102117Responses to Stakeholder TOR Feedback - IESO
15 passages
The term "sustainable" is used throughout the ToR, including in two separate IRP objectives. We understand that the term is used in section 2(e) of the More Access to Energy Act, but the ToR would benefit from a definition of the term, giv...
AI summary The document discusses the need for clearer definitions of terms like 'sustainable' and 'integrated electricity system' in the Terms of Reference (ToR) for the Integrated Resource Plan (IRP). It also raises concerns about the placement of an objective related to updating avoided cost calculations for demand-side resources, suggesting it should be moved or rephrased to align with statutory requirements under the More Access to Energy Act.
this IRP objective to include all resource cost assumptions. The ToR would benefit from additional specificity regarding the pre-IRP studies that have been commissioned by the IESO, which will allow stakeholders to plan their resources for...
AI summary The document discusses revisions to the Terms of Reference (ToR) for the Integrated Resource Plan (IRP), including adding specificity regarding pre-IRP studies, incorporating sensitivities into assumption development, and improving stakeholder engagement language. Stakeholders also raised concerns about meeting participation limits and the need for written requests for information.
EAST COAST ENVIRONMENTAL LAW these categories or, at minimum, consider reductions to their weights in the evaluation process. The ToR would benefit from additional language explaining how the load forecast (and scenarios) will be developed...
AI summary The document discusses feedback on the Terms of Reference (ToR) for an Integrated Resource Plan (IRP), including suggestions to improve clarity on load forecasting, fuel supply considerations, and grid reliability modeling. Responses indicate that these issues will be addressed during the assumption and scenario development phase of the IRP with input from stakeholders and technical working groups.
NRSTOR Question/Comment Response PHP is supportive of the primary objective of the IRP to be the least cost plan. In the previous IRP there were a significant number of scenarios and the IESO has commented on the need to reduce service wit...
AI summary The document discusses the Integrated Resource Plan (IRP) and its focus on creating a least-cost plan. It notes improvements in demand response (DR) capacity and customer enrollment in time-varying rates. The document also highlights the update of avoided costs of DSM and the incorporation of Dunsky's recommendations into the Terms of Reference (ToR).
and seeking feedback from stakeholders on them was to help refine this approach. The Draft TOR states that an additional element of the IRP to "Determine the economic opportunity for domestic use of energy from offshore wind" (p. 10). Econ...
AI summary The draft Terms of Reference (TOR) for the Integrated Resource Plan (IRP) includes an analysis of the economic opportunity for domestic use of energy from offshore wind, which is not a conventional element of an IRP. The TOR should be more explicit about the objective, scope, and methodology of this analysis. IESO Nova Scotia acknowledges that this is the first time incorporating such secondary considerations and that the approach may need to evolve.
Introduction Bates White appreciates the opportunity to provide these comments to the Independent System Operator of Nova Scotia ("IESO") regarding its March 31, 2026 Draft Terms of Reference ("ToR") related to the IESO's 2026 Integrated R...
AI summary Bates White provides comments to the IESO on its March 31, 2026 Draft Terms of Reference for the 2026 Integrated Resource Plan process, addressing eleven areas of concern.
Objectives We appreciate that the listed objectives of the IRP recognize sustainability as a core system need, along with reliability and cost effectiveness. We also appreciate that the listed objectives recognize the need to support the s...
AI summary The text emphasizes aligning the IRP's objectives with sustainability, reliability, and cost-effectiveness, referencing the Environmental Goals and Climate Change Reduction Act and the More Access to Energy Act. It discusses the need to define 'sustainable' in the TOR, citing statutory definitions from the More Access to Energy Act and suggesting broader clarification if needed.
Conclusion Thank you for the opportunity to provide comment on the draft TOR. We look forward to future opportunities to engage in the 2026 IRP process. April 24, 2026 Mark Peachey Director, Regulatory Affairs IESO Nova Scotia mark.peachey...
AI summary The letter from Mark Peachey, Director of Regulatory Affairs at IESO Nova Scotia, thanks the recipient for the opportunity to comment on the draft Terms of Reference (ToR) and expresses anticipation for future involvement in the 2026 Integrated Resource Plan (IRP) process.
Re: IESO Nova Scotia 2026 Integrated Resource Plan ("IRP") Draft Terms of Reference Eastward Energy Inc. ("Eastward") appreciates the opportunity to provide the following comments on IESO Nova Scotia's draft Terms of Reference for its 2026...
AI summary Eastward Energy Inc. provides comments on IESO Nova Scotia's draft Terms of Reference for its 2026 Integrated Resource Plan, signaling engagement in the regulatory process for energy planning in Nova Scotia.
Introduction - The Independent Energy System Operator Nova Scotia (IESO) has initiated its first Integrated - Resource Plan (IRP) which is being carried out over 2026. On March 31, 2026 the IESO shared its - draft Terms of Reference with s...
AI summary The IESO has initiated its first Integrated Resource Plan (IRP) in 2026, sharing draft Terms of Reference with stakeholders and holding a session for comments. EfficiencyOne (E1) provided feedback on the IRP Terms of Reference.
Karl Leuschen Hi IRP Team, Below are my written comments on the Draft Integrated Resource Plan Terms of Reference, submitted ahead of the April 24 deadline discussed at the April 17 stakeholder engagement session.
AI summary Karl Leuschen submits written comments on the Draft Integrated Resource Plan Terms of Reference ahead of the April 24 deadline, referenced in the April 17 stakeholder engagement session. The comments address the ToR for the IRP process.
1701 HOLLIS ST. 12th FLOOR, HALIFAX, NS B3J 3M8 (902) 422-9663 NATURALFORCES.CA IESO Nova Scotia April 24, 2026 1791 Barrington St. Suite 1010 Halifax, NS B3J 3K9 RE: IESO's Draft Terms of Reference To whom it may concern; On behalf of Nat...
AI summary Natural Forces submits comments on the IESO's draft Terms of Reference for the 2026 Integrated Resource Plan, emphasizing that cost assessments should align with asset lifespans, sustainability must be prioritized, and risk evaluation should include factors like fuel price variability and geopolitical risks. It also advocates for broader environmental impact assessments, local economic considerations, and explicit energy security measures.
Nova Scotia Power TOR Section Details/Component NS Power Feedback/ Questions Objectives All objectives listed in the TOR NS Power supports the objectives noted in the TOR. In addition to the near-term resource procurement identification (3...
AI summary Nova Scotia Power supports the objectives outlined in the Terms of Reference (TOR) and recommends using the Integrated Resource Plan (IRP) to identify capital work for existing resources. They also mention the Mersey Hydro System as an example of a decision point for rebuild or partial decommissioning.
Thank you for the opportunity to comment on the draft 2026 IESO IRPTerms of Reference. This is an important first step that sets the agenda for the IRP. While the Terms Of Reference attempt to capture all aspects of the process, there may...
AI summary The commenter appreciates the opportunity to provide input on the draft 2026 IESO IRP Terms of Reference, acknowledging it as a crucial first step in setting the agenda for the IRP. They note that while the Terms of Reference aim to be comprehensive, there may be instances where flexibility is needed to address unexpected issues.
Written Comments on the 2026 Integrated Resource Plan Terms of Reference (dated March 31, 2026 The following key points are provided for consideration:
AI summary The document outlines written comments on the 2026 Integrated Resource Plan Terms of Reference, indicating key points for consideration. Specific details of the comments are not provided in the excerpt.