N-1Application - Redacted
42 passages
1 2 In preparing its capital plans, NS Power utilizes its established asset management approach, and 3 considers safety, reliability, climate change adaptation, and affordability, while incorporating the 4 Company’s decarbonization targets...
AI summary NS Power uses an asset management approach to prepare capital plans, focusing on reliability, resiliency, and affordability. The 2026 ACE Plan includes investments in reliability-focused improvements to the T&D system, addressing challenges from severe weather events through vegetation management, storm hardening, and grid modernization.
bility. These targeted reliability projects include vegetation 26 management, storm hardening and reliability upgrades, targeted device replacements, and 27 grid modernization. 28 Date: December 12, 2025 Page 8 of 782 REDACTED REDACTED (CO...
AI summary The 2026 ACE Plan focuses on safety compliance, environmental compliance, and aligning with the coal phase-out and renewable energy goals. It includes projects such as hydro dam safety upgrades, PCB remediation, and grid modernization, and addresses directives from the 2025 ACE Plan Decision.
1 5. The Board directs NS Power to provide an update on the Centre for Energy Advancement 2 through Technological Innovation (CEATI) Grid Resiliency working group in the 2026 3 ACE Plan. 6 Please refer to Section 11.1.4. 4 6. The Board dir...
AI summary The Board has directed NS Power to provide updates and analyses related to several projects and plans, including the Centre for Energy Advancement through Technological Innovation (CEATI) Grid Resiliency working group, pole upgrades, The Path to 2030, and the Mersey Hydro System Redevelopment Project, as part of the 2026 ACE Plan.
CI# Project Title 2026 Budget ($) Project Total ($) General Plant C0082133 IT - Renew Microsoft Enterprise Agreement 1,800,000 1,800,000 This project funds the on-premises portion of the Microsoft Enterprise Agreement for software assuranc...
AI summary The document outlines several IT and infrastructure projects planned for 2026, including the renewal of Microsoft Enterprise Agreement, implementation of distributed intelligence apps, a DERMS solution, and improvements to the Sydney Depot. Each project includes budget allocations and total project costs.
eliver and manage data integrations in a more timely and cost effective manner. C0047278 IT - Oracle MDM Upgrade 4,684,089 7,949,409 The Meter Data Management (MDM) System is nearing end-of-life and requires an upgrade to maintain vendor s...
AI summary The text discusses the need to upgrade the Meter Data Management (MDM) System and the Advanced Distribution Management System (ADMS) to ensure vendor support, cybersecurity, and compatibility with emerging technologies. These upgrades are part of the 2026 ACE Plan and involve significant financial investments.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 9.0 GENERAL PLANT 2 3 General Plant includes information technology (IT), operational technology (OT), computer 4 infrastructure, vehicle replaceme...
AI summary The 2026 Annual Capital Expenditure (ACE) Plan outlines General Plant investments, which include IT, OT, infrastructure, and communication equipment. These investments support NS Power’s digital transformation, regulatory compliance, and operational resilience, aligning with strategic initiatives like grid modernization and cybersecurity.
1 Details regarding the execution of year one of the Five-Year Reliability Plan and anticipated 2 activities in year two can be found in Appendix G. 3 4 The combined benefits of these programs and the positive impacts on the reliability of...
AI summary The document discusses the execution of the Five-Year Reliability Plan, including benefits and anticipated activities. It also outlines the establishment and progress of the CEATI Grid Resiliency Working Group, including survey development, terms of reference, and planning for a resiliency workshop.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data including scope, capacity, location, requirements, technology selection, strategy, and planning for a project. It details the defined and preliminary status of various aspects such as site infrastructure, voltage, environmental monitoring, and logistics planning.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data, including scope, capacity, location, requirements, technology selection, strategy, and planning for a project. Key details cover infrastructure, voltage, environmental monitoring, right-of-way, and logistics planning, with various sections defined or not applicable.
o Section 11.2 of the CEJC, related CIs for General Plant projects include “Work completed on the same asset (application, building, etc.).” • No other projects in 2024, 2025, 2026, 2027, or 2028 Depreciation Class: General Plant - Communi...
AI summary This text discusses a project to deploy RTUs as part of the Advanced Grid Modernization program, aimed at improving real-time visibility and remote operability, reducing SAIDI, and enhancing grid resilience. The project aligns with NS Power’s Five-Year Reliability Plan and contributes to improved outage response and system performance.
functionality and reducing time to restore through access to remote operations. Overall, this contributes to sustaining improvements achieved in customer reliability on NS Power’s distribution system. During severe weather events and other...
AI summary NS Power is implementing a project to improve system visibility and enable remote control of switching operations, enhancing reliability and response during severe weather events. This contributes to more efficient operations and faster restoration of services.
the work is completed (January 2026); therefore, the Final Cost Date (June 2027) is listed as six months after the last portion of the work is forecast to be completed). Why do this project this way? This project establishes an effective w...
AI summary The project aims to improve data intelligence on distribution assets using technology and machine learning automation, replacing manual and outdated methods. It is fully funded by the federal government except for administrative overheads and is classified as a Class 1 estimate with a 2% contingency applied for unforeseen issues.
2026 ACE Plan Appendix D Page 65 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Summary Document Telecontrol and telecommunica ons are essen al for the protec on and control of the Bulk Power Syste...
AI summary Nova Scotia Power Inc. justifies capital expenditures on telecontrol/telecommunications systems for Bulk Power System reliability, compliance with NPCC/NERC standards, and IT investments under technical, economic, and customer experience criteria. These technologies enable system protection, remote monitoring, and alignment with evolving customer needs.
1 6.2.3 Grid Stability & Renewable Integration Resources 2 3 Transitioning from a traditional power system which is largely made up of synchronous generators 4 to a power system which will rely heavily on inverter-based resources (IBRs) su...
AI summary Transitioning to inverter-based resources (IBRs) like wind and solar requires grid stability measures such as synchronous condensers and FACTS devices. NS Power, following DOE directives, prioritizes inertial support projects at Benjamin’s Mill and Wedgeport. The NS-NB Reliability Intertie Project aims to enhance transmission reliability between Nova Scotia and New Brunswick.
. 26 17 4.5 Trimming and Removal of Trees Around Existing Power Lines .......................... 27 18 5.0 STORM HARDENING – TARGETED EQUIPMENT REPLACEMENTS AND 19 UPGRADES .....................................................................
AI summary The document outlines infrastructure upgrades for Nova Scotia's power grid, including tree trimming, storm hardening, equipment replacements, and grid modernization programs. It is part of the 2026 Annual Capital Expenditure (ACE) Plan, focusing on distribution, transmission, and substation improvements.
1 6.1.2 Downline Connectivity ............................................................................. 45 2 6.2 Fault Location Isolation and Service Restoration ................................................. 47 3 6.3 Distributed En...
AI summary The document outlines Nova Scotia Power's 2026 Five-Year Reliability Plan, focusing on storm hardening through vegetation management, corridor widening for distribution/transmission lines, equipment upgrades, and advanced grid modernization programs including connected assets and infrastructure improvements.
............................... 26 18 Figure 13: Map of 2025 Completed and Planned Establishment of New Rights-of-Way ........... 27 19 Figure 14: Trimming and Removal of Trees Around Existing Powerlines - 2025 ....................... 28 2...
AI summary The document outlines NS Power's 2025 infrastructure projects, including rights-of-way establishment, tree trimming, equipment upgrades, and transmission work. It references the Five-Year Reliability Plan update and the 2026 ACE Plan Appendix G, focusing on grid modernization and reliability improvements.
1 Figure 26: In Progress Construction of New Mount Uniacke Substation .................................... 42 2 Figure 27: 2025/2026 Advanced Grid Modernization Progress Overview ................................. 44 3 Figure 28: 2025 Plann...
AI summary The document outlines infrastructure projects and planning for grid modernization, reliability, and expansion in Nova Scotia, including substation construction, remote terminal unit installations, vegetation management, right-of-way widening, and conductor upgrades for 2025/2026.
ments 8 detailed in year one of the Plan. The Plan has a goal of reducing the overall duration and frequency 9 of outages while balancing the affordability of these investments for customers. 10 11 1.1 Five-Year Reliability Plan Commitment...
AI summary NS Power's Five-Year Reliability Plan aims to reduce outage duration and frequency through three core programs: vegetation management, storm hardening, and grid modernization. The plan balances reliability improvements with customer affordability, focusing on infrastructure upgrades and advanced grid technologies.
1 2 As shown in Figure 1 below, NS Power’s Plan includes approximately $1.3 billion of investment 3 in the 2025-2029 period with a commitment to $206 million of investment in 2025 and $234 4 million in 2026. 5 6 Figure 1: Forecast Investme...
AI summary NS Power outlines a $1.3 billion investment plan (2025-2029) targeting grid resilience and reliability improvements, including $206M in 2025 and $234M in 2026. Goals include reducing SAIDI by 20% and achieving 91.98% service restoration within 48 hours post-major events.
1 October 31, there is a 53 percent reduction in customer interruptions and a 29 percent reduction in 2 customer hours of interruption due to device failure in 2025 over 2023 levels. 3 4 The benefits of the program and the impact on the re...
AI summary NS Power outlines reliability improvements through targeted investments, citing a 53% reduction in customer interruptions by 2025. The Board directed NS Power to update its 2025 ACE Plan (M12012) with progress on its Five-Year Reliability Plan, emphasizing risk-based decision-making and grid-modernization upgrades. NS Power agrees with stakeholders on balancing reliability and affordability.
1 2.0 RELIABILITY PERFORMANCE ANALYSIS 2 3 NS Power has developed the Plan to deliver a 20 percent improvement in the performance 4 standards overall average duration of outages (SAIDI) and to achieve the Performance Standards 5 SAIFI targ...
AI summary NS Power's Plan aims to improve system reliability by reducing outages caused by tree contacts and equipment failures, targeting a 20% improvement in SAIDI and achieving a SAIFI target of 2.05 by 2029. Grid modernization, including RTUs and remote connectivity, will mitigate outage impacts and enhance fault isolation.
1 3.0 2025 Overview – Year One of Five Year Reliability Plan 2 3 In 2025, NS Power’s Reliability team has been focused on executing the projects identified in year 4 one of the Plan, with $206.6 million committed to strengthen the grid and...
AI summary NS Power's 2025 reliability efforts focused on $206.6 million in grid upgrades, including distribution system improvements like replacing insulators, conductors, and transformers, as well as tree clearing to enhance resilience against weather events and support growing energy demand.
Distribution 8 kms 8.8 kms 2.0 kms 10.8 kms System Build-To- Roadside Distribution 39 kms 73.7 kms 4.5 kms 78.2 kms System Conductor Upgrades Distribution 50 padmounts 64 padmounts Program 64 padmounts System Complete Underground Upgrades...
AI summary The document outlines grid modernization initiatives, including distribution system upgrades (8.8 km, 73.7 km), conductor and underground upgrades (64 padmounts), transmission line upgrades (37 lines), substation transformer replacements (5 transformers), remote terminal units (11 devices), and fault isolation/service restoration systems (24 devices). Projects span multi-year execution with some components ongoing through 2026.
, as well as improve 9 worker and public safety. The PCB program exemplifies this approach and continues to progress 10 on schedule, remaining compliant with federal regulations and timelines. 11 12 5.1.2 Power Line Protective Devices 13 1...
AI summary The document discusses NS Power's 2025 recloser installation plan, highlighting progress on seven new devices to improve grid reliability by reducing outage frequency and duration. Three reclosers are completed, with four remaining for installation, targeting key regions like Canso, Merigomish, and Glace Bay.
