Cape Breton Regional Hospital (CBRH) Load Impact Study Alternative 3 Secondary Supply - 6S-311 4 Refurbish 6S substation & install a 69-12.5 kV, 7.5/10/12.5 MVA transformer: Includes refurbishment of structures and ground grid, environment...
AI summary The Cape Breton Regional Hospital (CBRH) Load Impact Study outlines Alternative 3, which involves refurbishing a substation and upgrading infrastructure, with a total estimated cost of $3,032,150. However, Alternative 1 is identified as the least cost option, though it has reliability concerns due to shared infrastructure.