N-1Dispatch Study Action Plan – Quarterly Update – Q3 2025 3 passages
March 2025 update: p. p. 6
March 2025 update: - Extensive Vendor Contracting caused schedule delays - Schedule impact = 3 months - Economic Dispatch Optimization and System Dispatch Dashboard workstreams combined

AI summary The March 2025 update highlights that extensive vendor contracting has caused a 3-month schedule delay, with the Economic Dispatch Optimization and System Dispatch Dashboard workstreams being combined.

Section 14 p. pp. 6-7
- Cybersecurity incident impacted timelines. - Recovery activities underway. - Advanced elements of technical development (SCADA/Generation Platform) - Advanced Test development and training deployment materials. - \ New Infrastructure req...

AI summary A cybersecurity incident has impacted project timelines and recovery activities are underway. The project schedule has been re-drafted but remains subject to change depending on vendor reconnection dates and progress in restoring core technology solutions within NS Power's IT infrastructure.

Economic Dispatch Optimization Timeline Elements p. pp. 10-11
Economic Dispatch Optimization Timeline Elements In the event of slippage of the recovery dependencies (actual vendor reconnection dates and critical cyber incident restoration resources and overall progress in restoring the core technolog...

AI summary The document discusses the Economic Dispatch Optimization Timeline Elements, including potential project plan impacts due to slippage in recovery dependencies, such as vendor reconnection dates and cyber incident restoration within NS Power's IT infrastructure. The impacts are estimated in monthly time increments.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →