HomeGrid ModernizationM12799Evidence
Topic/Matter Intersection

Topic:"Grid Modernization" in M12799

Matter: Nova Scotia Power Inc. - CI C0080101 – 539N-201 Big Island Subsea Cable Replacement - $4,388,679
2 passages 2 documents

Grid Modernization across all matters →

N-2NSPI (NSEB) RIR 1 to 16 - Redacted 1 passage
NON-CONFIDENTIAL
NON-CONFIDENTIAL 1 Request IR-8: 2 3 (a) Please provide a table that lists the past five years of load records for Big Island, 4 including but not limited to peak and average demand, as well as the load forecast 5 over the expected service...

AI summary The response to Request IR-8(a) indicates that direct metering data is unavailable for the asset in question, but AMI data from 2022 provides peak load estimates. For IR-8(b), technical details on the new cable are referred to IR-2(b), while information on the 1990 cable is referred to IR-4(a). The 1977 cable's specifications are not available.

101647NSEB (NSPI) IR-1 to IR-16 1 passage
Request IR-8:
Request IR-8: - a. Please provide a table that lists the past five years of load records for Big Island, including but not limited to peak and average demand, as well as the load forecast over the expected service life of the proposed new...

AI summary Request IR-8 seeks data on Big Island's load records over the past five years and forecasts for new cable infrastructure, alongside a comparison of new subsea cables with older ones from 1977 and the 1990s, focusing on design, performance, and maintenance.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →