Home›Hearing Procedures›M06319›Evidence
Topic/Matter Intersection

Topic:"Hearing Procedures" in M06319

Matter: P-886 Nova Scotia Power Inc. (NSPI) Rate Application 2007
22 passages 15 documents

Hearing Procedures across all matters →

N-1-aNotice of Application and Direct Evidence - NSPI - REDACTED (Large File - 59 MB) 1 passage
NOTICE OF APPLICATION
any party who has a good faith interest in accessing the confidential information, who would not be otherwise conflicted, and who signs an agreement to maintain the confidentiality of the information. - 12. NSPI also seeks Directions from...

AI summary Nova Scotia Power Inc. (NSPI) is requesting directions from the Utilities and Review Board regarding pre-hearing procedures, including public notice, confidential evidence filing, access to confidential information, interventions, and establishing an issues list. NSPI also seeks a hearing date in January 2007 to allow implementation of any resulting order by April 1, 2007.

N-2-bRIR 76 - NSUARB to NSPI - REDACTED (Large File - 46 MB) 1 passage
Annual General Meeting
Annual General Meeting The Annual General Meeting is scheduled to be held May 9, 2006 at 2:00 p.m. (Atlantic 1ime) at the World Trade and Convention Centre in Halifax, Nova Scotia.

AI summary The document provides the logistics for the Annual General Meeting, specifying that it is scheduled to take place on May 9, 2006, at 2:00 p.m. Atlantic Time. The meeting location is designated as the World Trade and Convention Centre in Halifax, Nova Scotia.

N-2-cRIRs 1 to 39 - CA to NSPI - REDACTED (Large File - 14 MB) 1 passage
5 Questions and Addenda
5 Questions and Addenda The Consultant is urged to carefully examine these Terms of Reference immediately and contact NSPI at once for any items that require clarification. All clarifications deemed by NSPI to be material will be issued as...

AI summary This section outlines the procedural requirements for the Consultant regarding the Terms of Reference. It instructs the Consultant to review the terms immediately and contact Nova Scotia Power Inc. (NSPI) for clarifications. It establishes that only written addenda issued by NSPI will be considered valid and binding, and that any subsequent addenda will supersede previous versions in the event of a conflict.

N-7-bRIRs 142 to 143 - SEB to NSPI - REDACTED (Large File - 45 MB) 2 passages
Listening to Customers
Listening to Customers - Increased investment in conservation - Increased vegetation management to improve reliability - Customer service initiatives - CEO "on the line" explaining request to customers - UARB improving process with "Issues...

AI summary The document highlights a series of customer-centric initiatives and commitments being presented during the regulatory proceeding. Key themes include increased investment in energy conservation, improved vegetation management for system reliability, and enhanced customer service initiatives. Notably, the CEO is actively engaging with customers to explain requests, and the Utility Advisory Review Board (UARB) is refining its process using an 'Issues List' to better address customer concerns.

Business of the Meeting
Business of the Meeting All resolutions placed before the Meeting must be approved by a majority of the votes cast.

AI summary The document outlines the procedural requirement for the Meeting, stating that all resolutions presented must be approved by a majority of the votes cast.

N-14Evidence filed by John Antonuk, Donald T. Spangenberg, Jr. and John B. Adger, Jr. (on behalf of NSUARB) (Large File - 26 MB) 1 passage
U.S. and Canadian Gas Industry Regulation
U.S. and Canadian Gas Industry Regulation Evaluated the fuel-oil and natural-gas supply activities of Nova Scotia Power, Inc. for the Staff of the Nova Scotia Utility and Review Board. Presented testimony to the Board regarding findings in...

AI summary The document outlines various regulatory roles involving fuel-oil and natural-gas supply activities, including testimony to the Nova Scotia Utility and Review Board and analysis of gas cost adjustment mechanisms and portfolio optimization agreements in Connecticut and Ohio.

N-40RIRs Attachment SEB-NSPI - 2d (Large File - 20 MB) 3 passages
RULES AND REGULATION GOVERNING APPLICATION OF ENERGY COST RECOVERY RATE
RULES AND REGULATION GOVERNING APPLICATION OF ENERGY COST RECOVERY RATE These rules and regulations are applicable to and are an integral part of Rate ECR. These rules and regulations established the procedures to be used in the determinat...

AI summary This text outlines the regulatory procedures for determining and adjusting the Energy Cost Recovery factor (ECRF). It establishes a timeline for the Company to submit estimates of energy costs and sales to the Commission. It specifies requirements for public hearings, the Company's burden of proof to justify rate increases based on cost fluctuations, and the notice periods required for proposing new factors to be incorporated into the Company's base rate schedules.

A SOUTHERN COMPANY
A SOUTHERN COMPANY PAGE EFFECTIVE DATE REVISION 5 of6 November, 2001 Billings Second Formal intervention by customers of the Company shall be permitted. The staff of the Commission and formal intervenors shall have the right to examine all...

AI summary The text outlines the formal procedures for determining the Energy Cost Recovery factor. It establishes the rights of Commission staff and formal intervenors to examine Company records, cross-examine witnesses, and submit rebuttal testimony. It specifies that rebuttal testimony must be submitted five days before the hearing. The Commission is required to issue an order for the factor within 35 days of the Company's submittal, with a provision that the Company's proposed factor becomes effective automatically if no order is issued by the 45th day.

Preamble
Wednesday, August 9, 2006 at 10:00 a.m. in Commission Hearing Room 2115, Dobbs Building, 430 North Salisbury Street, Raleigh, North Carolina BEFORE: Chair JoAnne Sanford, Presiding; and Commissioners Robert V. Owens, Jr.; Sam J. Ervin, IV;...

AI summary This text serves as the formal preamble for a Commission Hearing held on August 9, 2006, in Raleigh, North Carolina. It identifies the presiding officers and commissioners of the regulatory body overseeing the proceeding. No substantive arguments, financial data, or policy details are contained in this specific excerpt.

N-44RIRs 144 to 191 - SEB to NSPI - REDACTED (Large File - 10 MB) 1 passage
RESPONSE TO INFORMATION REQUEST
RESPONSE TO INFORMATION REQUEST TO: NSPI FROM: SEB Question IR-170: Please identify parts of draft reports that were changed as a result of feedback from the client and explain the reason for the change. Response IR-170: Please refer to SE...

AI summary The document is a formal response from the Nova Scotia Energy Board (SEB) to Nova Scotia Power Inc. (NSPI) regarding Information Request IR-170. The Board directs the respondent to refer to a previous Information Request (IR-169) to identify specific changes made to draft reports based on client feedback and the underlying reasons for those modifications.

N-47Proof of Advertising - Newspaper Clippings 3 passages
HEARJNG PROCEDURE:
HEARJNG PROCEDURE: HEARING COMMENCES: ~onday, Januar 22 2007 9:00a.m. EVENING SESSION: Wednesday, January 24, 2007 7:00p.m. PLACE: Office of the Board Summit Piace, 3rd Floor 1601 Lower Water Street Halifax EVERYONE is entitled to attend t...

AI summary This document outlines the hearing procedure for a regulatory proceeding, including dates, locations, and procedures for participation. It details how parties can formally present evidence, cross-examine witnesses, or submit written comments.

HEARING PROCEDURE:
HEARING PROCEDURE: HEARING COMMENCES: Monday, January 22, 2007 9:00 a.m. EVENING SESSION: Wednesday, January 24, 2007 7:00 p.m. PLACE: Office of the Board Summit Place, 3rd Floor 1601 Lower Water Street Halifax EVERYONE is entitled to atte...

AI summary The hearing procedure for the proceeding outlines the dates, location, and procedures for participation. Attendees can speak, present evidence, or submit written comments. Formal standing requires notice by October 31, 2006, while those wishing to speak at the evening session must notify the Board by January 5, 2007.

HEARING PROCEDURE:
HEARING PROCEDURE: HEARING COMMENCES: Monday, January 22, 2007 9:00a.m. EVENING SESSION: Wednesday, January 24, 2007 7:00p.m. PLACE: Office of the Board Summit Place, 3rd Floor 1601 Lower Water Street Halifa~ EVERYONE is entitled to attend...

AI summary The hearing procedure outlines the schedule and process for the proceeding, including dates, locations, and procedures for participation. Interested parties must notify the Board by a specific deadline to have formal standing or to speak at the hearing.

57960Board Decision 1 passage
PROPOSED TIMELINE
PROPOSED TIMELINE Date Week No. Actions & Activities February 5 Hearing Order Issued February 19 3 Workshop 1 March 5 5 Filing FAM Proposals by NSPI and Intervenors March 12 6 Workshop 2 March 19- April9 7-10 Discussion April16 11 Workshop...

AI summary The proposed timeline outlines key dates and activities for a regulatory proceeding, including hearings, workshops, and the filing of proposals and evidence. Dr. Stutz will guide the topics discussed during the workshops.

57963Hearing Order 1 passage
ORDER
ORDER BEFORE: ~eter W. Gurnham, Q.C., Chair ~tv~argaret A. M. Shears, Vice-chair ;;·,<0 Kulvinder S. Dhillon, P. Eng., Member ~ UPON READING the Application of Nova Scotia Power Incorporated (the "Company", "NSPI") dated October 10, 2006;...

AI summary The Nova Scotia Utility and Review Board has ordered a hearing for Nova Scotia Power Incorporated's application, setting a detailed timetable for the proceeding, including deadlines for filing interventions, submitting evidence, and conducting the hearing.

57960Board Decision 2 passages
3.7 Findings
ll of the costs of providing safe and adequate service to its customers are prudently incurred and are as low as reasonably possible. There are usually two processes in which NSPI must meet this test. [30] Pursuant to s.35 of the Act, Boar...

AI summary The document outlines the two processes in which NSPI must demonstrate that its capital expenditures are prudently incurred and as low as reasonably possible. These include obtaining Board approval for expenditures over $25,000 and participating in general rate proceedings with evidence, witness cross-examination, and public transparency.

PROPOSED TIMELINE
PROPOSED TIMELINE Date Week No. Actions & Activities February 5 Hearing Order Issued February 19 3 Workshop 1 March 5 5 Filing FAM Proposals by NSPI and Intervenors March 12 6 Workshop 2 March 19- April9 7-10 Discussion April16 11 Workshop...

AI summary The proposed timeline outlines key dates and activities for a regulatory proceeding, including workshops, evidence filing, and hearings. Dr. Stutz will guide the topics discussed during the workshops.

57961Notice of NSPI Rate Application 1 passage
HEARING PROCEDURE:
HEARING PROCEDURE: Hearing Commences: Monday, January 22,2007 9:00a.m. Evening Session: Wednesday, January 24,2007 7:00p.m. .- Place: Office of the Board Summit Place, 3rd Floor 1601 Lower Water Street Halifax EVERYONE is entitled to atten...

AI summary The hearing procedure outlines the dates, times, and locations for the hearing, as well as the process for parties to formally participate, present evidence, or comment on the matter. Notices and submissions must be filed by specific deadlines.

57986Letter - HRM- Re: Late Filed Evidence 1 passage
Section 2
ase that has to be m.et, and to detennine what expert evidence is necessary to meet that case, and to obtain that evidence. The failure to know the case to be met, constitutes a denial of due process. HRM's supports SEB request to extend t...

AI summary The text discusses a regulatory proceeding involving a request to extend the hearing schedule and delay the commencement of the hearing. It highlights concerns about due process, late filing of evidence, and the need for proper preparation and submission of all required documentation by NSPI.

58243Comments on Preliminary Issues List - Halifax Regional Municipality (HRM) 1 passage
Renewable Energy:
Renewable Energy: There are numerous outstanding issues surrounding the future and current impact on electricity pricing. Stakeholders and intervenors such as HRM have been and are continuing to consume considerable resources to effectivel...

AI summary The text discusses the complexity of current and future electricity pricing issues, highlighting the numerous regulatory proceedings involving NSPI and the need for a consolidated approach. It emphasizes the importance of addressing renewable energy as part of the overall electricity management strategy, noting the rising costs of wind turbines and the need for timely decision-making on transmission and distribution system costs.

86472Submission - Re: Future Filing Requirements and comments on Board Draft Strawman 2 passages
A. Statement
A. Statement - 1. The Commission held a prehearing conference in this matter on February 11 , 2004. Appearances were entered on behalf of Aquila, Inc., doing business as Aquila Networks-WPC (Aquila); Staff of the Commission (Staff); the Of...

AI summary The Commission held a prehearing conference on February 11, 2004, and adopted a procedural schedule for the proceeding. Key dates include testimony deadlines, a technical conference, and a hearing. Aquila is required to provide work papers and pay for hearing transcripts. Discovery requests must be resolved by an Administrative Law Judge.

A. The Commission Orders That:
A. The Commission Orders That: - 1. The procedural schedule proposed by the parties to this matter at the pre-hearing conference as articulated above is adopted. - 2. Aquila, Inc., doing business as Aquila Networks-WPC shall provide work p...

AI summary The Commission adopts a procedural schedule for the proceeding, sets deadlines for submitting work papers and discovery responses, and requires parties proposing rate designs to provide cost of service study models and customer impact analyses. The 120-day decision period is extended to 210 days but waived by agreement, with a final decision due by September 3, 2004.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →