Matter: Nova Scotia Power Inc. - CI C0067906 – POA Boiler Refurbishment 2025 – $1,218,254
5 passages 2 documents

Infrastructure Planning across all matters →

N-1Application 1 passage
Document No: XXX-XX-XXXX-XXXX p. p. 6
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Process Industries Required fields: Estimate Classification Project Name: POA Boiler Refurbishment 2025 Started or Preliminary Class 5 Class 4 Class 3...

AI summary This document outlines a checklist and maturity matrix for estimating the cost of the POA Boiler Refurbishment 2025 project. It includes sections on project scope, capacity, location, requirements, and strategy, with defined and preliminary classifications for various deliverables.

N-2NSPI (NSEB) RIR 1 to 5 4 passages
1 Request IR-1: p. p. 12
NON-CONFIDENTIAL 1 Request IR-1: 17 • Install new arrowhead assemblies to restore system integrity and 18 performance. 19 • Ensure all work complies with NS Power's quality and safety protocols, 20 including confined space and hot work sta...

AI summary The text outlines specific requests for installing arrowhead assemblies, ensuring compliance with safety protocols, and engaging specialized contractors for boiler refractory projects at Point Aconi. It distinguishes refractory work from pressure part refurbishment due to differences in scope and processes.

Preamble p. pp. 12-13
- Boiler Tube Failure Reports generated for any failure events that result in unit outages. - Annual Boiler Inspection Reports conducted by NS Power's maintenance contractor under Boiler Asset Strategy Committee supervision. - Header Inspe...

AI summary The document outlines the process for generating and compiling boiler failure and inspection reports, which are used to develop boiler risk profiles. No remedial work is planned for the current year's boiler refurbishment, with major replacements deferred to future projects or treated as operational expenses.

NON-CONFIDENTIAL p. pp. 12-13
NON-CONFIDENTIAL (c) Not Applicable. (d) The budget estimate for the current boiler refurbishment at the Point Aconi Generating Station was developed using historical cost data from prior annual refurbishment projects at the facility, esca...

AI summary The budget estimate for the boiler refurbishment at the Point Aconi Generating Station is based on historical cost data, adjusted for inflation. Annual inspections guide the refurbishment scope, with specific testing and replacement procedures for high-wear and critical components.

Date Filed: August 22, 2025 NSPI (NSEB) IR-4 Page 1 of 1 p. p. 13
Date Filed: August 22, 2025 NSPI (NSEB) IR-4 Page 1 of 1 1 Request IR-5: 2 3 Reference to 2025 10-Year System Outlook (M12386), page 17 of 64 (Figure 7), NS Power 4 notes that Point Aconi will be retired on 2029/2030. 5 6 (a) How does the...

AI summary The document outlines a request for information regarding NS Power's boiler refurbishment at Point Aconi Generating Station and its alignment with the 80% renewable energy generation goal by 2030. NS Power responds that the refurbishment ensures safe and reliable operation through the station's planned retirement in 2029/2030, supporting system reliability during the energy transition.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →