1 Request IR-1:
NON-CONFIDENTIAL 1 Request IR-1: 2 3 Page 1 of the application explains the project will include installing new instrumentation, 4 replace the Programmable Logic Controllers (PLCs), network infrastructure and transfer 5 data to the NS Powe...
AI summary The document outlines a request for information regarding the replacement of Programmable Logic Controllers (PLCs) and related infrastructure at Avon 2 Hydro Station. The response indicates that new technology will be used, aligning with systems at other NS Power plants for standardization and operational flexibility.