Topic/Matter Intersection

Topic:"Information Disclosure" in M12438

Matter: EfficiencyOne - 2025 Q2 Demand Side Management (DSM) Report
3 passages 2 documents

Information Disclosure across all matters →

E-1Report 2 passages
11 Table 6: Existing Residential p. p. 17
11 Table 6: Existing Residential EXISTING RESIDENTIAL (2025) Existing Residential Energy Savings (GWh) Demand Savings (MW) Expenditure ($ million) Unit Cost ($/kWh) 2025 Plan as Approved 60.6 10.2 23.6 0.39 2025 Year-end forecast 36.8 10.0...

AI summary The 2025 forecast for Existing Residential energy savings falls below approved targets due to the paused Residential Behaviour program, impacted by NS Power's cybersecurity incident and lack of AMI data. Revised participant savings expectations further reduced energy savings.

Residential Behaviour Highlights p. p. 17
Residential Behaviour Highlights - Residential Behaviour achieved 2.3 GWh of energy savings in Q2, before the program component was paused indefinitely in May 2025 due to a cybersecurity incident at NS Power that has resulted in NS Power b...

AI summary Residential Behaviour achieved 2.3 GWh savings in Q2 before being paused indefinitely in May 2025 due to a NS Power cybersecurity incident blocking AMI data transfers to E1. E1 cannot generate customer reports or measure usage changes without the data, leading to uncertainty in program targets and year-end forecasts. E1 and NS Power are discussing system restoration timelines, but no firm dates exist yet.

99090Letter from E1 re: NS Power's cybersecurity incident affecting residential behaviour program 1 passage
Section 1 p. pp. 0-1
Mr. Stephen McGrath, K.C. Chair, Nova Scotia Energy Board 3rd Flood, Summit Place 1601 Lower Water Street Halifax, Nova Scotia, B3J 3P6 August 21, 2025 Dear Chair McGrath: EfficiencyOne (E1) is submitting this update to the Nova Scotia Ene...

AI summary EfficiencyOne (E1) informs the Nova Scotia Energy Board that the Residential Behaviour Program was suspended due to a NS Power cybersecurity incident disrupting AMI data transfers. Without this data, E1 cannot generate customer reports or track program savings, risking 2025 targets. Discussions with NS Power and the delivery partner focus on cost management and resuming operations once data flows resume.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →