N-2NSPI (NSEB) RIRs 1-9 1 passage
1 Request IR-4:
NON-CONFIDENTIAL 1 Request IR-4: 11 transmission impact were all discussed. For this event, there were more external contractor crews 12 brought into the Northeast based on the forecasts for the potential for more heavy, wet snow. 1 Reques...

AI summary The document discusses the deployment of automated sectionalizing capabilities (FLISR) by NS Power, including the percentage of feeders equipped with this technology and a response to a request for a system-wide assessment of distribution automation and circuit segmentation. It also references a Board approval (M12417) for expanding FLISR deployment.

101379NSEB (NSPI) IR-1 to IR-9 1 passage
Request IR-6:
Request IR-6: - Please provide a system wide assessment of distribution automation and circuit segmentation. - The response should include: - a) The percentage of feeders equipped with automated sectionalizing capability; and - b) A compar...

AI summary Request IR-6 seeks a system-wide assessment of distribution automation and circuit segmentation, focusing on the percentage of feeders with automated sectionalizing capability and a comparison of restoration times between automated and non-automated circuits.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →