Why do this project now? This project is required to restore overload criteria and provide for further development in this area.
AI summary The project is necessary to address current overload issues and facilitate future development in the area. It aims to restore criteria that ensure system reliability and accommodate growth, which is critical for maintaining infrastructure integrity and supporting expansion efforts.
Why do this project this way? Alternatives to extending this feeder include building a 138kV transmission line and a new substation in Eastern Passage. This item was investigated in th\'l Distribution Planning Study . "Dartmouth 25kV Syste...
AI summary The document outlines alternatives to extending a feeder, including a 138kV transmission line and substation in Eastern Passage, referencing a 2008 Distribution Planning Study. The current approach is deemed the most cost-effective, executed by NSPI and an affiliate under ACE 2010 guidelines.