency (RoCoF) requirements for the Nova Scotia Power Inc. (NSPI) grid, analyzing how changes in grid inertia due to the phasing out of synchronous generation and the increase of renewable generation affect RoCoF. Simulations show varying RoCoF values under different load and generation scenarios, with a 500ms sample time used for calculations.

4 System Strength Assessment in PSS®E p. pp. 28-29
4 System Strength Assessment in PSS®E A minimum level of System Strength is required for the power system to remain stable during system disturbances. A minimum level is also required for inverter-based facilities to stay online during sys...

AI summary The document discusses the importance of system strength in maintaining power system stability during disturbances and the testing conducted on the NSPI grid using a full contingency set based on 2020 IRP studies. Six cases were analyzed for system strength under different load conditions.

4.4 System Support Requirements p. p. 30
4.4 System Support Requirements System Strength requirements will be driven by the need to support existing facilities as the grid transitions to high renewables as well as to strengthen the grid to support the addition of significant quan...

AI summary System strength requirements are necessary to support existing grid facilities during the transition to high renewable energy integration and to strengthen the grid for the addition of significant Inverter-Based Resources (IBR) to meet Nova Scotia Power Inc. (NSPI), provincial, and federal targets.

4.4.2 SCMVA for Sensitive Buses p. p. 30
4.4.2 SCMVA for Sensitive Buses With all contingencies solving well for the 6 cases, a comparative look at the SCMVA for sensitive buses was run. See [Appendix B: Sensitive SCMVA Buses](#page-58-0) for the tables of values. As can be seen...

AI summary The analysis examines the Short Circuit MVA (SCMVA) for sensitive buses under different generation dispatch scenarios. It highlights the need for inertia support, particularly with a second 345kV tieline to New Brunswick, and notes that synchronous condensers are currently the preferred mechanism for grid support.

4.4.5 Stability Requirement p. p. 32
4.4.5 Stability Requirement When sufficient inertia, FFR and reactive support was added to meet criteria (Frequency, Voltage, and RoCoF, SCMVA etc) as defined in this report there were no observed stability issues in PSS®E. Stability and C...

AI summary The document discusses the stability requirements for the power system, noting that sufficient inertia, fast frequency response (FFR), and reactive support were added to meet defined criteria. Stability and control interactions are best observed in EMT simulations and require further analysis in PSCADTM.

5 Frequency Control and System Strength Assessment in PSCADTM p. pp. 32-33
5 Frequency Control and System Strength Assessment in PSCADTM First Stage studies, RMS analysis in PSS®E, have been completed as detailed in the sections above. Stage Two focused on EMT analysis in PSCAD are ongoing. As there are significa...

AI summary First Stage studies using RMS analysis in PSS®E have been completed, with significant findings reported. Stage Two, focusing on EMT analysis in PSCAD, is ongoing, and an updated report will be issued upon completion.

5.1 EMT Analysis Methodology p. pp. 33-35
5.1 EMT Analysis Methodology NSPI, in collaboration with MHI, is in the process of developing the full NSPI network (including portions of neighbouring areas) in PSCADTM. The EMT model includes transmission details including 69 kV level an...

AI summary NSPI, in collaboration with MHI, is developing a detailed EMT model of the NSPI network in PSCADTM to analyze system behavior under various conditions. The model includes transmission and distribution levels and is used to study the impact of faults and IBR performance. Results are illustrative and do not reflect actual NSPI system responses.

5.2 EMT Models p. p. 35
5.2 EMT Models NSPI requires that all new interconnection customers provide accurate, site-specific models of their plant in PSCADTM format. In addition to the PSCADTM model, a corresponding PSS®E model that is benchmarked for performance...

AI summary NSPI requires accurate PSCADTM and PSS®E models from interconnection customers for system planning. However, obtaining accurate PSCADTM models remains challenging. MHI recommends that NSPI establish clear model requirements and validation processes to ensure model accuracy and performance.

5.3 Detailed PSCADTM Simulation p. pp. 35-36
5.3 Detailed PSCADTM Simulation Detailed PSCADTM simulations are used to identify stability and fault ride though concerns and further assess potential RoCoF concerns. EMT simulations have become critical when integrating PE inverter-based...

AI summary Detailed PSCADTM simulations are used to assess stability, fault ride-through, and RoCoF concerns when integrating inverter-based resources (IBR) into AC networks. Traditional RMS simulations may miss critical design considerations, and EMT simulations are essential for identifying system challenges. Increasing short circuit levels and using synchronous support are recommended solutions, though new transmission may not be economically viable. Future NSPI grid analysis will explore IBR controls for system inertia and strength.

SSTI due to interaction with power electronic converters: p. p. 40
SSTI due to interaction with power electronic converters: Power electronic converters and their controls can interact with the natural modes of generator shafts and give rise to poorly damped mechanical shaft oscillations. A main objective...

AI summary This section discusses the potential for Sub-synchronous Torsional Interaction (SSTI) caused by the interaction between power electronic converters and generator shafts, leading to poorly damped mechanical oscillations. The focus is on investigating these impacts through Electromagnetic Transient (EMT) studies, particularly in proximity to generating stations and transmission systems.

Torsional interactions due to network resonance conditions: p. p. 40
Torsional interactions due to network resonance conditions: In addition to SSTI due to interactions with power electronic converters, transient torque magnitude and damping can be negatively affected when series compensated transmission ar...

AI summary The text discusses how torsional interactions can occur due to network resonance conditions, particularly when series compensated transmission lines are near generators. These interactions can cause unstable resonant conditions that affect thermal generators and their mechanical systems, especially when the natural frequency of the mechanical system aligns with the complement of sub-synchronous network resonant frequencies.

5.4.5 IBR Low Frequency Oscillations p. p. 40
5.4.5 IBR Low Frequency Oscillations According to field results and detailed simulation-based studies, the operation of many inverter-based devices in a weak network area can result in sustained low-frequency oscillations. The oscillation...

AI summary The document discusses the potential for low-frequency oscillations (8 Hz – 12 Hz) caused by inverter-based resources (IBRs) in weak network areas, a concern first observed in Australia around 2019. These oscillations, though small and stable, may cause visible flicker. Solutions such as SVC and STATCOM are suggested for system strength issues.

5.4.7 Motor Starting p. pp. 41-42
5.4.7 Motor Starting Industrial motor starting has been a critical consideration of the NSPI power system planning process. With the expected penetration of IBR, EMT study-based verification may be required in specific situations. Data has...

AI summary Industrial motor starting is a key consideration in NSPI's power system planning, especially with the increasing use of IBR. EMT studies may be needed to assess potential adverse impacts on motor starting capabilities, and data from large manufacturing plants in Nova Scotia is being used to develop plant models for this purpose.

5.4.8 Transformer Inrush p. p. 42
5.4.8 Transformer Inrush NERC technical report: "Integrating Inverter Based Resources into Low Short Circuit Strength Systems" [9] raises concerns for the energization of transformers in a weak grid. Transformer inrush current initial peak...

AI summary The NERC technical report highlights concerns about transformer inrush currents in weak grid systems, noting that these currents can cause voltage dips that may affect nearby power electronic plants, potentially leading to tripping if voltage dip limits are exceeded.

6 Potential Mitigation Options p. pp. 42-43
6 Potential Mitigation Options Technology to support the integration of renewable energy sources is evolving quickly, in particular for IBR sites with PE controls. The following are mitigations under consideration to resolve issues identif...

AI summary The document outlines potential mitigation options for integrating renewable energy sources, particularly focusing on technologies related to inverter-based resources (IBR) with power electronic (PE) controls. Some technologies are well-established, while others are emerging and their effectiveness is yet to be determined.

6.1.1 Mechanical Inertia from WECs p. p. 43
6.1.1 Mechanical Inertia from WECs Recent development in WEC turbines allow for the short-term extraction of mechanical inertia in wind turbine generators. IBR control design can support the fast delivery of this mechanical inertia to the...

AI summary Recent advancements in wind energy conversion (WEC) turbines allow for the short-term extraction of mechanical inertia, which can be delivered to the grid through IBR control design. New WECs are required to provide frequency support to the NSPI grid, potentially including mechanical inertia from the turbine.

6.1.2 Grid Following and Grid Forming Inverters p. p. 43
energy supplied across a HVDC link) [19, 20]. Grid-forming controllers have the potential to replace grid following controllers to augment the lower amount of available SIR in a high renewables grid. There is significant research and in se...

