N-1Joint Use Agreement between NS Power and Bell Aliant
16 passages
(n)Miscellaneous Pole: A miscellaneous pole is a pole placed out of line with the main pole line for the use of other than (e), (g), (h), (i), or (m) outlined in this section. They are placed for the specific needs of one party only and as...
AI summary A miscellaneous pole is defined as a pole placed out of line with the main pole line for specific needs of one party, with the requesting party bearing the associated costs. This definition is referenced in section 2.06.03 (d).
2.02 General Policies (a)Each utility agrees to the policy of one Joint Use Pole Line whenever such joint use is desirable in the judgement of both utilities.
AI summary This section outlines a general policy requiring utilities to agree on the use of joint utility poles whenever such joint use is deemed desirable by both parties involved.
(b)New Construction Along Highways and Streets Whenever feasible along any highway or street, only one pole line is to be built. This also applies to pole extensions beyond existing separate lines.
AI summary The regulation mandates that, whenever feasible, only one pole line should be constructed along highways and streets, including extensions beyond existing separate lines.
(d)Consolidation of Separate Lines In any location where separate and paralleling pole lines now exist, consideration is to be given to consolidating the pole line when it becomes necessary to make major repairs replacements or alterations...
AI summary The document discusses the consolidation of separate and paralleling pole lines in locations where major repairs, replacements, or alterations are necessary, directing reference to Section 2.03.04 for responsibility details.
2.03.03Consolidation of Separate Lines Where the two parties agree to consolidate existing lines, by erecting a new Joint Use Line, the party responsible for erecting the new line shall arrange with the tenant to carry out joint staking. E...
AI summary The document outlines the process for consolidating separate utility lines into a new Joint Use Line, including responsibilities for joint staking, cost allocation, and loss of undepreciated value. It distinguishes this from situations where one party abandons their line to attach to another party's line.
2.04.02 Initial Identification of Pole Requirements The MT&T District Outside Plant Engineering Supervisor/ NSPI Zone Manager initially identify Joint Use requirements for attachments per Section 6.04 - Forecasting; however, it is recogniz...
AI summary The MT&T District Outside Plant Engineering Supervisor and NSPI Zone Manager are responsible for identifying joint use requirements for attachments, though unforeseen requirements may arise that were not previously identified.
2.05.01 General This Section deals with the replacement of existing Joint Use plant. No construction credit will normally be given for this type of work unless the number of poles increase or decrease. This Section includes pole replacemen...
AI summary This section outlines the replacement of existing Joint Use plant, specifying that construction credits are typically not given unless there is a change in the number of poles. Reasons for pole replacement include deterioration, highway relocations, emergencies, tenant requests, owner requirements, and third-party requests.
2.05.02 Initial Identification of Pole Requirements The MT&T District Outside Plant Engineering Supervisor/NSPI Zone Manager initially identify Joint Use Replacement per Section 6.04 - Forecasting; however, it is recognized that certain un...
AI summary The document outlines procedures for identifying and scheduling pole replacement requirements. If requirements were forecasted and approved, work is scheduled accordingly. If not, proposals must be submitted for discussion and approval, ensuring tenants are informed of the owner's intentions.
2.08.02 Scheduled Completion Date All projects require yearly forecasting and scheduling using the Joint Use Forecast form. This process will identify projects and place them in approximate time slots. However, as the target date approache...
AI summary The document outlines the process for yearly forecasting and scheduling of projects using the Joint Use Forecast form, with more specific scheduling required as the target date approaches through the Construction Notification form.
Placing/Replacing Joint Staking - 2 weeks 1 to 3 new poles - 1 week 4 to 10 new poles - 3 weeks 11 to 20 new poles - 14 weeks 21 to 30 new poles - 17 weeks For each additional 10 new poles, add 1 additional week.
AI summary The text outlines the time required for joint staking and placing/replacing poles based on the number of new poles involved, with increasing time needed as the number of poles increases.
(c)Replacements Due to: - I Deterioration of Hazardous Poles - II Consolidation of Separate Lines - III Highway Relocations - IV Emergency Relocations Cannot be Scheduled - V At the Request of Tenant - VI Requirement of Owner - VII Request...
AI summary The document outlines reasons for replacements, including deterioration of hazardous poles, line consolidation, highway relocations, and requests from tenants or owners. It also provides a timeline for joint staking and pole installation based on the number of new poles required.
(a)Principles (Continued) In construction, reconstruction, or additions, if proposing to disturb the ground to install poles or anchors not covered on the original right-of-way, additional right-of-way is to be obtained. Each utility is to...
AI summary The text outlines principles related to the acquisition and management of right-of-way for utility installations. It emphasizes obtaining additional right-of-way when necessary and maintaining records of existing joint rights-of-way to prevent duplication.
(a)New Construction - In sub-divisions, the owner of the line is responsible for coordinating the initial clearing with the subdivider to meet the requirements of both utilities including the removal of danger trees. - For extended service...
AI summary The text outlines responsibilities for line owners and tenants regarding tree clearing and infrastructure adjustments in new construction scenarios. Line owners are primarily responsible for clearing, but tenants may be involved in costs or alternative solutions if requirements exceed standards.
3.10.02 General (Continued) When replacement of existing poles and/or installation of new poles is required, consideration is to be given each case so that the best joint engineering solution results. Where possible, poles should be replac...
AI summary The text discusses the replacement and installation of poles, emphasizing the need for joint engineering solutions and retaining poles in their original locations when possible, particularly for specific types of poles.
2.Due to Renovation of Substandard Poles Where substandard joint use or potential joint use poles are being relocated, replaced or upgraded and where the requirements do not exceed joint use standards, the utility providing the service sha...
AI summary The text outlines the responsibilities of utilities when relocating or upgrading substandard poles, specifying that the utility must bear the cost if requirements do not exceed joint use standards, while customer-owned riser systems are handled according to Section 2.06 when standards are exceeded.
7. Renovations to Riser Systems Only NSPI will be responsible to ensure that all new power related riser systems are installed in accordance with Joint Use Standards. Renovations to power riser systems that do not meet Joint Use Standards...
AI summary NSPI is responsible for installing new power riser systems according to Joint Use Standards and upgrading substandard power risers for safety. Communication utilities are responsible for renovating substandard communication risers, while renovations to risers meeting standards are the responsibility of the requesting party.