Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $1,648,189
1 passage 1 document

Infrastructure Planning across all matters →

N-1Redacted Work Order 4/30/2010 1 passage
CI 34622 - Upgrade L-8002 p. p. 1
CI 34622 - Upgrade L-8002 The following is a breakdown of costs associated with the Upgrade L-8002 • Administrative Overheads and Interest $237,812 $32,303 • Labour • Materials • Contracts • Total $1,582,587 The major costs for this projec...

AI summary The document outlines the cost breakdown for upgrading L-8002, totaling $1,582,587. Major costs include contracts ($237,812), administrative overheads ($32,303), and materials, which involve replacing 48 poles across 24 structures. Labour and other unspecified costs are also noted.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →