N-10NSPI (NSEB) RIRs 1-25 - Redacted
3 passages
4 Project: MV90 Restoration sk Name → Duration → Start → Finish → % Complete → ▲ MV90 Restoration 380 days Thu 5/1/25 Wed 10/14/26 67% ▷ Initiation 5 days Thu 5/1/25 Wed 5/7/25 100% ◆ Release 1 - MOC - MV90 for analog meter data retrieval...
AI summary The MV90 Restoration project, managed by NSP, involves multiple phases including initiation, planning, execution, and integration with the CIS. The project is 67% complete, with some phases fully completed and others ongoing.
7 Project: Grid Model Management Restoration ask Name → Duration → Start → Finish → % Complete 175 days Mon 11/3/25 Fri 7/3/26 88% Initiation 5 days Mon 11/3/25 Fri 11/7/25 100% Planning & Design 60 days Mon 11/10/25 Fri 1/30/26 100% Relea...
AI summary The Grid Model Management Restoration project is 88% complete, with key phases including Initiation, Planning & Design, and two Releases (ArcGIS and ArcFM Designer) that are 75% complete. The project is scheduled to finish in July 2026.
10 Project: OpenView / ActiVu Restoration Task Name ▼ Duration → Start ▼ Finish ▼ % Complete ▼ ■ OpenView / ActiVu Restoration 145 days Mon 11/3/25 Fri 5/22/26 92% Initiation 5 days Mon 11/3/25 Fri 11/7/25 100% Planning & Design 20 days Mo...
AI summary The OpenView / ActiVu Restoration project is 92% complete and is scheduled to finish on May 22, 2026. The project is divided into several phases, with the Initiation and Planning & Design phases completed, and the Release 2 - Execution & Build (ActiVu) phase currently at 80% completion.
N-23M12835 Exhibit N-2 Att 3 2025 Managements Discussion AnalysisHIGHLIGHTED
4 passages
INTRODUCTION AND STRATEGIC OVERVIEW NSPI is a vertically integrated regulated electric utility. It is the primary electricity supplier in Nova Scotia, Canada. NSPI has $8.1 billion of assets and provides electricity generation, transmissio...
AI summary NSPI is a major regulated electric utility in Nova Scotia with significant generating and transmission assets. It has diversified its energy mix, with over 40% of sales from renewable sources in 2025 and a significant reduction in solid fuel generation. NSPI has also invested in grid-scale battery storage and has contracts for renewable energy from independent producers and COMFIT participants.
Nova Scotia Energy Reform Act: On October 15, 2025, the Nova Scotia Independent Energy System Operator ("IESO Nova Scotia") announced that the organization will be phased in over two phases during an 18-month period. On December 1, 2025, t...
AI summary The Nova Scotia Independent Energy System Operator (IESO Nova Scotia) is being phased in over an 18-month period, with the first phase completed in December 2025 and the second expected in 2027. This transition follows the enactment of Bill 404 - Energy Reform (2024) Act in April 2024, which established the Nova Scotia Energy Board (NSEB) and initiated the transition to IESO Nova Scotia.
Supply Chain Risk NSPl's ability to meet customer energy requirements, respond to storm-related disruptions and invest in capital in a cost-effective and timely manner are dependent on maintaining an efficient supply chain. Domestic and gl...
AI summary NSPI's ability to meet energy demands, manage disruptions, and invest in capital is dependent on an efficient supply chain. Supply chain issues, trade restrictions, inflation, labor shortages, and international conflicts could delay deliveries, increase costs, or cause shortages of critical materials and resources.
Technology Risk NSPI relies on various technology systems to manage operations, including increasing reliance on IT solutions operated by third parties, such as software as a service and third party cloud hosting. This subjects NSPI to inh...
AI summary NSPI faces technology risks due to reliance on third-party IT systems and the rapid evolution of AI. These risks include operational disruption, increased vulnerability to cyberattacks, and potential failure to integrate AI effectively, which could lead to adverse outcomes. The company's digital transformation strategy involves significant investment in emerging technologies, increasing project risks.
100856NS Power's Monthly Update #5 (M12273)
4 passages
Additional Capabilities NS Power continues to expand access to real-time operational data, with progress made in restoring the plant information systems and onboarding users for access. Connections have now been established for several gen...
AI summary NS Power is enhancing real-time data access, restoring reporting systems, and rebuilding operational applications. Progress includes establishing connections for generating assets, restoring critical reports, and advancing asset management and fuel management systems to support decision-making and operational oversight.
Recovery Timeline NS Power remains focused on restoring its most critical business functions by continuing to rebuild and stabilize the supporting technologies and infrastructure that enable them. Over the past month, significant progress...
AI summary NS Power is focused on restoring critical business functions by rebuilding infrastructure and technology platforms, with progress made in data integration, networking, and disaster recovery. System restoration is expected to continue through 2026, prioritizing operational needs and long-term resiliency.
— PROGRAM ST DUCTIOE — РКОВКА М ЗТ RUCIURE — The Restoration Program is structured into five (5) key portfolios of work – focusing on restoring business capabilities. Portfolio Scope Summary Enterprise Resource Planning (ERP) Recovery and...
AI summary The Restoration Program is divided into five key portfolios: Enterprise Resource Planning (ERP), Customer, Additional Capabilities, Cybersecurity, and Technology Enablement, each focusing on restoring critical business systems and operations.
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Enterprise Resource Planning (ERP) PowerPlan Pow...
AI summary The document outlines adjustments to the completion timelines of various projects, including PowerPlan, AMI HES, ADMS Resiliency, Aligne Fuels & PI, and Self-Serve Analytics & Bl. The changes are attributed to additional scope, resourcing constraints, and planning activities.
101623NSPI Monthly Update Report #7 (M12273)
3 passages
Technology Enablement Foundational technology restoration continued through staged delivery and operational readiness activities across backup and disaster recovery, compute, and network domains. During the reporting period, infrastructure...
AI summary The Technology Enablement section outlines ongoing efforts in foundational technology restoration, including backup and disaster recovery, compute, and network domains. Activities such as infrastructure configuration, validation, and network modernization are progressing under established governance processes.
PROGRAM STRUCTURE The Restoration Program is structured into five (5) key portfolios of work – focusing on restoring business capabilities. Portfolio Scope Summary Enterprise Resource Planning (ERP) Recovery and restoration of core enterpr...
AI summary The Restoration Program is organized into five key portfolios: Enterprise Resource Planning, Customer, Additional Capabilities, Cybersecurity, and Technology Enablement, each focusing on restoring critical systems and operations.
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Additional Capabilities Aligne Fuels / Pi Projec...
AI summary The completion timelines for two projects, Aligne Fuels/Pi and Adept, have been adjusted. The Aligne Fuels/Pi project was delayed due to testing and configuration issues, while the Adept project's delay is due to vendor availability.
102373NSPI Monthly Update Report #9 (M12273)
4 passages
Technology Enablement Foundational technology capabilities have progressed through staged enablement into full operational use, effectively supporting broader restoration and stabilization efforts across dependent services. Core infrastruc...
AI summary The document discusses the progress of foundational technology capabilities, which have moved into full operational use, supporting restoration and stabilization efforts. Core infrastructure services are established, and remaining capabilities have completed validation and transitioned into operational readiness. Integration and optimization activities are ongoing, with a focus on reliability and governance.
Recovery Timeline The recovery program continues to be delivered through structured governance, phased sequencing, and ongoing validation, enabling consistent and coordinated progress across all workstreams. Strong alignment across infrast...
AI summary The recovery program is being delivered through structured governance and phased sequencing, ensuring consistent progress across all workstreams. Replanning activities maintain alignment with validated scope and dependencies, supporting a smooth transition to steady-state operations. Significant progress has been made with high-priority items addressed and service continuity maintained.
PROGRAM STRUCTURE The Restoration Program is structured into five (5) key portfolios of work – focusing on restoring business capabilities. Portfolio Scope Summary Enterprise Resource Planning (ERP) Recovery and restoration of core enterpr...
AI summary The Restoration Program is organized into five portfolios focusing on restoring business capabilities: Enterprise Resource Planning, Customer, Additional Capabilities, Cybersecurity, and Technology Enablement. Each portfolio outlines specific systems and operations to be recovered and restored.
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale System Plan nning System Planning Introduced NA...
AI summary The document outlines adjustments to project timelines, including the transition of IRP Modelling to the IESO-NS and the resolution of an issue related to the Maritime Link Project, with updated reporting by NSPML in its October 15, 2025, Quarterly Report.
103205NSPI Monthly Update Report #11 (M12273)
3 passages
Technology Enablement Foundational technology capabilities remain fully restored and continue to operate as expected. Core infrastructure services, including compute, backup and recovery, and supporting technology platforms, provided relia...
AI summary Foundational technology capabilities are fully restored and operating as expected. Activities focused on routine operations, maintenance, and oversight to ensure service reliability and performance. Governance and operational controls are in place to maintain stability and alignment with business requirements.
PROGRAM STRUCTURE The Restoration Program is structured into five (5) key portfolios of work – focusing on restoring business capabilities. Portfolio Scope Summary Enterprise Resource Planning (ERP) Recovery and restoration of core enterpr...
AI summary The Restoration Program is organized into five portfolios: Enterprise Resource Planning, Customer, Additional Capabilities, Cybersecurity, and Technology Enablement. Each portfolio focuses on restoring critical systems and operations to ensure business continuity and service delivery.
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Dispatch Study Action Plan Quarterly Update Intr...
AI summary The document outlines adjustments to the completion timelines of various projects, including the Dispatch Study Action Plan, Hosting Capacity Map, and others. Some projects are now live or in the Hypercare Phase, with forecasts for restoration of normal activities by late 2026. The timeline changes are accompanied by rationales such as software integration and data requirements.