Matter: CI# 28867 - P-128.10 - NSPI WO - LIN Unit#1 Low Nox Combustion Firing System $3,875,373
4 passages 1 document

Infrastructure Planning across all matters →

N-1Non-Confidential Work Order 7/30/2010 4 passages
Section 28 p. p. 1
CI Number 28867-S266 - LIN UNIT#1 LOW NOX COMBUSTION FIRING SYSTEM Project Number S266 ~Parent CI Number Cost Centre 304 - 304-Lingan 1&2 Prod. Unit Budget Version - 2010 06/06 Forecast Forecast Start 10/01/2007 Operational 01/30/2009 Fina...

AI summary This document outlines a project to install a low NOx combustion firing system on Lingan Unit 1, including baseline testing, equipment installation, modifications, and post-outage performance testing. The project was budgeted with costs spanning from 2007 to 2009.

Preamble p. p. 8
Date: 2007/09/24 Page: 1 of 4 CI Number: 28867 - LIN UNIT#1 LOW NOX COMBUSTION FIRING SYSTEM Parent CI Number: Responsibility: 05270000 - GENERATION SERVICES Cost Centre: 304 - Lingan 1&2 Prod. Unit Project Number: Parent Project Number: A...

AI summary This document outlines a project to install a Low NOx Combustion Firing System on Lingan Unit 1&2, including performance testing, equipment installation, modifications, and staff training. The project is part of a capital initiative with a total cost of $4,149,920, to be completed by 2008/12.

2. Why Do This Project Now? p. p. 16
2. Why Do This Project Now? The projects planned for 2008 on Lingan Unit 1, Point Tupper Unit 2, and Trenton Unit 6 are required for NSPI to comply with provincial regulations in 2009. Continuing the NO x reduction program in 2008 allows N...

AI summary Projects planned for 2008 on Lingan Unit 1, Point Tupper Unit 2, and Trenton Unit 6 are required for NSPI to comply with provincial regulations in 2009. Continuing the NOx reduction program in 2008 aligns with maintenance outages and allows assessment of retrofit performance to determine further investment needs.

The following table provides a summary of the schedule of work included in the three capital projects. p. p. 16
The following table provides a summary of the schedule of work included in the three capital projects. Task Lingan Unit 1 Pt Tupper Unit 2 Trenton Unit 6 Submission to DARB September 2007 Authorize vendor to proceed November 2007 Delivery...

AI summary The text provides a table summarizing the schedule of work for three capital projects, including key milestones such as submission to DARB, authorization to proceed, delivery to site, start of outage, completion of work, and guarantee testing for each project.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →