N-1Application - Redacted
88 passages
among other things, mandated a transfer of certain system functions from the incumbent - utility, Nova Scotia Power (NS Power), to the not-for-profit independent system operator, IESO - Nova Scotia. - The proclamation of the MAEA contempla...
AI summary The text describes the phased transition of system operator functions from Nova Scotia Power (NS Power) to the independent system operator, IESO Nova Scotia, as mandated by the More Access to Energy Act (MAEA). Phase 1, which commenced in October 2024, covers independent energy procurement, system planning, and generation interconnection. IESO Nova Scotia is currently preparing for Phase 2, which involves real-time energy dispatch. Key accomplishments in Phase 1 include the start of the first Integrated Resource Plan and various system impact studies and BESS facility commissioning.
1.3 Material Changes in the Application - The Board and parties will note that this Application differs in some respects from the prior - applications for the 2025/2026 and 2026/2027 fiscal years. The material changes or additions - fall u...
AI summary IESO Nova Scotia outlines material changes in its current application compared to prior filings for the 2025/2026 and 2026/2027 fiscal years. Key updates include a revised transition date for Phase 2A to March 2028 based on completed design work. The application also introduces a more functional alignment of OM&A expenditures within the revenue requirements to improve consistency for Board evaluation. Additionally, it details the phased implementation of the Phase 2 Control Centre project to support independent Balancing Authority and Transmission Operator functions.
ransition plan. It provides - for the continued delivery of IESO Nova Scotia's existing responsibilities while advancing the - further institutional and operational changes contemplated by the MAEA. - 2.3 Business Plan Priorities and Cost...
AI summary The document outlines the transition plan for IESO Nova Scotia to assume independent grid operations from Nova Scotia Power by 2027/2028. Key priorities include establishing a dedicated control center, implementing necessary IT and operational infrastructure, training a specialized workforce, and developing compliance frameworks for Balancing Authority (BA) and Transmission Operator (TOP) functions. This transition involves updating Market Rules and the Open Access Transmission Tariff to support an independent operating model while maintaining system reliability.
3.2 Proposed Expenditures - Phase 2 Control Centre - IESO Nova Scotia's proposed expenditures in this Application are exclusively related to the - capital work in progress costs of its Phase 2 Control Centre8 build-out (the "Project"). Thi...
AI summary IESO Nova Scotia is seeking Nova Scotia Energy Board (NSEB) approval for $48.99 million in capital expenditures to complete Phases 2A and 2B of its Phase 2 Control Centre project. These expenditures, spanning four fiscal years (2026-2030), are part of a $75.4 million project to transition system operations. The project was informed by a value analysis by FTI Consulting and IBM to determine the most cost-effective independent system operator model for grid operations.
Phase 2 Control Centre - Following the successful implementation of Phase 1 in December 2025, IESO Nova Scotia - undertook a comprehensive assessment of options for establishing independent operational - control of Nova Scotia's integrated...
AI summary IESO Nova Scotia is pursuing 'Scenario 4 Enhanced Independence' for the Phase 2 Control Centre, following a comprehensive assessment of options for establishing independent operational control of the province's electricity system. This pathway involves establishing an independent control room space within Nova Scotia Power's Atlantic Data Centre and progressively transferring operational responsibilities. Scenario 4 was selected as the most prudent balance because it achieves high operational independence while avoiding the high costs of new construction and leveraging existing synergies with Nova Scotia Power systems.
3.2.2 Options Analysis - To develop the option selection process, select an option, and prepare budget estimates, IESO - Nova Scotia engaged the expert support of FTI and IBM. FTI was engaged to develop a value - framework and to quantify...
AI summary The text describes the process for selecting and budgeting options for the Independent Energy System Operator (IESO) Nova Scotia's Control Centre. Nova Scotia engaged FTI Consulting to develop a value framework to quantify the benefits and disbenefits of transitioning from a vertically integrated utility model to an independent system operator model. IBM was engaged to assess five strategic scenarios, ranging from simple models to the construction of a new control facility with new systems, and to provide AACE Class 3 cost estimates for the recommended option.
11 Strategic Scenarios IESO-Lite Near-term planning role only Shared Operations Shared facilities and systems Minimum Independence Limited tactical investments Enhanced Independence Enhanced Capability Fit for future market evolution Contr...
AI summary The document presents a comparative analysis of five strategic scenarios for the evolution of the Independent Energy System Operator (IESO) and Nova Scotia Power (NSP) operational relationship. The scenarios range from 'IESO-Lite' (minimum independence) to 'Fit for future market evolution' (full independence). Each scenario is evaluated based on control center facilities, EMS/SCADA systems, dispatch capabilities, market mechanisms, and projected CAPEX and benefits. The 'Fit for future' scenario requires the highest investment ($167M mid-range) but offers the most robust market operation capabilities and highest projected benefits.
Scenario 1 - IESO Lite: Scenario 1 represents the lowest-independence model. Under this approach IESO Nova Scotia would perform planning, monitoring and advisory functions while NS Power retained responsibility for real-time BA and TOP ope...
AI summary The text evaluates 'Scenario 1 - IESO Lite,' a low-independence model where IESO Nova Scotia handles planning and advisory functions while Nova Scotia Power retains real-time Balancing Authority and Transmission Operator responsibilities. While noted as a low-cost, simple implementation, the scenario fails to meet More Access to Energy Act (MAEA) requirements and long-term goals for operational independence. The document also defines technical components including day-ahead P×Q pairs, SCADA systems, Energy Management Systems (EMS), and the NSP optimizer (ECCPO) for resource dispatch optimization.
4 Figure 5: Core Capabilities CAPABILITY OPERATIONAL PURPOSE SCENARIO 4 PRINCIPAL SYSTEM APPROACH 1. SCADA & Monitoring Provides operators with real- time visibility into the electricity system so they can monitor system conditions and res...
AI summary The document outlines the core operational capabilities required for the electricity system, categorized by their operational purpose, approach (Shared, Transfer, or Build New), and principal systems. Key capabilities include SCADA and monitoring for real-time visibility, Energy Management Systems (EMS) for decision support, dispatch/redispatch for reliability, market management, operational forecasting, and intertie management for coordinating energy flows with neighboring jurisdictions. It also covers outage coordination, training systems, and reporting and analytics.
Phased Approach - Scenario 4 will be implemented through a phased transition. This is a risk balanced approach - that will help accelerate early deliverables while allowing more time to refine later deliverables - to maximize value. As not...
AI summary The document outlines a phased transition plan for Scenario 4 to balance risk while accelerating early deliverables. The transition involves three phases: Phase 2A (Operational Control), Phase 2B (Settlement), and Phase 2C (Enhanced Independence). These phases progressively transfer operational responsibilities, systems, and capabilities from Nova Scotia Power to IESO Nova Scotia. Phase 2A establishes core dispatch capabilities; Phase 2B transfers market settlement and administration; and Phase 2C provides enhanced technological independence. Phases 2A and 2B together constitute 'Steady State 1'.
1 Figure 6: Cost Breakdown (All costs in $M) Total Phase 2A Phase 2B Phase 2C IT Costs $ 20.6 $ 0.8 $ 5.9 $ 13.9 Proqram lnteqration $ 11.4 $ 9.0 $ 1.0 $ 1.4 Control Center Build $ 9.0 $ 9.0 $ - $ - NERC Compliance $ 6.4 $ 6.4 $ - $ - Cybe...
AI summary The document provides a detailed cost breakdown for different phases (2A, 2B, and 2C) of a project, likely related to grid infrastructure or IT modernization. It categorizes expenditures into IT costs, program integration, control center construction, NERC compliance, cybersecurity, and NSP support costs. The table highlights that Phase 2A has the highest direct capital expenditures and program integration costs, while Phase 2C is significantly more weighted toward IT costs and direct capital expenditures.
11 Control Center Build 12 Control Centre Build includes the design, construction, fit-out, physical security systems, and 13 commissioning of t he IESO Nova Scotia Control Centre at the Atlantic Data Centre. This includes 14 t he dedicate...
AI summary The Control Centre Build involves the design, construction, and commissioning of the IESO Nova Scotia Control Centre at the Atlantic Data Centre. This facility is a foundational component for the transition to an independent system operator under the More Access to Energy Act (MAEA). It enables IESO Nova Scotia to independently manage real-time operations of Nova Scotia's bulk electricity system and assume Balancing Authority (BA) and Transmission Operator (TOP) responsibilities, independent of Nova Scotia Power.
NERC Compliance - NERC Compliance includes compliance program and procedure development, audit readiness, - certification activities, and the documentation required for IESO Nova Scotia to assume BA and - TOP functions. This work supports...
AI summary The text outlines the requirements for NERC Compliance as part of the IESO Nova Scotia transition to assume Balancing Authority (BA) and Transmission Operator (TOP) functions. This involves developing compliance programs, audit readiness, and certification activities aligned with reliability and cybersecurity standards. These activities are essential for certification by NERC and the NPCC. The cost estimate for these compliance activities was developed by IBM based on industry benchmarks and past experience, primarily supporting Phase 2A of the project.
Cyber Security - Cyber Security includes the security architecture, network controls, monitoring, identity - management, and other cybersecurity controls required to support IESO Nova Scotia's - independent operating environment. This work...
AI summary The document outlines the scope and requirements for cyber security within IESO Nova Scotia's independent operating environment. It specifies that cyber security encompasses security architecture, network controls, monitoring, and identity management necessary to support Balancing Authority (BA) and Transmission Operator (TOP) functions while adhering to NERC CIP requirements. The associated cost estimates were developed by IBM based on industry benchmarks and professional judgment. These activities are essential throughout Steady State 1 and Steady State 2, specifically during Phases 2A and 2B.
Program Integration - Program Integration includes program management, design authority, process development, - change management, quality assurance, and program administration. This category covers the - resources and activities required...
AI summary The document defines Program Integration as the management of design authority, process development, change management, quality assurance, and program administration for the Phase 2 program. It encompasses the resources needed to coordinate various workstreams, oversee vendors and system integrators, and manage dependencies. The cost estimate was developed by IBM using a bottom-up assessment based on detailed design activities, internal resource planning, and experience with similar projects to support the transition from Nova Scotia Power to IESO Nova Scotia.
Phase 2A Workstreams (GRA) Governance & Regulatory - Market Rules & Open Access Transmission Tariff (OATT) Establish the governance, regulatory change management, stakeholder approval, and agreement frameworks needed to support the IESO NS...
AI summary The document outlines the specific workstreams for Phase 2A of a project aimed at establishing the Independent Electricity System Operator Nova Scotia (IESO NS). The workstreams are categorized into Governance & Regulatory (covering market rules, OATT, and NERC compliance), Technology & Communications, Control Centre infrastructure, and Operational Frameworks (focused on processes and people). These activities are designed to ensure regulatory compliance, cybersecurity, and operational readiness for the transition to a new market model.
4 Phase 2B Sequencing 3 - 5 Although Phase 2B is scheduled for completion after Phase 2A, work on Phase 2B will begin - 6 before Phase 2A is complete. This is necessary because Phases 2A and 2B together comprise - 7 Steady State 1 and are...
AI summary The text explains the sequencing of Phase 2B in relation to Phase 2A of the project to achieve 'Steady State 1'. While Phase 2B is scheduled for completion after Phase 2A, work will begin concurrently because the two phases form an integrated operating model. Phase 2A focuses on independent operation and dispatch, while Phase 2B establishes the necessary settlement, reporting, and participant administration systems. Parallel implementation is required to ensure timely completion of the administrative and market functions mandated by the MAEA.
2. Reliability Through Transition - Risk: Material reliability incident occurring during transition, cutover, or early operations, - particularly under challenging operating conditions. - Mitigation: The mitigation measures for this risk a...
AI summary The document outlines the risks and mitigation strategies associated with maintaining grid reliability during system transitions, cutovers, or early operations, especially under adverse conditions. Key mitigation strategies include active collaboration with Nova Scotia Power, clear role definition for separated processes, established communication protocols, parallel operations, and extensive testing. Furthermore, the plan advocates for a controlled, staged cutover approach informed by weather assessments and comprehensive internal and external training.
4. NS Power Dependency - Risk: This Project has significant impacts on NS Power, and this is one of its many priorities. - Delays or cost increases due to the transition leading to unexpected requirements for NS Power - to reconfigure syst...
AI summary The document outlines the operational dependencies and risks associated with the transition of certain capabilities to IESO Nova Scotia from NS Power. Key risks include potential delays and cost increases resulting from necessary system reconfigurations, process updates, and documentation changes. To mitigate these risks, the project utilizes continued collaboration, an expanded Project Management Office purview to manage shared scope, a Joint Transition Committee for leadership communication, and a phased implementation approach to allow for ongoing reassessment of transfer requirements and costs.
5. Cybersecurity Risk: Cybersecurity risk associated with shared systems, transitional access arrangements, and interim technology solutions implemented during the phased transition to IESO Nova Scotia operations. Mitigation: While certain...
AI summary The document outlines cybersecurity risks and mitigation strategies during the phased transition to IESO Nova Scotia operations. Key risks involve shared systems and transitional access arrangements. Mitigation efforts include network segmentation, identity and access management, and adherence to NERC and NPCC Critical Infrastructure Protection (CIP) standards. The transition plan aims to reduce reliance on NS Power systems over time while building internal expertise at IESO Nova Scotia, supported by external consultants and collaborative risk assessments with NS Power.
1 3.3.1 Phase 2 Control Centre 2 As described above in section 3.2 regarding the Phase 2 Control Centre project, Phase 2A 3 regarding system operational dispatch functionality, and the corresponding control centre 4 assets, are expected to...
AI summary The text describes the Phase 2 Control Centre project, noting that the Phase 2A system operational dispatch functionality and associated assets (including buildings, hardware, and software) are expected to be in-service by March 2028. Because of this timeline, one month of amortization expense is included in the current revenue requirement. These investments align with IESO Nova Scotia's strategic priority to complete the successful transition of system operations.
1 3.3.2 Information Technology 2 Separate from the assets deployed in the Control Centre, IESO Nova Scotia will also need to 3 implement software and hardware assets to enable additional existing business functions. As 4 more employees are...
AI summary IESO Nova Scotia identifies necessary investments in information technology (IT) and operational technology (OT) to support its foundational business functions and strategic priorities. This includes the procurement of hardware, such as computers and mobile devices, to accommodate new employees, as well as a specific software solution to manage transmission interconnection activities. The text emphasizes that these IT expenditures are essential for the organization's core operations and includes an amortization budget for these assets.
Staffing and Compensation - Consistent with IESO Nova Scotia's prior revenue requirement applications (M12412 and - M12663), compensation continues to be the single largest category of cost across all functional - areas of the organization...
AI summary IESO Nova Scotia outlines its staffing and compensation requirements for fiscal year 2027/2028, noting that compensation remains its largest OM&A cost at approximately $6.9M. The staffing plan reflects the organization's growth as it assumes new responsibilities under the More Access to Energy Act (MAEA), specifically the transfer of bulk system control operations from Nova Scotia Power. The plan projects a phased increase from 55 to 91 full-time equivalents (FTEs) by March 2028, prioritizing internal hiring to build expertise and reduce project costs.
to mature, - but submits that the evidence in this Application demonstrates meaningful progress and a - continuing commitment to prudent management, accountability and year-over-year - improvement. - Significant work remains. During the 20...
AI summary IESO Nova Scotia submits that its evidence demonstrates a commitment to prudent management and year-over-year improvement. The organization emphasizes the necessity of completing Phases 2A and 2B of the Control Centre project to establish independent operational, settlement, and reporting capabilities. The proposed phased approach aims to balance operational independence with risk and cost management. IESO Nova Scotia requests Board approval for $48.99 million in capital work in progress, the 2027/2028 OM&A and amortization revenue requirement, and specific DVM Guidelines and Accounting Policies.
NON-CONFIDENTIAL Project Key Activities (Updated) Estimated or Actual Completion MAEA Objects Phase II Planning and Implementation - Determined best option for establishing IESO Control Center to perform IESO operating functions (Q4 2025/2...
AI summary The document outlines the project status and key activities for several initiatives under the More Access to Energy Act (MAEA). These include Phase II Planning and Implementation for the IESO Control Center, SGIP Administration and Revisions (incorporating FERC Order 2023 recommendations), and annual reporting for interconnection processes. The text details specific timelines for planning, implementation, stakeholder engagement, and submission deadlines for each project through the 2027/28 period.
Priority 1 - Complete the Successful Transition of Independent Grid Operations Key Activity/ Project Description Estimated Completion MAEA Linkage Independent Grid Operations Planning and Implementation Please refer to Proposed Expenditure...
AI summary The document outlines Priority 1 for the transition to independent grid operations in Nova Scotia, primarily involving the establishment of IESO Nova Scotia. Key activities include the creation of an independent control centre, obtaining NERC certification for Balancing Authority and Transmission Operator functions, and updating market rules and tariffs. The plan also encompasses technology enablement (cybersecurity and IT/OT systems), organizational change management for personnel transitioning from Nova Scotia Power, and the development of a new settlement system to support a competitive electricity market.
As discussed in the Phase 2 Control Centre section, while operational cutover of system operations to IESO Nova Scotia's dedicated control centre is targeted for the end of 2027-28, the full transition of is part of multi-year program that...
AI summary The text outlines the timeline for transitioning system operations to the IESO Nova Scotia dedicated control centre. While the operational cutover is targeted for completion by the end of the 2027-28 period, the full transition is characterized as a multi-year program. This initiative will include ongoing activities related to system stabilization, settlements, and optimization, which are expected to continue through the 2028-32 period.
Interconnection Studies and commissioning support will continue beyond 2027-28 as part of ongoing work to facilitate new generation, storage, and load connections to the Nova Scotia transmission system. Depending on the determined scope of...
AI summary The text outlines the ongoing commitment to provide interconnection studies and commissioning support beyond the 2027-28 period. This work is intended to facilitate new connections for generation, storage, and load to the Nova Scotia transmission system. The timeline for full implementation may be extended depending on the defined scope of Interconnection Process Improvements, which may include the deployment of new software systems.
Project Work Plan and Schedule Object Summary 9(a) exercise and perform the powers, duties and functions assigned to the IESO under this Act, the market rules and its licence; 9(b) enter into agreements with transmitters giving the IESO th...
AI summary The document outlines the statutory powers, duties, and functions of the Independent Electricity System Operator (IESO) as defined under the relevant Act. These responsibilities include maintaining the adequacy and reliability of the bulk electricity system, procuring ancillary services, coordinating power system planning, and facilitating a competitive electricity market. Additionally, the IESO is tasked with procuring various energy resources (including storage and renewables), forecasting electricity demand, and conducting independent planning for transmission and demand-side management.
What it delivers: - Establishes the independent IESO-NS control centre (ADC) - Begins BA/TOP operations using existing NSP systems - Creates secure physical/cyber boundaries - Builds operator capabilit1• and early credibility
AI summary The text outlines the initial deliverables of a project focused on establishing independent control center operations for the Independent Electricity System Operator - Nova Scotia (IESO-NS). Key objectives include establishing the ADC control center, initiating Balancing Authority (BA) and Transmission Operator (TOP) operations utilizing existing Nova Scotia Power (NSP) systems, and creating secure physical and cyber boundaries to build operator capability and credibility.
Why it matters: - Achieves the long-term "North Star" operating model and long-term customer benefits - Postpones enhancement capex, allowing design l o be based on real operation;:il experiences, including seeing full functionality of NSP...
AI summary IBM recommends that IESO-NS adopt 'Scenario 4 – Enhanced Independence' as the preferred operating model for Phase 2 of the transition to independent operational control. This move aligns with the More Access to Energy Act (MAEA) and aims to achieve long-term system value and reliability. The proposed phased implementation (2A, 2B, and 2C) is estimated to cost $75 million in capital over five years, with an expected net present value of $219 million and significant annual benefits starting in 2028/29.
2. Purpose of this Report This report has been prepared by IBM for IESO-NS to provide a clear recommendation on the preferred strategic approach for Phase 2 of the transition of BA and TOP functions from NSP to IESO-NS. The report is inten...
AI summary IBM prepared this report for IESO-NS to recommend a strategic approach for Phase 2 of transitioning Balancing Authority (BA) and Transmission Operator (TOP) functions from Nova Scotia Power Inc. (NSP) to IESO-NS. The report serves as a public-facing document for internal decision support, government and stakeholder communication, and as a basis for future regulatory filings. It outlines the recommended delivery pathway, including expected benefits, costs, implementation timing, and risk/reliability management.
Scenario 4 - Enhanced Independence Scenario 4 introduces an independent EMS environment, enhanced operational optimization capabilities, stronger cyber segregation and greater operational autonomy. It delivers a level of independence suffi...
AI summary Scenario 4 describes an 'Enhanced Independence' model for the Energy Management System (EMS). This scenario aims to provide an independent EMS environment that features improved operational optimization, stronger cyber segregation, and increased operational autonomy. The goal is to satisfy the long-term legislative intent of the More Access to Energy Act (MAEA) while deliberately avoiding the high implementation complexity associated with a full wholesale market model.
Strategic Scenarios IESO-Lite Near-term planning role only Shared Operations Shared facilities and systems Minimum Independence limited tactical investments nhanced Independence Enhanced CapabiUty Full Markel Operations Ftt for future mark...
AI summary The document outlines five strategic scenarios for the evolution of the Independent System Operator (IESO) and Nova Scotia Power (NSP) relationship. These scenarios range from 'IESO-Lite' (near-term planning role with shared operations) to 'Full Market Operations' (full market evolution). The table details specific operational components—including Control Centre facilities, EMS/SCADA systems, dispatch responsibilities, and market mechanisms—alongside associated capital expenditures (CAPEX), estimated benefits, and implementation timelines for each strategic path.
Tool/Platform Descriptions - 1. Day-ahead P×Q pairs : This refers to the day-ahead submission of power (P) and quantity (Q) pairs by generators, indicating their planned generation output and associated costs for the next day. These pairs...
AI summary The text describes various technical tools and platforms used for power grid management, including SCADA, EMS, and the NSP optimizer (ECCPO). It evaluates different scenarios for market development, concluding that Scenario 4 is the preferred long-term model. This scenario is favored for balancing legislative compliance, operational independence, reliability, and implementation feasibility over other options. The assessment recommends a phased pathway for reaching the target state rather than a single-step implementation.
5.2. Basis of Cost, Benefit and Timeline Estimates The strategic scenarios were supported by high-level Class 4 planning estimates developed to provide a consistent basis for comparing costs, benefits and implementation timelines across th...
AI summary The text describes the methodology used to develop Class 4 planning estimates for various strategic scenarios. IBM used a capability-based assessment to decompose requirements into workstreams like EMS, SCADA, and cybersecurity, utilizing a mix of vendor data, NSP information, and analogous projects. FTI Consulting independently developed the benefit estimates, focusing on operational independence and optimization. Timelines were established based on complexity factors such as procurement lead times, facility readiness, and NERC compliance obligations.
7.Recommended Delivery Pathway: Phase 2A / 2B / 2C IBM recommends that Scenario 4 be implemented through a phased 2A / 2B / 2C delivery pathway. This phased approach is central to the recommendation. It allows IESO-NS to progress toward th...
AI summary IBM recommends a phased delivery pathway (2A, 2B, and 2C) for Scenario 4 to transition IESO-NS toward its long-term end-state. This approach manages complexity and preserves reliability by creating decision points. Steady State 1 (Phases 2A and 2B) establishes the first independent operating model by transferring BA/TOP responsibilities while leveraging existing systems. Steady State 2 (Phase 2C) completes the target model, adding technology resilience, cybersecurity segregation, and operational flexibility while minimizing risk.
What it delivers: - Establishes the independent IESO-NS control centre (ADC) - Begins BA/TOP operations using existing NSP systems - Creates secure physical/cyber boundaries - Builds operator capability and early credibility
AI summary The text outlines the functional objectives and deliverables of a new initiative, which includes establishing an independent IESO-NS control centre (ADC). Key milestones include commencing BA/TOP operations utilizing existing Nova Scotia Power (NSP) systems, creating secure physical and cyber boundaries, and developing operator capability to build early credibility in the system's management.
What it delivers: - Adds province wide settlement capabilities - Enhances forecasting, outage coordination, and analytics - Strengthens governance, transparency, and participant trust
AI summary The text outlines the core benefits and deliverables of a system upgrade or technological implementation. Key improvements include the addition of province-wide settlement capabilities, enhanced capabilities for forecasting, outage coordination, and data analytics, as well as the strengthening of governance, transparency, and trust among participants.
Why it matters: - Achieves the long-term "North Star" operating model and long-term customer benefits - Postpones enhancement capex, allowing design to be based on real operational experiences, including seeing full lunctionality of NSP EC...
AI summary The text outlines a three-phase roadmap to establish IESO-NS as an independent electricity system operator in Nova Scotia. Phase 2A focuses on operational control, including monitoring and dispatching. Phase 2B introduces independent settlement capabilities and commercial transactions. Phase 2C provides enhanced independence through an independent Energy Management System and improved dispatch optimization. This phased approach aims to achieve long-term system value, postpone capital expenditures, and eliminate dependencies to accelerate the transition to an independent operator model.
7.1. Phase 2A Phase 2A is the first phase within Steady State 1, and is the recommended first implementation milestone and a credible initial operating step for IESO-NS. Steady State 1 is intended to establish operational independence whil...
AI summary Phase 2A is the initial implementation milestone of Steady State 1, designed to establish operational independence for the IESO-NS. The phase aims to enable safe and compliant BA and TOP operations by utilizing an independent IESO-NS control room while leveraging specific NSP-hosted systems to avoid infrastructure duplication. Key objectives include establishing clear decision-making authority, ensuring regulatory compliance with the More Access to Energy Act, and delivering early operational benefits to Nova Scotians.
7.1.1. Rationale for Shared, Transferred and Newly Built Components The Steady State 1 operating model was intentionally designed to balance operational independence, reliability, cost, and implementation risk. As a result, not all capabil...
AI summary The document explains the rationale behind the Steady State 1 operating model, which categorizes system components as shared, transferred, or newly built. This classification is based on asset ownership, operational requirements, implementation complexity, and cost-effectiveness. The primary objective of this design is to balance operational independence and reliability while ensuring practical compliance with the legislative goals of the More Access to Energy Act.
7.1.1.1. Shared Components Shared components are capabilities where NSP continues to provide infrastructure, technical support, or hosting services during the transition period. These arrangements reduce implementation cost and schedule ri...
AI summary The text discusses the use of 'shared components' during the transition of operational authority to IESO-NS. Nova Scotia Power (NSP) will continue to provide infrastructure, technical support, and hosting services for certain capabilities, such as SCADA systems, which NSP owns and operates. This collaborative approach is intended to reduce implementation costs and schedule risks by avoiding the duplication of assets while ensuring continued operational effectiveness and reliability during the transition.
7.1.1.2. Transferred Components Transferred components represent capabilities currently operated by NSP that are required for IESO-NS to exercise independent operational responsibility. These capabilities are transferred where direct opera...
AI summary The text defines transferred components as existing capabilities operated by Nova Scotia Power (NSP) that must be transitioned to the IESO-NS to enable independent operational responsibility. These transfers occur when direct operational control is essential for supporting BA and TOP functions, or when transferring existing ownership is deemed more effective than developing new systems.
7.1.1.3. Newly Built Components Newly built components are new capabilities established directly within IESO-NS to support operational decision-making, governance, compliance, and control room operations. These capabilities form the founda...
AI summary The text describes the newly built components within the IESO-NS, which are essential capabilities established to support governance, compliance, operational decision-making, and control room operations. These components serve as the fundamental infrastructure for the IESO-NS' independent operating model.
Fig 8 below illustrates the technology operating model for Steady State 1, with most of the OT components either shared with NSP or transferred from NSP. Base capablUtles Option selected for this capability Component I SCADA & Monitoring S...
AI summary The text describes the technology operating model for 'Steady State 1,' outlining how various Operational Technology (OT) components will be managed between Nova Scotia Power (NSP) and IESO-NS. Key capabilities such as SCADA & Monitoring, Energy Management Systems (EMS), and Training Systems will be shared or transferred. Specific tools for ECC Optimization, Operational Forecasting, Intertie Management, and Settlement are identified for transfer to IESO-NS, while new reporting capabilities will be built from the ground up.
7.2. Phase 2B Phase 2B remains within Steady State 1. It introduces additional independence and transparency enhancements without changing the core operating model. Phase 2B addresses the establishment of commercial arrangements under IESO...
AI summary Phase 2B of the project aims to establish the business and commercial capabilities required for IESO-NS to independently administer Nova Scotia's electricity system. While Phase 2A focuses on safe system operation and dispatch, Phase 2B focuses on participant workflows, settlement capabilities, reporting processes, and information exchange. These enhancements are designed to increase transparency and accountability by allowing stakeholders to interact directly with IESO-NS. The project has an estimated capital cost of $8 million and is subject to a formal decision gate review following Phase 2A.
7.3. Phase 2C Phase 2C corresponds to Steady State 2, which represents the completion of the long-term Scenario 4 target model. Steady State 2 builds on the independent operating model already delivered in Steady State 1, extending it with...
AI summary The text describes Phase 2C of the project, which corresponds to Steady State 2 of the long-term Scenario 4 target model. While Steady State 1 (Phases 2A and 2B) establishes the core operational and commercial capabilities for IESO-NS to assume BA, TOP, and market administration responsibilities, Steady State 2 builds upon this foundation. Phase 2C introduces enhanced technology resilience, cybersecurity segregation, independent EMS capabilities, and reduced dependency on NSP-hosted infrastructure to support Nova Scotia's long-term energy transition and future grid complexity.
Strategic Scenario #4 Option selected for this capability Component I Base capablUtles SCADA & Monitoring Same as Steady State 1 Same as in Scenario #3. The system is built around a core SCADA platform for real-time monitoring, control, an...
AI summary The document outlines Strategic Scenario #4 for system capabilities, focusing on the transition to a new operational framework. Key components include the transfer of an Energy Management System (EMS) from Nova Scotia Power to IESO-NS, featuring tools for automatic generation control and power system analysis. It also details plans for enhanced ECC Optimization Tools, improved market management, operational forecasting for wind and load, and the procurement of a new settlement system to align with market rules.
1. IT Costs: - Description: Assumes the configuration of shared platforms (EMS, etc.), transferred platforms, communications, interfaces, and other IT tools. This includes shared or partitioned EMS and SCADA environments, telemetry, and hi...
AI summary The document outlines the basis for estimating Information Technology (IT) costs associated with the IESO-NS project. It covers the configuration of shared and exclusive platforms, including EMS, SCADA environments, telemetry, and historian systems. The text emphasizes that shared systems with Nova Scotia Power (NSP) are preferred for ratepayer benefit. Cost estimates are derived from a combination of vendor quotes, NSP internal estimates, industry benchmarks, and historical project data.
3. Control Center Build: - Description: Covers the design, construction, fit-out, physical security systems, and commissioning of the IESO-NS control center. This includes the dedicated primary control centre facility and operating workfor...
AI summary The text describes the scope and basis for the IESO-NS control center build. This project encompasses the design, construction, fit-out, physical security, and commissioning of a dedicated facility. The primary objective is to provide the IESO-NS with an environment and workforce capable of conducting real-time operational control independently of Nova Scotia Power (NSP). The cost estimates for this project are derived from professional judgment and benchmarks from analogous control center projects and historical data.
5. Cyber Security: - Description: Covers security architecture, network controls, monitoring, identity management, and required cyber controls. This includes the cybersecurity architecture and controls needed to support IESO-NS's independe...
AI summary The document outlines the requirements and scope for cybersecurity in the context of the IESO-NS independent operating environment. It specifies that the security architecture must include network controls, monitoring, identity management, and necessary cyber controls to meet NERC CIP requirements for BA/TOP certification. The cost estimates for these measures are based on a combination of vendor quotes, industry benchmarks, and professional judgment from past project experiences.
7. Other: - Description: Covers internal IESO-NS effort, software licenses, third-party vendor costs for systems to be transferred/shared, training, and miscellaneous implementation items. This category captures costs that do not fall with...
AI summary This section describes 'Other' costs associated with the Phase 2 implementation of the IESO-NS system. These costs include internal efforts, software licenses, third-party vendor expenses for system transfers or sharing, training, and miscellaneous implementation items not captured in other categories. The estimates for these costs are based on a combination of vendor quotes, industry benchmarks, and professional judgment.
9.1. Cost Estimation Method and Assumptions The cost estimates for the Phase 2 program have been developed as a Class 3 Budgetary Estimate as defined by AACE standards. This indicates an estimate developed at a level appropriate for strate...
AI summary The document outlines the methodology and assumptions for the Phase 2 program's cost estimates, which are classified as Class 3 Budgetary Estimates according to AACE standards. These estimates are intended for strategic decision-making and program approval rather than final execution, with an expected accuracy range of -15% to +20%. Key assumptions include a 2026 commencement date, a 15% capital contingency, approximately $6.3 million in annual operating costs, and a phased benefit realization schedule validated against benchmarks like the Ontario IESO model.
Program Integration Risk The transition of core operational functions involves complex integration between IESO-NS systems, NSP legacy infrastructure, and third-party vendors. The full extent of integration complexity may not be fully know...
AI summary The text addresses the risks associated with integrating core operational functions during the transition between IESO-NS systems and legacy Nova Scotia Power infrastructure. It highlights that the complexity of integrating these systems with third-party vendors may not be fully quantifiable until the detailed design phase of the project commences.
Technology Procurement Risk Vendor pricing and availability for operational technology systems, including EMS components, may vary from planning estimates once competitive procurement is underway. The key point is that the recommended phas...
AI summary The text discusses the risks associated with technology procurement for operational technology systems, specifically noting that vendor pricing and availability for EMS components may fluctuate during competitive procurement. To mitigate these risks, a phased implementation pathway with defined decision gates is recommended. IBM supports this approach, asserting that the staged strategy effectively manages procurement uncertainties while maintaining the program's overall benefits.
11. Managing Risks, Costs, and Reliability Through the 2A / 2B / 2C Approach A central strength of IBM's recommendation is that it does not propose a single-step transition. Instead, it recommends a phased pathway that manages risk, reliab...
AI summary The text highlights the strategic advantages of IBM's recommendation to adopt a phased approach (2A / 2B / 2C) for infrastructure or system transitions. Rather than proposing a single-step change, this methodology is designed to mitigate risks, maintain system reliability, and manage costs progressively over time.
Reliability Management Phase 2 affects core operating responsibilities for the Nova Scotia electricity system. Accordingly, the recommendation emphasizes Phase 2A as a credible first milestone that allows IESO-NS to establish an initial op...
AI summary The document outlines reliability management strategies for Phase 2 of the electricity system's core operating transition. It recommends Phase 2A as a credible first milestone, allowing IESO-NS to establish initial operating capabilities. Key safeguards for the transition include a Spring 2028 cutover window to avoid extreme weather, parallel operations to validate systems in real-time, mandatory NERC compliance readiness, and the completion of operator training and certification before IESO-NS assumes live operational responsibilities from Nova Scotia Power.
Early Value with Controlled Progression Phase 2A allows IESO-NS to begin realizing a portion of the anticipated benefits earlier by establishing independent operational control, decision-making authority and the initial operational capabil...
AI summary The text discusses Phase 2A of a project, which enables IESO-NS to begin realizing benefits early by establishing independent operational control and decision-making authority for BA/TOP responsibilities. It notes that benefit realization increases as subsequent phases are completed. Furthermore, it asserts that the initiative remains economically viable with a positive business case even if implementation were to be paused after Phase 2A or 2B, a claim supported by NPV and sensitivity analyses.
Benchmarking the roles, responsibilities and operating costs of an ISO ES.8 In Chapter 2 of our report, we compare IESO-NS with a benchmarking group of ISOs in other regions. No existing ISO is entirely comparable with IESO-NS in its curre...
AI summary The report benchmarks the IESO-NS against other Independent System Operators (ISOs) to determine reasonable operating costs and roles. It establishes a general minimum fixed operating cost of $70-140 million per year for ISOs. The analysis highlights that many ISO costs are non-incremental, as they replace functions previously performed by Vertically Integrated Utilities (VIUs) or Transmission System Operators (TSOs). Furthermore, the report notes that cost scaling is not strictly linear with grid size but depends on specific roles, such as wholesale energy and capacity markets.
created by Nova Scotia's Energy Reform (2024) Act, such as the introduction of more competitive procurement for new energy resources, which are better supported under an ISO structure.[5](#page-21-0) - ES.11 The IESO's broad benefit catego...
AI summary The text outlines the anticipated benefits of establishing an Independent System Operator (ISO) in Nova Scotia as part of the Energy Reform (2024) Act. Key benefits include the removal of perceived bias inherent in Vertically Integrated Utility (VIU) models, increased competition through independent auctions to lower investment costs, and accelerated development timelines. Furthermore, an ISO structure is expected to foster innovation in clean energy and demand-side management while improving operational efficiency and decision-making in the control room.
not yet begun serving customers. See Nova Scotia Energy Board, 25 August 2025, [(link)](https://nserbt.ca/sites/default/files/NSEB%20Board%20Decision%20-%20Renewall%20Energy%20Inc%20M12339.pdf). 15 Transmission refers to the high-voltage g...
AI summary The text discusses the structural transition of Nova Scotia's electricity grid from a vertically integrated utility (VIU) model to an Independent System Operator (IESO-NS) model. It distinguishes between high-voltage transmission and low/medium-voltage distribution networks. Furthermore, it explores the characteristics of wholesale 'spot' markets versus bilateral markets, noting that a small regional spot market in Nova Scotia might face challenges regarding market power and diversity of participants. The report outlines a framework for benchmarking existing ISOs and quantifying the benefits of this transition for consumers.
Identification of the ISOs for benchmarking purposes 2.3 IESO-NS has several defining characteristics that influence our benchmarking group selection. We summarise those characteristics and the relevant ISOs in Figure 2-1 below. Source: FT...
AI summary The document outlines the methodology for identifying comparable Independent System Operators (ISOs) for benchmarking the IESO-NS. It identifies two key characteristics for selection: peak load and utility structure. IESO-NS is characterized by a relatively small peak load (approx. 2.5 GW) and a system primarily composed of a former vertically integrated utility (VIU). Comparable entities identified include EirGrid, Transpower, EMA (Singapore), CAISO, ISO-NE, MISO, and IESO Ontario.
ument/367396/download), EirGrid Annual Report 2024 [(link)](https://cms.eirgrid.ie/eirgrid-annual-report-2024), ISO New England Financial report 2024 [(link)](https://www.iso-ne.com/static-assets/documents/100021/2024_financial_statements....
AI summary The provided text consists of a list of external references, including annual reports, corporate fact sheets, and demographic data from various Independent System Operators (ISOs), Transmission System Operators (TSOs), and international organizations. These links serve as source material for benchmarking the roles and responsibilities of ISOs, covering entities in regions such as North America, Europe, Australia, and Singapore.
Table 2-2: Electricity sector role benchmarking Role Responsibility MISO ISO-NE CAISO AESO IESO Ontario NESO EirGrid AEMO EMA Transpower IESO Nova Scotia Transmission planning \overline{\mathbf{V}} \overline{\mathbf{V}} \overline{\mathbf{V...
AI summary The document presents a benchmarking table comparing the roles and responsibilities of various electricity sector entities across different jurisdictions (e.g., MISO, ISO-NE, CAISO, AESO, IESO Ontario, NESO, EirGrid, AEMO, EMA, Transpower, and IESO Nova Scotia). It evaluates key functions including transmission planning, resource procurement, capacity markets, load forecasting, reliability standards, market design, and market operation. The analysis highlights the specific capabilities and limitations of each operator, particularly regarding market settlement, congestion management, and transmission ownership.
3. Anticipated benefits of an ISO - 3.1 In this chapter, we describe the benefits and costs from the establishment of an ISO. The establishment of an ISO is a step in the liberalisation or restructuring of the electricity sector. - 3.2 Unb...
AI summary The text outlines the anticipated benefits and costs associated with establishing an Independent System Operator (ISO) in Nova Scotia as part of the electricity sector's liberalization. Key benefits include reduced bias, increased competition, innovation, and lower consumer costs through fair grid access and technology diversity. Conversely, the text acknowledges that unbundling a vertically integrated business introduces incremental costs, including staff and equipment expenses, and a potential loss of synergies between roles.
Phase 2 : More efficient operations and further unlocking benefits from independent planning and resource procurement - 3.17 The core roles transferred to IESO-NS under Phase 2 are Scheduler, Residual Energy System Balancer and Settlement...
AI summary The text describes Phase 2 of a regulatory transition involving the transfer of Scheduler, Residual Energy System Balancer, and Settlement roles to IESO-NS. This shift aims to improve operational efficiency, innovation, and reliability by providing a clearer mission and reducing information asymmetry in settlements. Furthermore, it highlights how operational improvements can unlock long-term benefits in planning pathways and increase developer participation in competitive auctions by removing the perceived information advantage of the Variable Independent Utility (VIU).
Phase 2 incremental costs - 3.25 Much of the cost for Phase 2 falls into the same broad categories as Phase 1, but to a larger magnitude for one-off costs associated with the control room and other capital-intensive activities. The impleme...
AI summary The text analyzes the incremental costs associated with Phase 2 of a system operator transition, noting that costs are largely similar to Phase 1 but higher due to one-off capital-intensive activities like control room modernization. It highlights a tension between restored planning and operator synergies and the potential loss of operational synergies caused by unbundling asset ownership from operation. Specifically, unbundling may lead to increased transaction costs for activities like temporary line overloading due to information gaps and negotiation requirements.
Benefit (CADm) Low Mid. High (1) Shifting cost overrun risk 47 67 87 (2) Reduced resource cost from competitive procurement - 67 135 (3A) Reduced production costs from accelerated deployment 186 274 363 (3B) Accelerated CapEx deployment (f...
AI summary The document presents a quantitative benefit-cost analysis of Nova Scotia Power's 2025 Annual Capital Expenditure Plan, categorized into Low, Mid, and High scenarios. It evaluates various factors including cost overrun risk mitigation, competitive procurement savings, accelerated deployment benefits, and avoided carbon costs. The analysis also accounts for financial disbenefits such as lost synergies from planner-operator separation and accelerated CapEx deployment. Total estimated benefits range from $500 million in the Low scenario to $2,361 million in the High scenario.
ximately stabilise over the 2026- 2050 period. The underlying carbon emission data assumes a transition away from coal, in line with policy goals, and reaching 80% renewables by 2030. [69](#page-65-2) - 4.17 The planned start date for each...
AI summary The text discusses the modeling of carbon emission reductions and associated cost impacts from 2026 to 2050, assuming a transition away from coal and an 80% renewable target by 2030. It notes that benefits from the Independent Electricity System Operator (IESO) transition are phased, with many starting in 2029. Additionally, the analysis clarifies that current planning documents do not account for federal carbon pricing changes after May 15, 2026, and notes the absence of plans for competitive transmission procurement in Nova Scotia.
Phase 2: Independent system operation 4.38 This analysis assumes an implementation timeline for the initial stage of Phase 2 in 2027 with substantial control room improvements effective in 2029. Because the timeline of Phase 2 is still und...
AI summary The document outlines the implementation timeline for Phase 2 of independent system operation. It assumes an initial implementation stage in 2027, with significant control room improvements occurring in 2029. Due to the ongoing development of the Phase 2 timeline, a sensitivity analysis is also provided based on a more conservative schedule, projecting the initial stage for 2028 and control room improvements for 2032.
(5) Regained synergies from planner and operator 4.39 Re-combining the planner-operator function regains the synergies explained in (5) in Phase 1 above. This simply cancels out the disbenefit above.
AI summary The text addresses the structural organization of the electricity system, specifically the re-combination of the planner and operator functions. It argues that merging these roles restores synergies that were lost when they were separated, thereby nullifying the previously identified disbenefits of a split structure.
(6) Direct control room improvements - 4.40 The transfer of system operations from NSP to the IESO is expected to coincide with a significant modernization of the current dispatch process. [78](#page-72-1) Updates to operational assets and...
AI summary The text discusses the expected operational improvements resulting from the transfer of system operations from Nova Scotia Power (NSP) to the Independent Electricity System Operator (IESO). It argues that the IESO's core focus on system operation will drive modernization of control room hardware and software, leading to more efficient resource utilization and reduced production costs. These improvements are projected to yield 2-10% in savings starting in 2029, surpassing the expected benefits of current improvements being implemented by NSP.
Core results - 4.61 The results of the quantification described above sum to over $1.4 billion in the midpoint case, within a range of $500 million to $2.4 billion over the 2026-2050 period. The IESO transition has a diverse set of benefit...
AI summary The text quantifies the economic impacts of the IESO transition, estimating a midpoint benefit of over $1.4 billion between 2026 and 2050. Benefits are driven primarily by reduced capital expenditures and production costs, with Phase 2 accounting for two-thirds of the total. Significant benefits arise from accelerated decarbonization in Phase 1 and control room improvements in Phase 2. The analysis also accounts for specific disbenefits and the cascading positive impacts of improved control room operations on competitive energy procurement.
- 4.81 Because the timeline of Phase 2 is still under development, we also provide a sensitivity analysis using a conservative timeline of 2028 as the initial stage of Phase 2 and 2032 for control room improvements, although improvements a...
AI summary The text presents a sensitivity analysis for Phase 2 of a project, using a conservative timeline (starting in 2028) to estimate potential benefits. In the midpoint case, benefits are estimated at $1.287 billion, representing a 10% decrease from the base case. Specifically, control room improvements contribute $189 million to the midpoint case, with cascading benefits totaling $459 million. The analysis provides a range of benefits from $460 million to $2.113 billion.
rt from Clean Electricity Solutions Task Force, Government of Nova Scotia, 23 February 2024, [(link)](https://news.novascotia.ca/en/2024/02/23/statement-report-clean-electricity-solutions-task-force). 98 NSEB Matter No. M12451, IN THE MATT...
AI summary The text references Nova Scotia Power's (NSP) application for rate revisions and its ownership by Emera Incorporated. It highlights the importance of transmission planning and long-term security of supply, citing the Clean Electricity Solutions Task Force report and legislative debates regarding the Electric Utility Capital Accountability and Transmission Competition Act. Additionally, it notes potential delays in the interconnection process within the context of market design.
Market design - A1.17 Market design includes rules and mechanisms that govern trading and access. Market access is improved by aligned incentives to find capacity for new connections and timeliness of connection responses. Vertically integ...
AI summary The text discusses market design principles, emphasizing that rules and mechanisms must govern trading and grid access fairly. It highlights how vertically integrated businesses can create barriers to entry for competitors through pricing rules and physical grid access. Specifically, it notes that market designs favoring locational signals may be resisted by network owners as they reduce the need for new assets. Additionally, the text identifies potential conflicts of interest when incumbents like Nova Scotia Power (NSP) perform feasibility and interconnection studies, potentially deterring new generation and storage projects.
Industry governance: Improved reliability standards and grid codes A1.21 The ISO may, as an independent and knowledgeable neutral entity, help to implement reliability standards and set grid codes better reflecting the economic trade-off b...
AI summary The text discusses the role of an Independent System Operator (ISO) in establishing reliability standards and grid codes. It highlights the ISO's ability to act as a neutral entity to balance the economic trade-off between investment costs and load served. The document notes that Variable Independent Utilities (VIUs) may face conflicting pressures between maintaining strict reliability standards and ensuring ratepayer affordability, and emphasizes that an independent ISO helps avoid conflicts of interest inherent in entities that own generation or transmission assets.
Benefits and costs of Phase 2 of the creation of IESO-NS - A1.25 The IESO takes on real-time operations roles in Phase 2. Much of the inherent biases and perceived conflicts of interest in operations would be eliminated with independent sy...
AI summary The document discusses Phase 2 of creating the Independent Electricity System Operator Nova Scotia (IESO-NS), focusing on the transition of real-time operations to an independent entity. The primary benefit cited is the elimination of inherent biases and perceived conflicts of interest in system operations. Phase 2 is expected to amplify the benefits of Phase 1 by providing more efficient operations through control room improvements, including roles for scheduling, residual energy system balancing, and settlement.
More efficient transmission and resource investment A1.39 Taking on the operations roles in Phase 2 can further unlock benefits in the core Phase 1 planning roles. Any improvements in operational efficiency may in the long run unlock diffe...
AI summary The text argues that assuming operational roles in Phase 2 can enhance core Phase 1 planning by unlocking operational efficiencies. These improvements could lead to reduced resource investment needs, better utilization of existing transmission infrastructure, and more informed long-term planning. Furthermore, an ISO with advanced system operation processes can facilitate more efficient resource and transmission choices within the Integrated Resource Plan (IRP), promoting a level playing field for diverse technologies like wind, storage, and non-wires alternatives while supporting clean energy goals and reducing system production costs.
Improved application of reliability standards and grid codes A1.43 An ISO taking over the operations role also scales the benefits derived from the supporting roles in Phase 1. With the ISO responsible for operations, it can better set gri...
AI summary The text discusses the operational benefits of an Independent System Operator (ISO) assuming the operations role within a multi-phase framework. It argues that by taking over operations, the ISO can more effectively establish and enforce grid and reliability standards as part of its broader industry governance responsibilities, thereby scaling the benefits derived from supporting roles in Phase 1.
Independence in advice to government and avoided professional services costs - A1.44 Deep technical expertise at the operational level is key to providing advice to government, and the removal of the perception of bias can lead to this adv...
AI summary The text discusses the importance of deep technical expertise in providing reliable advice to the government, emphasizing that removing perceptions of bias is crucial for the advice to be trusted. It highlights that the Market Design role involves creating rules for Schedulers and Balancers. Furthermore, it suggests that the Independent System Operator (ISO) can provide valuable expertise to regulators and the government by gaining a better understanding of operational realities, such as congestion management.
Table A1-1 Benefits and cost categorisation IESO Nova Scotia Role Outcome Benefits (🌼 y quantified in Chapter 4, and corresponding benefit number) CORE Transmission planner and long-term security of supply ■ Reduced risks borne by consumer...
AI summary The document outlines the benefits and costs associated with the roles of IESO Nova Scotia across various phases. Key benefits include reduced risks of cost overruns for consumers, more efficient transmission and resource investment, and improved system expertise. It highlights 'Key Levers' such as timeliness, removal of perceived bias, and increased innovation. Conversely, it identifies costs related to the implementation of separation, additional staffing, reduced decision-making efficiency, and potential loss of synergies and increased transaction costs between asset owners and operators.
$ - × (1- reduction in cost overrun relative to VIU %) - × VIU cost overrun % - × (1- reduced cost overrun passed on to consumers relative to VIU %) - × VIU cost overrun passthrough to customers % - A5.4 To capture the range of outcomes, w...
AI summary The text analyzes the potential cost overrun risk reduction associated with the Independent Electricity System Operator (IESO) compared to the VIU case. It provides estimates for two scenarios: a low-benefit scenario where cost overruns are reduced by 0% (resulting in a 7% cost pass-through to customers) and a high-benefit scenario where cost overruns are reduced by 50% (resulting in a 1% cost pass-through to customers). The analysis notes that these benefits are intertwined with capital cost savings from competitive procurement.
Appendix A Sum of Sum of Sum of Sum of Sum of Sum of Sum of Sum of 0490-125 Nova Scotia Power Incorporated NSPI - TVP Stakeholder Session 0490-128 Nova Scotia Power Incorporated M11588 - NSPI - ELIADC Tariff - 2023 Annual Report Stakeholde...
AI summary Appendix A provides a summary of various regulatory matters involving Nova Scotia Power Incorporated (NSPI). The table lists specific proceedings including the TVP Stakeholder Session, the ELIADC Tariff 2023 Annual Report, the Smart Grid Nova Scotia Project Final Report, the Michelin Waterville Dynamic Voltage Restorer, and the Commercial Net Metering Program 2023 Annual Report. It outlines the scope of work for each matter, such as stakeholder sessions, correspondence review, and compliance reporting, alongside associated costs.
INTRODUCTION The Small Business Advocate (the "SBA") represents small business customers of regulated electricity utilities in Nova Scotia, including Nova Scotia Power Inc. ("NSPI"), Nova Scotia Power Maritime Link Inc. ("NSPML") and Effic...
AI summary The Small Business Advocate (SBA) provides an overview of its regulatory activities for the 2025 calendar year in Nova Scotia. The SBA represents small business customers across three rate classes, advocating for reliability and affordability. Key activities in 2025 included engaging with the newly created Nova Scotia Independent Energy System Operator (IESO-NS), participating in the Wasoqonatl Transmission Incorporated (WTI) NS-NB Reliability Intertie Project, and reviewing various rate applications and plan extensions for Nova Scotia Power Inc. (NSPI), Nova Scotia Power Maritime Link Inc. (NSPML), and Efficiency One (E1).
CONCLUSION 2025 was an incredibly busy year, both before the Board and working in collaboration with NSP, NSPML, El, IESO-NS and WTI, as well as other intervenors. There were extensive consultations, discussions and negotiations with all p...
AI summary The Small Business Advocate (SBA) concludes its 2025 activities, highlighting extensive consultations and negotiations with Nova Scotia Power, NSPML, El, IESO-NS, and WTI. The SBA emphasizes its role in advocating for small business, small industrial, and general rate classes during the energy transition. The report notes the SBA's efforts to reduce ratepayer costs through strategic expert engagement and its commitment to ensuring that the unique needs of these classes are recognized by utilities and the Independent Electricity System Operator.
Small Business Advocate Company Total Hours for SBA and Consultants Sum of Fees for SBA Sum of Costs for SBA Sum of HST for SBA Total Sum for SBA Sum of Fees for Consultants (USD) Sum of Costs for Consultants (USD) Total Sum for Consultant...
AI summary The document provides a detailed breakdown of the Small Business Advocate's (SBA) involvement in various regulatory proceedings. It lists the total hours, fees, and costs associated with both the SBA and their consultants across multiple matters. Key activities include reviewing evidence, filing submissions, and attending hearings for projects such as the Fuel Adjustment Mechanism (FAM) audits, the 2023 Evergreen Integrated Resource Plan, and various grid and battery storage projects.