AI summary The text discusses the potential of grid-forming inverters to replace grid-following inverters in high renewables grids, highlighting research and in-service projects supporting the advancement of inverter-based resource (IBR) control systems.

6.6 Transmission Connections p. pp. 45-46
6.6 Transmission Connections New transmission paths will generally strengthen a power system. The more the ties between areas of a power system the stronger the ability of the system to withstand grid events. For Nova Scotia, additional tr...

AI summary New transmission connections can enhance power system resilience by reducing RoCoF and increasing SCMVA near tie line termini. Two areas in Nova Scotia are identified as having potential to improve grid stability and support IBR resources under various system conditions.

6.7 Operating Guidelines p. p. 46
6.7 Operating Guidelines It is important to consider credible operating conditions when identifying potential issues and corresponding additional investments to strengthen the system. As an example, curtailing a portion of wind output duri...

AI summary The text discusses the importance of considering credible operating conditions when identifying system issues and potential investments. It suggests that curtailing wind output during outlier conditions may be more cost-effective than building a more robust system. It also notes that curtailed wind farms can be used for AGC control and provide FFR to the grid.

7.1 Findings p. p. 47
7.1 Findings NSPI can incorporate renewables, in particular IBR resources, limited only by the load to be served and the best economic dispatch to meet target metrics for renewables. There will be technical challenges and the grid will nee...

AI summary NSPI can integrate renewable energy sources, particularly inverter-based resources, up to the limits of load demand and economic dispatch. However, technical challenges and grid support requirements will increase as legacy plants are phased out or converted to alternate fuels, though the transition is deemed achievable with current and emerging technologies.

7.1.2 Minimum System Inertia and FFR p. pp. 47-48
7.1.2 Minimum System Inertia and FFR The PSC study [23] performed for NSPI in 2019 documented the following: - A minimum of 3266 MW.sec of synchronous inertia will be required for steady state operation. - o Synchronous condensers generall...

AI summary The document discusses the minimum system inertia and Fast Frequency Response (FFR) requirements for Nova Scotia Power Inc. (NSPI), noting that a minimum of 3266 MW.sec of synchronous inertia is required for stable operation. It highlights various sources of inertia and FFR, including thermal units, hydro plants, biomass facilities, and the Maritime Link. The approach to maintaining inertia is based on RoCoF limits and current operating guidelines.

7.1.3 EMT Model Quality p. pp. 49-50
7.1.3 EMT Model Quality IBR control systems and operating modes are evolving rapidly and have the potential to strengthen the grid and support a 100% renewable energy dispatch in Nova Scotia. Detailed analysis of options may provide more t...

AI summary The document emphasizes the importance of high-quality EMT models for IBR control systems to support grid reliability and renewable energy integration in Nova Scotia. Current vendor models lack robustness in large simulations and may not align with actual equipment, hindering effective analysis and solution development.

7.1.4 Operability p. p. 50
7.1.4 Operability As the grid moves to higher penetration of IBR, reduced SCMVA that occurs due to forced outages and planned maintenance will need an assessment for SCMVA and IBR stability. This may be in the form of updated guidelines or...

AI summary As the grid integrates more IBR, reduced SCMVA from forced outages and maintenance requires assessment for stability. This may involve updated guidelines or real-time studies, with increased need for real-time data visibility for inertia and SCMVA at critical buses for Transmission Operations staff.

• Protection and Control p. p. 50
• Protection and Control The expected short circuit levels, considering fault current contribution from IBR as well as without a contribution from IBR is noted in the above. This information and EMT study results should be reviewed by prot...

AI summary The document discusses the impact of Inverter-Based Resources (IBR) on short circuit levels and relay performance, emphasizing the need for protection engineers to review EMT study results and assess negative sequence current contributions from generation sources.

• Transformation p. p. 50
• Transformation Inrush issues may arise as noted in Section [5.4.8](#page-42-1) and will be evaluated on a case-by-case basis as new plants and equipment are connected to the grid.

AI summary The document notes that inrush issues may occur when new plants and equipment are connected to the grid, as outlined in Section 5.4.8, and these issues will be assessed individually.

7.2.1 Stable and Reliable Integration p. p. 51
7.2.1 Stable and Reliable Integration Recommendations to facilitate the integration of renewables on the timelines in place for Nova Scotia: - Based on study to date, there are significant concerns for the ability of the existing and futur...