2026 ACE Plan Appendix G Page 43 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 6.0 ADVANCED GRID MODERNIZATION PROGRAMS 2 3 2025-2029 Forecast Investment: $78 million 4 Forecasted Performance Standards SAIDI Reducti...
AI summary NS Power's Advanced Grid Modernization Program (2025-2029) aims to enhance grid reliability and efficiency through three initiatives: Connected Assets (real-time device control), FLISR (automated outage response), and DER integration. The $78 million investment targets a 0.06-0.11 SAIDI reduction.
2026 ACE Plan Appendix G Page 44 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 Figure 27: 2025/2026 Advanced Grid Modernization Progress Overview Program Devices Remaining Devices On Track Complete Forecast 2025/202...
AI summary NS Power's 2025-2029 grid modernization plan includes $65M investment, with $21M allocated to Remote Terminal Units (RTUs). As of 2025, six of 11 RTUs are installed, with two more targeted for completion by year-end. The plan emphasizes real-time monitoring and outage response improvements through advanced grid technologies.
RTUs planned for deployment in 2025. The remaining units are in progress and remain a priority 18 to have two completed before year-end, and the final three installations to be completed early in Page 44 of 71 Date: December 12, 2025 Page...
AI summary NS Power outlines its 2025 RTU deployment plan, with Phase 6 under regulatory review. The company emphasizes its commitment to the Board's oversight in ensuring project value for customers. Progress updates include completed and on-track installations across multiple substations, with final installations targeted for early 2026.
2026 ACE Plan Appendix G Page 46 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 2 As outlined in NS Power’s Five-Year Reliability Plan, establishing a communications path 3 between downline reclosers and the Advanced...
AI summary NS Power's 2025/2026 reliability plan emphasizes integrating 35 downline reclosers with the Advanced Distribution Management System (ADMS) to improve outage response, reduce restoration delays, enhance asset visibility, and improve worker safety through remote SCADA operations.
ion status of these communication paths and identifies the specific devices and feeders 11 involved. 12 13 Figure 29:2025/2026 Planned Communications Path with Downline Reclosers Installation
AI summary The text discusses the current status of communication paths, identifying involved devices and feeders, and references a figure detailing the 2025/2026 planned communications path with downline reclosers installation.
2026 ACE Plan Appendix G Page 48 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 reliability and operational flexibility. To address these challenges, enhanced visibility, automation, 2 and control of DERs is importan...
AI summary NS Power's 2026 ACE Plan Appendix G discusses the integration of distributed energy resources (DERs) to enhance grid reliability and decarbonization. It highlights the DERMS project, stakeholder engagement, and alignment with Nova Scotia's 2030 Clean Power Plan, emphasizing coordinated DER management for system resilience.
2026 ACE Plan Appendix G Page 49 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.0 2026 – YEAR TWO – FIVE-YEAR RELIABILITY PLAN 2 3 2026 is year two of the Five-year Reliability Plan. NS Power has committed to an ov...
AI summary NS Power's 2026 reliability plan allocates $234 million for grid improvements, including storm hardening ($178.9M), vegetation management ($45M), and advanced grid modernization ($10.7M). This follows $206M in 2025 and over $185M annually in prior years, focusing on corridor widening, ROW establishment, and tree trimming.
TS AND 4 UPGRADES 5 6 2026 Forecast Investment: $178.9 million 7 8 7.2.1 Distribution System Equipment Upgrades and Replacements 9 10 2026 Forecast Investment: $83.9 million 11 12 7.2.1.1 Modernize and Replace Aging Equipment 13 14 NS Powe...
AI summary NS Power plans $83.9M in 2026 for distribution upgrades, including PCB replacement and 7.1km of line relocation to roadside to improve reliability. Modernization efforts align with federal regulations and prioritize infrastructure renewal based on inspection data.
1 7.2.1.4 Distribution System Underground Upgrades 2 3 In 2026, a planned investment of $10.2 million will support the Distribution Underground 4 program, aimed at strengthening and modernizing NS Power’s underground electrical system. Thi...
AI summary NS Power plans a $10.2M 2026 investment in underground distribution upgrades, including cable replacement in Kentville, SCADA-enabled switch installation in Halifax, and a high-capacity ductbank with QEII Health Sciences Centre. These projects aim to enhance system reliability, reduce outages, and support infrastructure growth in high-density areas.
y with additional substations in the Wellington, Stillwater, Bridgewater and Dartmouth 12 communities. Engineering and procurement activities for these new substations will continue in 13 2026. 14 15 7.3 ADVANCED GRID MODERNIZATION PROGRAM...
AI summary NS Power is expanding its grid modernization efforts in 2026, including the installation of new substations in Wellington, Stillwater, Bridgewater, and Dartmouth, as well as the implementation of advanced telecommunications connectivity to enhance grid reliability.
al 1 replacement of RTUs and enhanced communications with distributed protection equipment, 2 strengthening real-time visibility, operational responsiveness, and overall system reliability. 3 4 7.3.1.1 Remote Terminal Units (RTUs) 5 6 In 2...
AI summary NS Power plans to replace and upgrade end-of-life RTUs in 2025 and 2026 to improve grid reliability, with a focus on enhancing real-time visibility and operational resilience. Additionally, efforts will continue to expand connectivity to downline devices by integrating advanced telemetry and remote control capabilities.
nline 16 devices. In 2026, the focus will continue to be on integrating advanced telemetry and remote 17 control capabilities into intelligent field equipment, as outlined in Figure 45 below. 18 Page 63 of 71 Date: December 12, 2025 Page 7...
AI summary The text discusses the integration of advanced telemetry and remote control capabilities into intelligent field equipment as part of the 2026 focus, as outlined in Figure 45, which shows the 2025/2026 planned communications path with downline reclosers installation.
In Design. Metro Kearney Lake (multiple devices) Planned for 2026 Execution 137H In Design. Metro Hammonds Plains (multiple devices) Planned for 2026 Execution 2H In Design. Metro Armdale (multiple devices) Planned for 2026 Execution 104H...
AI summary NS Power is advancing grid modernization through the deployment of FLISR technology, which automates fault detection and service restoration, as part of its Five-Year Reliability Plan Update. The implementation follows a structured, multi-step approach.
2026 ACE Plan Appendix G Page 65 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 • Device Deployment: The first phase involves ensuring the necessary field devices are in 2 place. While most of the required devices al...
AI summary NS Power's Five-Year Reliability Plan Update outlines three phases of FLISR implementation: device deployment, connectivity enablement, and FLISR configuration. These projects are targeted for completion by the end of 2026 and are currently under consideration by the NSEB under matter M12417.
ion 104H In Design. Metro Kempt Rd (multiple devices) Planned for 2026 Execution 2 3 7.3.3 Distributed Energy Resources (DERs) 4 5 As the presence of Distributed Energy Resources (DERs) such as solar, wind, and battery storage 6 continues...
AI summary The document discusses the importance of managing Distributed Energy Resources (DERs) such as solar, wind, and battery storage to maintain grid reliability and efficiency. NS Power plans to implement a DERMS platform through a capital work order in 2026 to enhance grid resilience and intelligence.
2026 ACE Plan Appendix G Page 67 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 8.0 CONCLUSION 2 3 NS Power’s Five-Year Reliability Plan represents a significant, sustained commitment to 4 improving system reliabilit...
AI summary NS Power’s Five-Year Reliability Plan outlines a commitment to improving system reliability and resilience through targeted investments, including vegetation management and grid modernization. The plan aims to achieve a 20 percent improvement in SAIDI by 2029 while maintaining affordability and transparency with stakeholders.
e efforts, NS Power will deliver a stronger, more resilient 22 grid capable of meeting the challenges of climate change, supporting electrification, and improving 23 the customer experience. 24 Page 67 of 71 Date: December 12, 2025 Page 77...
AI summary NS Power outlines efforts to enhance grid reliability through its Five-Year Reliability Plan, including updates on distribution feeders and work completed or in progress on 2025 priority feeders.