Document: 332093 Recommendation Requirements Two Cluster Studies Per Year System Upgrade Cost Allocation Will require amendments to the SGIP and Cluster Study Cost Allocation corresponding NSEB approval. ISO Penalty Structure Will require...
AI summary The document outlines several recommendations for the System Upgrade and Cluster Study Cost Allocation, requiring amendments to the SGIP and NSEB approval. IESO NS plans to consult stakeholders in 2026 and submit revised SGIP to the Board by December 2026, with an interim agreement with NS Power expected by Q1 2026.
on IESO NS's expectation that an interim agreement between IESO NS and NS Power about respective responsibilities for administration of various interconnection processes would be finalized in Q1 2026. In its filing, the SBA provided commen...
AI summary The SBA provided comments on IESO NS's plan to implement Concentric recommendations with exceptions and highlighted concerns about cost inclusion, lack of a transmission capacity heat map, and the need for stakeholder workshops. IESO NS responded to these comments on May 6, 2026.
- Regarding cluster studies, IESO NS clarified its intent to "reserve the ability to conduct more than two cluster studies a year, not less, based on the number and nature of Interconnection Requests (IR) received in a study window". It al...
AI summary IESO NS discusses its approach to cluster studies, transmission capacity mapping, study deposits, penalty structures, and interim agreements with NS Power. It highlights the flexibility in conducting cluster studies, the shift from heat maps to alternative solutions for transmission capacity, and the need to align study deposits with actual costs. It also mentions plans for SGIP amendments and stakeholder consultations in 2026.