H-2Appellants Evidence (redacted)
5 passages
Where are they? If the records exist, produce them. If they do not, say so. If they existed but are no longer available, explain what happened to them. 3 Email: NSP to Redmayne 7th July 2026 with attachments (Appendix 3)
AI summary The text requests the production of records related to an email from NSP to Redmayne dated July 7th, 2026, with attachments referenced in Appendix 3. The request covers scenarios where records exist, do not exist, or have been lost.
$9,018.67 backhoe variance that has not been substantiated and recognises the $2,599.42 traffic-control underspend. On that basis, the arithmetic does not produce a smaller additional bill. It eliminates the additional contribution altoget...
AI summary The text discusses an unsubstantiated backhoe variance and traffic-control underspend, resulting in a surplus before HST. It requests NSP to clarify any disputes and provide supporting records if an additional amount is still considered payable.
Line and males with many a male at Labour $11,278.46 Meal Chit(s) $17.00 Materials $6,806.34 Traffic Control $741.36 Backhoe/Excavator/Floating Services $13,771.42 Subtotal $32,614.58 Free Service Allowance $4,925.68 Total Line Extension W...
AI summary The text presents a detailed breakdown of costs associated with a line extension and new service, including labor, materials, traffic control, and other expenses. It also includes HST calculations and a balance owing, indicating a financial transaction related to infrastructure work.
Payment Method: Cheque (20,827.06 + 3124.06 HST= $23,951.12) $20,827.06
AI summary The payment method details a cheque payment of $20,827.06, including HST of $3,124.06, for a total of $23,951.12.
Site Address Total Cost of Line $ 20,827.06 Additional Costs Phone Number Labour $ ‐ Material $ ‐ Work Order Number Contractor Costs $ ‐ 6873680 Engineering Assessment for Water, Highway or Railway Crossing $ ‐ Feeder Number Municipality P...
AI summary The document outlines the total cost of a line installation at a specified site, including additional costs and HST. The total cost is listed as $23,951.12, with HST of $3,124.06 included. The document includes details such as work order numbers, planned design dates, and other related information.