AI summary The document outlines recommendations to ensure stable and reliable integration of renewable energy sources into Nova Scotia's grid. Key concerns include managing high RoCoF events, updating interconnection requirements, and addressing grid support needs as synchronous plants retire. Studies and system upgrades are recommended to mitigate risks of cascading tripping and maintain grid reliability.

7.2.2 Resource Planning for High IBR Penetration p. pp. 51-52
7.2.2 Resource Planning for High IBR Penetration Recommendations to facilitate current and future economic generation dispatch for increased renewables on the timelines in place for Nova Scotia: - Update IBR and inertia constraints for Ple...

AI summary The document discusses resource planning for high Inverter-Based Resources (IBR) penetration in Nova Scotia, emphasizing the need to update models, incorporate frequency response, and maintain system strength through inertia or Frequency Response (FFR) as key metrics for stable grid operation.

7.2.3 Good Planning Practice p. pp. 52-53
7.2.3 Good Planning Practice Recommendations to implement good planning practices to the integration of renewables in Nova Scotia: - MHI recommends performing an annual assessment of NSPI System Inertia and Strength requirements in the 10-...

AI summary The text outlines recommendations for good planning practices in integrating renewables into Nova Scotia's grid, including annual assessments of system inertia, updated model requirements for load and generation, system studies for load growth and hydro availability, and maintaining SCMVA levels.

7.2.4 System Operator Transition to High IBR Grid p. p. 53
7.2.4 System Operator Transition to High IBR Grid Recommendations to support the System Operator transition to a grid with high IBR online. - Develop a methodology to estimate the minimum SCMVA and SCR online prior to the addition of addit...

AI summary The text outlines recommendations for the System Operator's transition to a grid with high Inverter-Based Resources (IBR). It suggests developing methodologies to estimate minimum Short Circuit MVA (SCMVA) and inertia, as well as reviewing and updating operating guidelines for the NSPI grid ahead of the next round of Transmission connected IBR integration.

8 References p. pp. 54-58
8 References - [1] "Fast Frequency Response Concepts and Bulk Power System Reliability Needs", NERC Inverter-Based Resource Performance Task Force, March 2020 - [2] "Experiences with Wind Power Plants with Low SCR", Lessons learned from th...

AI summary The document provides a list of references related to power system reliability, renewable energy integration, and grid management, including studies on inverter-based resources, system strength, and high-voltage direct current (HVDC) systems.

N-8Electrification Strategy Report 5 passages
Short-term Actions, Customer Programs & Capital Investments p. p. 20
- In this instance, E3 does not believe that submetering or installing a second meter for EVs is necessary to support EV adoption in the near-term. These options have generally been costly, and have faced implementation challenges, includi...

AI summary E3 suggests that submetering for EVs is not necessary in the near-term due to cost and implementation challenges. Instead, the focus should be on whole-home rate designs. Nova Scotia Power is piloting opt-in dynamic pricing programs, and AMI is essential for managing loads and enabling TOU rates.

2.2.3 Example Utility Actions p. p. 33
ates include a rate that follows the car with clear managed charging incentives, credits for not charging onpeak, demand charge mitigation, and multi-part rates with a dynamic real-time energy charge. Managed charging has been recognized a...

AI summary The text discusses managed charging strategies for electric vehicles (EVs), emphasizing their importance in reducing peak load impacts. It highlights methods such as time-of-use (TOU) rates, dynamic real-time energy charges, and advanced metering infrastructure (AMI) to optimize EV charging times and costs.

Hourly load forecasts p. pp. 46-47
Hourly load forecasts Load forecasts were developed at an hourly level for a full year for each scenario identified in Section 4. Load forecasts across the entire LDV population are averaged to give a per vehicle profile. [Figure 3-6](#pag...

AI summary The document discusses hourly load forecasts for light-duty vehicles (LDVs) in Nova Scotia, comparing unmanaged and managed charging profiles. Unmanaged charging occurs primarily in the early evening, while managed charging, influenced by Nova Scotia Power's time-of-use (TOU) rates, shifts charging to off-peak hours. These profiles are used in cost-benefit analysis and total load forecasting.

5.1 Key Analysis Findings p. p. 77
5.1 Key Analysis Findings The analysis generated several findings related to electrification in Nova Scotia.

AI summary The analysis generated several findings related to electrification in Nova Scotia, focusing on key areas such as energy efficiency, renewable energy integration, and the impact of electrification on the grid and customers.

Short-term Actions, Customer Programs & Capital Investments p. p. 86
- Drive customer transition: A transition to more dynamic rates requires significant customer outreach and education and should be implemented gradually to ensure customers can adjust their behavior and avoid abrupt bill changes. Pilot pro...

AI summary The text discusses the need for gradual customer transition to dynamic rates through pilot programs and opt-in rate designs, emphasizing the importance of customer education and outreach. It highlights Nova Scotia Power's efforts with TVP and CPP pilots, and the role of AMI in enabling load management and TOU rates, while noting the need for more dynamic strategies as DER adoption increases.

N-9Wind-Integration-Study-Engagement-Session-Material 12 passages
Voltage Control p. pp. 5-7
Voltage Control - Voltage Regulation - o Voltage Ride Through - o Voltage Recovery Failure - SCR and SCMVA Requirements - o Ride Through for IBR facilities, WECS, BESS, HVDC - o Manufacturing plants, motor starting - o Grid Protection Devi...

AI summary The document outlines voltage control requirements, including voltage ride-through and recovery failure considerations, as well as SCR/SCMVA standards for IBR facilities, WECS, BESS, HVDC, manufacturing plants, motor starting, and grid protection devices. Technical diagrams are referenced but not detailed in text.

Transmission System Design and SMEs p. pp. 7-9
Transmission System Design and SMEs - Developing good quality EMT simulations models: - o Faster response to grid disturbances - o Higher frequency oscillatory response - o Work with IC, OEM, Simulation and EMT consultants - Existing Plant...

AI summary The document outlines the development of EMT simulation models to enhance grid response, the modeling of existing and new plant technologies, and the importance of accurate load modeling, including non-traditional loads like EVs and hydrogen.

Iterative Assessment for EMT Studies p. pp. 9-10
Iterative Assessment for EMT Studies FREQUENCY CONTROL ASSESSMENT IN PSS®E SYSTEM STRENGTH ASSESSMENT IN PSS®E TRADITIONAL PSS®E SIMULATION FREQUENCY CONTROL AND SYSTEM STRENGTH ASSESSMENT IN PSCADTM

AI summary The document outlines iterative assessment methods for Electromagnetic Transient (EMT) studies, focusing on frequency control and system strength evaluations using PSS®E and PSCADTM tools. It highlights traditional simulations and assessments specific to power system stability and reliability.

Stage 1, Iterative Assessment p. pp. 10-14
Stage 1, Iterative Assessment FREQUENCY CONTROL ASSESSMENT IN PSS®E SYSTEM STRENGTH ASSESSMENT IN PSS®E TRADITIONAL PSS®E SIMULATION FREQUENCY CONTROL AND SYSTEM STRENGTH ASSESSMENT IN PSCADTM CRITICAL DYNAMIC CONTINGENCY CRITICAL DYNAMIC...

AI summary This section of the document outlines various technical assessments related to frequency control, system strength, and critical dynamic contingencies using simulation tools like PSS®E and PSCADTM. It includes case development and fast frequency response considerations.

p. pp. 14-15
Case Total Inertia (MWs) ML FFR 51 1044 50MW 52 1102 0MW 53 1603 - 101 2381 50MW 102 2381 0MW 103 3158 -

AI summary The document presents a table with case numbers, total inertia in MWs, and ML FFR values, indicating variations in inertia and FFR across different cases. The data appears to relate to power system analysis or grid stability considerations.

Section 10 p. pp. 15-16
CRITICAL DYNAMIC CONTINGENCY CASE DEVELOPMENT FAST FREQUENCY RESPONSE RATE OF CHANGE OF FREQUENCY

AI summary The text highlights critical dynamic contingency, fast frequency response, and the rate of change of frequency, which are key aspects of grid stability and emergency response in power systems.

p. pp. 16-18
Case Total Inertia (MWs) ML FFR RoCoF (Hz/s) 51 1044 50MW 2.65 52 1102 0MW 3.31 53 1603 - 2.32 101 2381 50MW 3.10 102 2381 0MW 3.27 103 3158 - 2.48 Case Total Inertia (MWs) ML FFR RoCoF (Hz/s) 511 1565 50MW 1.91 521 1890 0MW 2.09 531 2586...

AI summary The text presents tables with case numbers, total inertia (MWs), ML FFR, and RoCoF (Hz/s) values. These tables likely relate to technical analyses of power system stability and performance under different scenarios.

System Strength Assessment in PSS®E p. pp. 20-21
System Strength Assessment in PSS®E EXISTING FAULT LEVEL ASSESSMENT MINIMUM SCMVA FOR SENSITIVE FACILITIES MINIMUM SCR FOR EXISTING WIND PLANTS

AI summary The document outlines a System Strength Assessment in PSS®E, focusing on existing fault level assessments, minimum short-circuit MVA (SCMVA) requirements for sensitive facilities, and minimum short-circuit ratio (SCR) standards for existing wind plants. Technical parameters are emphasized for grid reliability and stability.

Stage 2, Iterative Assessment p. pp. 22-24
Stage 2, Iterative Assessment FREQUENCY CONTROL ASSESSMENT IN PSS®E SYSTEM STRENGTH ASSESSMENT IN PSS®E TRADITIONAL PSS®E SIMULATION FREQUENCY CONTROL AND SYSTEM STRENGTH ASSESSMENT IN PSCADTM

AI summary The document outlines simulations in PSS®E and PSCADTM for frequency control and system strength assessments, focusing on grid stability and reliability during iterative regulatory evaluations. Technical analyses are emphasized without explicit stakeholder claims or regulatory references.

General Findings p. pp. 32-33
General Findings - IBR for Frequency Support Grid Following Limits - IBR for System Strength - Minimum Inertia and FFR - o Non traditional sources can reduce the need for synchronous support - o A sliding load/IBR generation online scale w...

AI summary The document discusses technical aspects of inverter-based resources (IBR) for frequency support and system strength, the development of a sliding load/IBR generation scale, EMT model quality, and operability considerations including dispatch guidelines, inertia, and uncontrolled distributed energy resources (DER).

Recommendations p. pp. 33-34
Recommendations - Stable and Reliable Operation - o RoCoF review for existing plant - o TSIR and DSIR revision for high IBR - o Studies for each wave of change, IBR, plant retirements, load growth - Resource Planning, Update IBR and Inerti...

AI summary The document outlines recommendations for ensuring grid stability with high Inverter-Based Resources (IBR), including RoCoF reviews, system strength assessments, inertia constraint updates, real-time operational tools, and black start protocols for dual grids. It emphasizes planning practices for load growth and IBR integration.

Next Steps p. pp. 34-36
Next Steps - Stage 2 Studies Ongoing - o Current focus is Interconnection Requests - o Ongoing studies - o Control Integrations - Generation and Load Models - Protection and Control - Operating Philosophy - Equipment Specification - Harmon...

AI summary The document outlines ongoing Stage 2 studies focusing on interconnection requests, control integrations, and technical aspects including generation and load models, protection and control systems, operating philosophy, equipment specifications, and harmonics analysis. These activities are part of broader grid modernization and infrastructure planning efforts.

N-10Electrification-Strategy-Report-Engagement-Session-Material 1 passage
Key Findings p. pp. 2-4
with E1 and the DSMAG on electrification initiatives and DR pilot projects to promote electrification under the current DSM Supply Agreement and the 2026 to 2030 DSM Plan. - Support development of infrastructure "backbone" for electric veh...

AI summary NS Power is collaborating with E1 and the DSMAG to advance electrification initiatives and DR pilots under the DSM Supply Agreement and 2026-2030 DSM Plan. Key actions include expanding EV charging infrastructure, modernizing the grid, and integrating electrification findings into planning models using the E3 report.

91371Submission - E1 1 passage
15 Action Plan Item 1b: Regional Integration p. p. 15
- firming of energy import and export assumptions. They recommended NS Power re-run the analysis of the Atlantic Loop as more information becomes available. - Synapse recommended that the development of the Reliability Tie continues to be...

AI summary Synapse recommends NS Power re-analyze the Atlantic Loop, prioritize the Reliability Tie, develop solar/wind procurement strategies, and address curtailment. They support electrification planning and 4-hour battery storage by 2030. E1 agrees with Synapse's recommendations for IRP implementation and action plan items.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →