N-1Application - Redacted
260 passages
1 1.0 EXECUTIVE SUMMARY 2 3 The Nova Scotia Power Incorporated (NS Power, Company) Annual Capital Expenditure (ACE) 4 Plan Application provides customers, the Nova Scotia Energy Board (NSEB, Board), and other 5 stakeholders with a comprehe...
AI summary NS Power's 2026 Annual Capital Expenditure (ACE) Plan Application outlines proposed capital investments totaling $702.1 million, with $284.0 million requested for approval from the Nova Scotia Energy Board. The plan aligns with the 2030 Clean Power Plan and Evergreen IRP Action Plan. The establishment of the Independent Electricity System Operator in Nova Scotia (IESO-NS) has impacted project accountability and planning.
1 • The IG provided comments on the proposed definitions of Scope and Scope Change, noting 2 that they differ from traditional project management terminology and how NS Power has 3 historically defined Scope in capital project applications...
AI summary The Independent Governor (IG) provided feedback on the proposed definitions of 'Scope' and 'Scope Change' within the Capital Expenditure Justification Criteria (CEJC), noting discrepancies with traditional project management terminology and NS Power's historical definitions. NS Power has considered this feedback and clarified that the definition of 'Scope Change' is intentionally limited to changes in stated intent to avoid excessive regulatory filings.
28 Fault Location, Isolation, 1,578,360 5,299,248 1,195,233 4,640,900 Awaiting Approval Service Restoration (FLISR) Implementation
AI summary The text outlines a project titled 'Fault Location, Isolation, Service Restoration (FLISR) Implementation' with associated costs and a status of 'Awaiting Approval'.
MacDonald Dam Access Improvements 963,078 1,547,398 This project is for the construction of an access walkway along the top of the spillway to a low level sluiceway gate for the Hydro Operations team to be able to adjust downstream flow re...
AI summary The document outlines several infrastructure projects related to hydro operations and environmental improvements. These include constructing an access walkway at the MacDonald Dam, building a fish passage at the Tusket Powerhouse, replacing a rubber dam at Lumsden, and decommissioning the Annapolis Tidal Generating Station.
CI# Project Title 2026 Budget ($) Project Total ($) and intermediate pressure steam from the boiler to produce power through the generator. C0082195 LIN2 2025/26 Capacity Requirement 299,478 3,162,203 This project is for the component refu...
AI summary The document outlines several infrastructure and maintenance projects across Nova Scotia's energy sector, including asset refurbishment, replacement of equipment, and system upgrades to ensure operational reliability and compliance with environmental regulations.
1,102,575 1,353,592 This project is for refurbishment of priority areas of the roof at the Sydney Coal Railway Transportation & Rail Maintenance Centre (Rail Centre). Total New Steam Spending for Subsequent Approval 10,402,603 24,560,654 T...
AI summary The text outlines various capital expenditure projects in Nova Scotia, including roof refurbishment, synchronous condensers, transmission tower rerouting, and network upgrades for wind farms. These projects aim to enhance infrastructure and support renewable energy integration.
CI# Project Title 2026 Budget ($) Project Total ($) C0071888 New Tidewater Substation 4,119,741 4,141,223 This project is to build a new Tidewater Substation to address increased residential electricity demand, improve system reliability,...
AI summary The document outlines several capital projects aimed at improving electricity infrastructure in Nova Scotia, including new substations, transformer replacements, and transmission line upgrades to enhance system reliability and meet growing demand.
or the replacement of the 10H-T2 transformer which serves the Victoria General Hospital and the IWK Children’s Hospital in Halifax. C0080108 L-5532 Replacements and Upgrades Phase 1 908,755 2,490,532 This project is for the replacement of...
AI summary The document outlines several transmission line replacement and upgrade projects, including the replacement of the 10H-T2 transformer serving key hospitals, upgrades to L-5532 and L-6043 transmission lines, and network upgrades for the Benjamin’s Mill Wind Farm. These projects are part of ongoing infrastructure planning and investment in Nova Scotia's power grid.
CI# Project Title 2026 Budget ($) Project Total ($) General Plant C0082133 IT - Renew Microsoft Enterprise Agreement 1,800,000 1,800,000 This project funds the on-premises portion of the Microsoft Enterprise Agreement for software assuranc...
AI summary The document outlines several IT and infrastructure projects planned for 2026, including the renewal of Microsoft Enterprise Agreement, implementation of distributed intelligence apps, a DERMS solution, and improvements to the Sydney Depot. Each project includes budget allocations and total project costs.
eliver and manage data integrations in a more timely and cost effective manner. C0047278 IT - Oracle MDM Upgrade 4,684,089 7,949,409 The Meter Data Management (MDM) System is nearing end-of-life and requires an upgrade to maintain vendor s...
AI summary The text discusses the need to upgrade the Meter Data Management (MDM) System and the Advanced Distribution Management System (ADMS) to ensure vendor support, cybersecurity, and compatibility with emerging technologies. These upgrades are part of the 2026 ACE Plan and involve significant financial investments.
iii 2.7 $1,000,000 for which approval is not sought. (As provided in Appendix B) iv Carry-over capital spending. (As provided in Section 7.1) 83.4 v Routine capital spending. (As provided in Section 10) 22.0 Total 2026 Transmission Capital...
AI summary This section outlines the 2026 Transmission Capital Investment Plan, including carry-over capital spending and routine capital spending. It details specific projects such as energy storage, substation upgrades, and transformer replacements with their respective budgets and expenditures.
Bulk Oil (KSO) Breaker Replacements 2023/05 2026/12 859,084 635,204 1,000,004 2,494,292 C0061403 2024/2025 Sacrificial Anode Installation 2024/07 2026/02 2,233,034 142,517 - 2,375,551 C0069238 2025/2026 Steel Tower Refurbishment 2025/12 20...
AI summary The text presents a list of infrastructure projects with associated costs and timelines, including breaker replacements, steel tower refurbishments, and line retirement programs, spanning from 2022 to 2027.
L (Attachments Only) 1 Figure 25: 2026 Distribution Investment by Investment Type 2 (Millions of dollars) Distribution 31.8 8.9 Sustaining 79.2 Customer/Load Driven Regulatory/Compliance Right-of-Way Widening 70.6 3 4 5 Distribution invest...
AI summary The 2026 Distribution investment plan, totaling approximately $190.5 million, is driven by asset management strategies and customer load growth. The investment focuses on sustaining capital, reliability, and regulatory compliance.
8 1,185,364 2,286,083 Replacement C0071954 87W-312 Dauphiness Mill Lake Rebuild 2024/10 2026/06 5,934 500,000 1,259,111 1,765,045 52184 37N-412-Glooscap Trail Rebuild PH2 2017/09 2026/09 786,166 49,303 337,901 1,173,369 C0070787 91W-411 La...
AI summary The table lists various infrastructure projects with their costs and timelines, including replacements and extensions. The document is part of the 2026 ACE Plan and contains confidential information.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 9.0 GENERAL PLANT 2 3 General Plant includes information technology (IT), operational technology (OT), computer 4 infrastructure, vehicle replaceme...
AI summary The 2026 Annual Capital Expenditure (ACE) Plan outlines General Plant investments, which include IT, OT, infrastructure, and communication equipment. These investments support NS Power’s digital transformation, regulatory compliance, and operational resilience, aligning with strategic initiatives like grid modernization and cybersecurity.
/02 2026/12 245,130 164,874 - 410,004 Total Telecommunications 2,038,491 3,508,360 2,866,859 8,413,711 C0061284 IT - OT Cyber Security Control 2023/11 2026/12 1,957,397 1,917,601 2,905,463 6,780,461 Implementation Phase 1 C0047277 IT - GIS...
AI summary The document outlines various IT projects and their associated costs under the 2026 Annual Capital Expenditure (ACE) Plan. These projects span cybersecurity, data migration, customer service improvements, and infrastructure upgrades, with detailed cost breakdowns and timelines provided.
ion Other Thermal $563,050 $537,973 $544,902 $495,729 $5,150,911 $7,592,390 $7,703,116 $6,661,024 Transmission Transmission Substation $4,327,200 $4,375,511 $4,370,346 $4,025,131 Replacement, Add'ns/Mod'ns Primary Equipment Spares $91,829...
AI summary The text presents financial data related to various infrastructure and energy projects, including transmission, distribution, and thermal costs, with figures spanning multiple years. The data includes line items such as equipment replacement, right-of-way widening, and meter upgrades. The document is redacted and contains confidential information.
completed under the routine is like-for-like replacements, the routine is 17 classified as like-for-like. New Customer routines, System Growth and Performance routines 18 (such as heat rate, system improvement, and right-of-way widening ro...
AI summary The 2026 Annual Capital Expenditure (ACE) Plan outlines routine capital spending for transmission substation replacements and modifications, including unplanned replacements, lightning arrestor replacements, and other equipment regaskets. Total projected costs for these activities are $3,122,388.
11 Provincial - Planned Transmission Line $5,680,154 Replacement T020 Transmission Switch & Breaker Replacements Avg Unit 2026 ACE Asset Quantity Price Plan Forecast Switch (<69 kV) 2 25,721 51,441 Switch (69 kV) 7 33,500 234,500 Switch (1...
AI summary The document outlines planned transmission line replacements and upgrades for 2026, including switch and breaker replacements, as well as tower life extension programs. The total projected cost for these activities is approximately $7.9 million.
ill 27 continue to improve the transmission system’s ability to withstand significant weather events 28 where tree fall ins from the edge of the ROW can pose a risk to NS Power’s infrastructure. 18 M07176, NS Power 2016 Annual Capital Expe...
AI summary The text discusses NS Power's efforts to improve the transmission system's resilience against weather events, particularly focusing on risks posed by tree falls near the right-of-way. It references the 2016 Annual Capital Expenditure Plan and the 2026 ACE Plan Reliability Directive for details on progress and future plans.
1 Widening these ROWs mitigates the risk of tree fall ins for the vast majority of trees on the edge 2 of the ROW. 3 4 The increased investment in T010 for the widening of 138kV, 230kV, and 345kV rights-of-way 5 remains consistent with the...
AI summary The document discusses the widening of rights-of-way (ROWs) to mitigate tree fall risks and references the 2016 directive on ROW widening for various voltage levels. It also mentions the 2021 Distribution Routines ATO and the requirement for NS Power to report on routine findings in the 2024 ACE Plan, along with forecasting methodologies for distribution routines.
le installations.) Conversion Work $940,000 5 year plan feeder level Targeted Equipment Replacement $6,668,263 Total D055 Planned Replacement of Distribution Equipment $15,000,016 D020 Padmount Replacements 2,278,256 Distribution Upgrades...
AI summary The document outlines the 2026 ACE Plan and discusses the Board's directives to NS Power regarding the D005 Routine, including improving transparency in forecasting, incorporating historical storm events, and providing details on failed and damaged devices in future filings.
1 New Distribution ROW where areas with no discernable ROW are being cleared to create a ROW 2 with a clearance of 20 feet on the forested side of the line. That program only focuses on areas 3 with no ROW currently, while prior to 2024, D...
AI summary NS Power is expanding the distribution right-of-way (ROW) from 10 to 20 feet on the forested side of the line in areas where no discernible ROW exists. The New Distribution ROW program has been successful, and the goal of 20 feet of clearance is now being applied to all areas where achievable. The costs associated with this work are detailed in Figure 49.
Managed Feeder Length Avg Cost Contract Total Geographic Location Length Cost Section (Km) per Km Overhead Segment Cost (Km) 102W-311 Wedgeport 5.94 5.94 39,600 235,062 33,995 269,057 23W-301 Clyde River 2.65 2.65 39,600 105,071 15,195 120...
AI summary The text provides a detailed table outlining the costs associated with various distribution right-of-way widening projects in Nova Scotia, including geographic locations, lengths, average costs per kilometer, contract costs, and total costs for each project segment.
404,118 58,444 462,562 Total Distribution Right-of-Way Widening 13,223,182 Note: Totals may be slightly off due to rounding. 1 2 Pursuant to CI 49611 - New Distribution Rights-of-Way Phase I, submitted to the Board on 3 November 1, 2016, L...
AI summary The document discusses NS Power's response to Post-Tropical Storm Arthur, including recommendations for managing overgrown distribution rights-of-way and the Board's direction to explore innovative financing options. It references a 2016 ACE Plan and a 2015 Board decision.
82 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) P028 Telecommunication Systems Replace & Modifications Miscellaneous teleprotection equipment upgrades (as required) 35,000 Upgrade misce...
AI summary The 2026 ACE Plan includes various telecommunication system upgrades and replacements, such as radio links, fiber optic equipment, network monitoring, and tower lighting, with associated costs ranging from $6,600 to $127,059 for different projects.
82 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 Figure 53: Computing Asset Management 2026 ACE Plan Forecast P010 SCADA Improvements This forecast is developed based on SCADA equipmen...
AI summary The text discusses the 2026 Annual Capital Expenditure (ACE) Plan, specifically focusing on SCADA (Supervisory Control and Data Acquisition) improvements under P010, with a forecasted cost of $120,428.
P031 NS Power IT Infrastructure Volume to Infrastructure Component Asset Management Plan be Refreshed Voice and Data Network Network Infrastructure & Equipment 100,000 Physical Security technology (Cameras, Physical Security 70,000 DVRs, C...
AI summary The document outlines the IT infrastructure components of NS Power, including network infrastructure, physical security systems, servers, power supplies, and personal computing devices, along with their associated costs for refreshment and replacement.
sions from the emitting fleet. 27 28 Figure 56 compares the capital investment forecast in the 2026 ACE Plan for NS Power’s thermal, 29 natural gas, and biomass generation units to the Evergreen IRP capital investment forecast. When 30 com...
AI summary The text compares the 2026 ACE Plan's capital investment forecast for NS Power's thermal, natural gas, and biomass generation units with the Evergreen IRP capital investment forecast, highlighting differences between a single year or subset of years in the ACE Plan and a long-term planning exercise.
1 Criticality and Condition values are typically influenced predominantly by the factors discussed 2 previously and assigned accordingly. However, other factors may also influence the rating of a 3 project. 4 5 Multiple influencing factors...
AI summary The document discusses how project ratings are influenced by various factors and the role of professional judgment in evaluating them. It also outlines the forecasted capital expenditures from 2026 to 2030, including sustaining capital and notable investments, while acknowledging that these projections may change due to external factors and regulatory directives.
3.2 17.2 30.1 30.0 - Distribution: Distribution R.O.W Widening 31.8 32.4 33.1 33.7 34.4 Transmission: Transmission R.O.W Widening 3.3 3.0 3.0 3.0 3.0 ECEI - Energy Storage 44.2 (3.3) - - - ECEI - Synchronous Condenser 84.7 115.3 91.3 46.7...
AI summary The text presents capital expenditure figures across various sectors including distribution, transmission, generation, and energy storage as part of the 2026 Annual Capital Expenditure (ACE) Plan. These figures highlight investments in infrastructure and energy initiatives, with specific allocations for projects such as Energy Conservation and Efficiency Initiative (ECEI) and the Wreck Cove LEM.
criticality and condition inputs. Specifically for distribution feeders, the criticality assessment 28 includes factors such as usage (kWh sales), regulatory consequences, customer count, redundancy, 29 and ease of access. The condition sc...
AI summary The text outlines the methodology for assessing the criticality and condition of distribution feeders, incorporating factors like usage, regulatory consequences, and customer count. It references specific regulatory decisions and documents related to the 2026 Annual Capital Expenditure Plan.
1 Within the 2026 ACE Plan, the Distribution projects included for approval (as well as previously 2 identified projects in progress), and associated risk rating inputs are provided in Figure 58 below. 3 4 Figure 58: 2026 ACE Plan Distribu...
AI summary This section outlines the 2026 Annual Capital Expenditure (ACE) Plan, specifically focusing on distribution projects for approval, including their risk ratings and condition inputs. The table lists several projects with details such as criticality, load balance, outage frequency, and vegetation conditions. Some projects are still in progress, and updates to condition scores will be provided in future ACE Plans.
class poles across the Utility’s four operating regions, and to provide a post 24 storm evaluation to determine pole status, survival rate, impact on customer 25 outages, and whether the upgraded class improved the resilience of the 26 woo...
AI summary The document discusses the need for pole upgrades across NS Power's operating regions to enhance resilience against severe weather and climate change. It references the 2026 ACE Plan and Appendix G of the Five-Year Reliability Plan Update, which outlines reliability strategies and directives.
and duration of outages caused by failed 29 equipment when compared to recent history. These years were also the most challenging years for 30 severe weather events. The increase in failed primary aerial conductors is believed to be attrib...
AI summary The 2026 ACE Plan discusses the impact of severe weather events on infrastructure reliability, noting increased failures in primary aerial conductors due to high wind stress. However, NS Power's targeted asset investments have improved equipment reliability, with 2025 showing a positive trend in reducing customer interruptions.
1 All distribution capital projects and routines that replace deteriorated equipment are aimed at 2 sustaining or improving system reliability and contribute to the reduction of customer impacts due 3 to device failures referenced in the t...
AI summary The document discusses NS Power's efforts to improve system reliability through capital projects and storm response, addressing the impacts of changing weather patterns and climate risks. It outlines the use of the 2.5 Beta Method for classifying storm events and highlights the current performance metrics and capital programs for 2026.
9 Foreign Interference 10,087 0 0 4.03% Total 250,026 0 0 1 2 Over 20 percent of all identified event day outage hours in 2025 have been caused by tree contacts. 3 Furthermore, a significant portion of events coded as adverse weather are l...
AI summary The text highlights that over 20% of event day outage hours in 2025 were caused by tree contacts, emphasizing the need for continued investment in vegetation management and right-of-way widening. Several capital projects are identified to address these issues in 2026.
1 • L-6511 was substituted by L-6002, L-6503 2 3 The following progress was made on distribution widening under D010: 4 5 • 62 percent of planned 2025 work has been completed as of October 31, 2025 6 • 80 percent completion is forecast for...
AI summary Progress on distribution widening under D010 shows 62% completion as of October 31, 2025, with 80% expected by year-end. Increased vegetation management costs are attributed to higher traffic control, labor, and expanded scope of work, including enhanced fire monitoring and targeting specific tree species to mitigate risks from wind events.
1 Plans for Replacement of Aging Energy Delivery Equipment & Storm Performance 2 3 The 2015 ACE Plan Terms of Consensus included two commitments with respect to reliability: 4 5 (4) As part of the reliability directive in future ACE Plans,...
AI summary The 2015 ACE Plan Terms of Consensus required NS Power to provide more detailed information on its plans for replacing aging transmission and distribution equipment, including asset descriptions, strategic goals, and inspection data, as recommended by the SBA's consultant, Mary Neal.
30 20 10 0 Age Group 2 3 4 • Expected useful life of 50-60 years depending on the transformer type, utilization, and 5 environmental conditions. 6 7 • Age Demographics – 43.8 percent of Transformers are beyond 50 years of service and 28.3...
AI summary The document discusses the aging of transformers in the electrical grid, noting that 43.8% are over 50 years old and 28.3% over 60 years old. It estimates annual replacements at 7-9 units and highlights that proposed 2026 investments will increase the proportion of aging transformers. Proactive replacement strategies and programs like the transformer spares and mobile substation programs are planned.
300 200 100 0 Age Group 2 3 4 • Expected useful life of 55-65 years depending on the conductor design and environmental 5 conditions. 6 7 • Age Demographics – 36.6 percent of conductor is beyond 55 years of service and 16.3 8 percent beyon...
AI summary The document discusses the aging of transmission conductor assets, noting that 36.6% of conductor is beyond 55 years of service and 16.3% beyond 65 years. The expected useful life is 55-65 years, with a projected increase in the number of assets beyond these ages due to planned capital investments in 2026.
N REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 Figure 86: Padmount Transformer Age Profile Padmount Transformer Age Profile 900 Number of Padmounts in Age Group 800 700 2025 Age Profile 600 500 2026 Age Profile 400 300 200 100 0
AI summary The document presents a padmount transformer age profile for 2025 and 2026, showing the number of transformers in different age groups. This data is likely used for planning capital expenditures and infrastructure upgrades.
1 11.1.6 CIS Replacement Project – Status Update 2 3 The Board’s letter dated October 1, 2025 pertaining to a customer DRO appeal provided the 4 following directive: 5 6 NS Power is directed to include specific updates about its Customer I...
AI summary The NSEB has directed NS Power to include updates on the CIS Replacement Project in its Annual Capital Expenditure filings until the project is completed. The current CIS, installed in 1997, is no longer supported and poses significant technological risks despite recent upgrades.
2026 Transmission Plant Land Rights - Easements 1.26% Station Equipment 2.14% Towers & Fixtures 1.26% Poles & Fixtures 4.32% Overhead Conductors & Devices 1.96% Underground Conduit 1.53% Underground Conductors & Devices 2.61% Roads, Trails...
AI summary The text outlines the distribution of costs across various components of the Transmission and Distribution Plant, including land rights, equipment, and infrastructure, with percentages allocated to each category.
2026 ACE Plan C0080206 Page 2 of 5 JUSTIFICATION: Justification Criteria: Thermal Sub Criteria: Equipment Replacement/ Refurbishment Why do this project? NS Power conducts condition and risk assessment and analysis based on the annual boil...
AI summary NS Power is proposing the replacement of boiler components such as tubes, tube shielding, and tube locks to enhance system reliability, mitigate the risk of unplanned outages, and ensure safe and cost-effective operation. The project is necessary due to the increased risk of failures from degraded components and the potential for higher costs from emergency repairs.
ficient, and cost-effective operation of the boiler, while supporting sustained asset integrity and reliability of the asset and maintaining the operating license compliance. Why do this project now? The inspection, refurbishment, and repl...
AI summary The project involves the inspection, refurbishment, and replacement of boiler tubes and tube shields during scheduled outages to ensure safe, efficient, and reliable operation while maintaining compliance with industry standards. This is necessary due to the high temperatures, pressures, and abrasive conditions these components operate under, which make regular maintenance essential.
General Project Data A. Scope Non-Process Facilities (Infrastructure, Ports, Pipeline, Power Transmission) Defined (D) P P D D D Project Scope of Work Description Preliminary (P) P P Byproduct and Waste Disposal Defined (D) NR P D D D Site...
AI summary The document outlines general project data, including scope, capacity, location, requirements, and technology selection for infrastructure and power transmission projects. It categorizes elements as defined (D), preliminary (P), or not required (NR).
onmental Monitoring Not Applicable (NA) NR NR E. Technology Selection Process Technology Not Applicable (NA) F. Strategy Contracting/Sourcing Defined (D) NR P D D D Escalation Defined (D) NR P D D D G. Planning Logistics Plan Preliminary (...
AI summary The text outlines various project planning and management aspects, including technology selection, contracting strategies, logistics planning, and regulatory approvals, with statuses ranging from defined to preliminary.
NR P Start-up & Commissioning Plan Preliminary (P) NR P P/D H. Studies Environmental Impact/Sustainability Assessment Not Applicable (NA) NR Environment/Existing Conditions Not Applicable (NA) NR Soils & Hydrology Not Applicable (NA) NR Te...
AI summary The document outlines the status of various technical deliverables for a project, including the completion of equipment data sheets, process flow diagrams, and design specifications, with some items marked as not applicable or preliminary.
Complete (C) NR S/P C C C Electrical One-Line Drawings Not Applicable (NA) NR General Equipment Arrangement Drawings Complete (C) NR S/P C C C Instrument List Complete (C) NR S/P C C C Piping & Instrumentation Diagrams Complete (C) NR S/P...
AI summary The document outlines the status of various technical and construction-related deliverables for a project, indicating completeness, preliminary status, or not applicable status for different categories such as drawings, permits, and schedules.
ment 2026 Start Date: 2026/08 In-Service Date: 2026/10 Final Cost Date: 2027/04 Function: Steam Forecast Amount: $1,024,385 DESCRIPTION: This project will replace refractory components in the Point Aconi boiler system, following inspection...
AI summary This project involves replacing refractory components in the Point Aconi boiler system to ensure safe and efficient operation, reduce thermal losses, and prevent unplanned outages. The work includes key areas such as cyclones, combustor-to-cyclone crossover ducts, and lower combustor sections, with a forecasted cost of $1,024,385.
100% 100% 80% 80% 73% towards Class Estimate Comments: This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 80% of Class 3 deliverables are completed. A contingency value of 10% was sel...
AI summary The TUC Shoreline Sheetpile Refurbishment project involves installing an 80-meter sloped rock revetment to address deteriorated steel sheet pile structures at the Tufts Cove Generating Station. The project is part of the 2026 ACE Plan with a forecast cost of $5,691,466, and a contingency of 10% has been included to account for risks such as material cost volatility and potential scope changes.
t has the highest total score among the 3 design options in the chosen weighted criteria which included design criteria, operational impacts, regulatory considerations, and probable cost. In addition: a. The design was the most simple and...
AI summary The rock revetment design option was selected due to its simplicity, lower environmental impact, and longer service life compared to other options. It requires less maintenance and has a 50-year design service life, whereas the retaining wall option has a shorter lifespan and higher maintenance needs.
Project Cost Estimate Input Checklist and Maturity Matrix General Construction Required fields: Estimate Classification Project Name: TUC Shoreline Sheetpile Refurbishment Started or Preliminary Class 5 Class 4 Class 3 Class 2 Class 1 Matu...
AI summary The text presents a Project Cost Estimate Input Checklist and Maturity Matrix for the TUC Shoreline Sheetpile Refurbishment project. It outlines the project's scope, capacity, location, and requirements, with classifications for estimate maturity levels and required fields.
D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Defined (D) NR P D D D Stakeholder Consultation/Engagement/Management Plan Preliminary (P) NR P Work Breakdown Structure (WBS)...
AI summary The text outlines various project deliverables and their status, including the Project Schedule, Regulatory Approval, Risk Register, and Environmental Impact Assessments. It indicates the status of deliverables as Defined (D), Preliminary (P), Not Applicable (NA), or Complete (C) and includes notes on stakeholder engagement and technical specifications.
Complete (C) NR S/P C C C Electrical One-Line Drawings Not Applicable (NA) NR General Equipment Arrangement Drawings Complete (C) NR S/P C C C Plot Plans/Facility Layouts Not Applicable (NA) NR Room Classification Datasheet Not Applicable...
AI summary The text outlines various documentation requirements and statuses for different project components, including drawings, plans, and permits, with statuses such as 'Complete (C)', 'Not Applicable (NA)', 'Preliminary (P)', and 'P/C'. It provides a structured overview of the project's documentation needs.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0021608 Attachment 1 Page 3 of 34 C. Lebans Page 3 The remainder of the SSP wall in this area has been largely untouched and was observed during a condition assessment in October 2...
AI summary The document discusses the poor condition of an SSP wall in a coastal area, noting corrosion due to seawater exposure. An inspection in October 2022 identified the need for remediation to ensure structural stability. Corrosion is particularly severe in the splash zone and around low water areas.
otection called an Impressed Current Cathodic Protection system was noted to be installed at the SSP wall location which acts by energizing the wall with electrical current using a continuous power Page 4 Date: December 12, 2025 Page 161 o...
AI summary The document discusses the installation of an Impressed Current Cathodic Protection system at the SSP wall location to prevent corrosion. It also outlines the original design specifications and thickness of the PS28 flat web sheet piles used in the construction of the cells.
have no capacity for any significant loading acting on the top portion of the cells where the corrosion is the greatest, and the remainder of the cell below the mid tide zone has compromised capacity. It should be noted that while most sev...
AI summary The document discusses corrosion issues on the SSP circular cell wall, noting significant corrosion on the seaward face and potential corrosion in the buried portion. CBCL has proposed three remediation options with concept drawings and cost estimates, though detailed design is required due to limited site information.
nfirm final configurations. Design Criteria To develop these options, CBCL has established the following design criteria, based on NPSI’s requirements and typical designs of similar structures: Table 1 - Proposed Design Criteria Criteria V...
AI summary The document outlines the design criteria for a structure, including a 50-year design life, surcharge loading, and deck elevation. It notes that the proposed deck elevation does not account for sea level rise, which may impact the site during detailed design.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0021608 Attachment 1 Page 9 of 34 C. Lebans Page 9 Demolition & Removals The condition survey noted that the top portion of all SSP cells is highly deteriorated, and it is recommen...
AI summary The document discusses the condition of SSP cells and the need for temporary support and removal of piping and parts of the wharf access bridge during repairs. It also outlines Option 1, which involves installing a new anchored combi-wall to replace the existing SSP wall.
l. If it is determined that driving conditions are more favorable, it may be possible to omit the king piles and construct the wall of SSP Z-panels, resulting in lower overall project costs. To achieve a 50-year design life, it is expected...
AI summary The text discusses potential construction modifications for a project involving the installation of a combi wall and the extension of a cold-water intake. It outlines options for reducing costs by omitting certain components and using alternative materials. The proposed design includes measures to ensure a 50-year lifespan and prevent corrosion.
2026 ACE Plan C0021608 Attachment 1 Page 12 of 34 C. Lebans Page 12 Figure 11 - Option 1 TUC3 Intake Extension In summary, this option would provide a brand-new structure that will have a service life of 50 years, with minimal maintenance...
AI summary The 2026 ACE Plan discusses two options for infrastructure improvements: Option 1 involves a new structure with a 50-year service life but may require additional regulatory steps due to seabed encroachment. Option 2 proposes a concrete retaining wall and partial cell encapsulation to minimize operational disruption.
ated on the top of the SSP cell. To reduce impact on operations, the front of the proposed cantilevered retaining wall will be located to provide sufficient working room around the existing piping. Figure 12 - Option 2 General Arrangement...
AI summary The text discusses a proposed concrete encapsulation project for SSP cells, which will serve as a sacrificial coating to prevent corrosion. Structural analysis of the SSP cells is required to ensure they can resist lateral loads, and reinforcement may be necessary. Installation details include the use of curved formwork, reinforcing mesh, and tremie pipes for concrete placement.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0021608 Attachment 1 Page 14 of 34 C. Lebans Page 14 Figure 13 - Option 2 Typical Section There is some uncertainty regarding the long-term viability of this option. The existing S...
AI summary This document discusses the potential vulnerabilities of existing SSP (Steel Sheet Pile) cells in a proposed infrastructure project. There is uncertainty about their long-term viability, particularly concerning corrosion in the buried portion of the cells. An investigation into the current condition of the buried portion is recommended before proceeding with detailed design.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0021608 Attachment 1 Page 15 of 34 C. Lebans Page 15 Option 3 – Rock Revetment This option is very similar to the existing rock revetment installed in front of TUC1, TUC2, and TUC3...
AI summary Option 3 involves the installation of a rock revetment with a 700mm median diameter armour rock in two layers at a 1V:2H slope, which would replace the existing SSP wall and reduce the need for maintenance following storm events.
NSPI TUFTS COVE SSP WALL REPAIR MARINE EXISTING CONDITIONS
AI summary The text references a wall repair project at Tufts Cove involving steel sheet pile (SSP) walls under the marine conditions section, indicating existing conditions related to the infrastructure.
CONSTRUCTION A ISSUED FOR REVIEW MAR 9/23 JEF No. Description Date By NSPI TUFTS COVE SSP WALL REPAIR MARINE
AI summary The document references a construction project related to the repair of the Tufts Cove Steel Sheet Pile (SSP) wall, issued for review on March 9, 2023, by NSPI (Nova Scotia Power Incorporated).
CONSTRUCTION A ISSUED FOR REVIEW MAR 9/23 JEF No. Description Date By NSPI TUFTS COVE SSP WALL REPAIR MARINE
AI summary The document references a construction project related to the repair of the Tufts Cove Steel Sheet Pile (SSP) wall, issued for review on March 9, 2023, by NSPI (Nova Scotia Power Incorporated).
Drawing No DRAWING NAME: Y:\HALIFAX\DATA\PROJECTS\2022\220322.00 NSPI TUFTS COVE SSP WALL\44 CAD\03 STRUCT\220322.00-MSK04.DWG LAYOUT NAME: OPTION 2 - NEW RETAINING WALL PLOT DATE: Thursday, March 9, 2023 11:12:16 AM CAD OPERATOR: LULI MSK...
AI summary The text appears to be a technical drawing and related documentation for a construction project, specifically a retaining wall at Tufts Cove, associated with the 2026 Annual Capital Expenditure Plan (ACE Plan) and contract number C0021608. The document is labeled as confidential and partially redacted.
NSPI TUFTS COVE SSP WALL REPAIR MARINE OPTION 2 - ELEVATION AND SECTIONS
AI summary The text refers to a project titled 'Tufts Cove SSP Wall Repair' under the 'Marine' category, with a focus on 'Option 2 - Elevation and Sections'. The document appears to be related to infrastructure planning or maintenance.
NSPI TUFTS COVE SSP WALL REPAIR MARINE OPTION 3 - NEW ROCK REVETMENT
AI summary The document outlines a project titled 'Tufts Cove SSP Wall Repair' under the 'Marine' category, with a specific focus on 'Option 3 - New Rock Revetment'. This suggests a plan for repairing or reinforcing a structure using a new rock revetment.
REMOVED) REDACTED 2026 ACE Plan C0068898 Page 1 of 5 CI Number: C0068898 Title: TUC1 IP LP Last Stage Blade Replacement Start Date: 2025/05 In-Service Date: 2026/06 Final Cost Date: 2026/12 Function: Steam Forecast Amount: $5,215,861 DESCR...
AI summary This project involves the replacement of L-0 blades on the Tufts Cove Unit 1 turbines to ensure safe and reliable operation. The blades are subject to erosion and fatigue, and the project is justified under the Thermal Equipment Refurbishment/Replacement sub-criteria. The estimated cost is $5,215,861, with a projected in-service date of 2026/06.
Defined (D) NR P D D D Escalation Not Applicable (NA) NR G. Planning Logistics Plan Preliminary (P) P P P Integrated Project Plan Not Applicable (NA) NR Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P...
AI summary The text outlines project planning and management phases, including logistics, integrated project plans, project codes of accounts, schedules, regulatory approvals, risk registers, and start-up plans. It also mentions the absence of certain studies like environmental impact assessments and technical deliverables such as block flow diagrams.
6.6 Contracting Entity Purchase order shall be issued to: EthosEnergy Canada, Ltd. 3100 South Sam Houston Parkway East Houston, TX 77047 www.ethosenergy.com 6.7 Terms and Conditions EthosEnergy has attached a copy of our standard terms and...
AI summary The document outlines a contract with EthosEnergy Canada, Ltd. for the TUC2 Stack Coating and Structural Refurbishment project at the Tufts Cove Generating Station. The project involves removing existing coatings, repairing concrete cracks, and applying a two-layer epoxy coating system to extend the asset's life.
e external stack column, and the application of a two-layer epoxy coating system to Unit 2 of the Tufts Cove Generating Station (TUC) concrete chimney stack to restore integrity and extend asset life. The stacks at Tufts Cove Generating St...
AI summary This document discusses the refurbishment of the TUC 2 stack column at Tufts Cove Generating Station, including the application of a two-layer epoxy coating system. The project is justified based on findings from a 2024 inspection that revealed extensive cracking in the stack, necessitating repairs to restore integrity and extend asset life. The asset is classified under the Steam Production Plant – Tufts Cove 2 depreciation class with an estimated life of 25 years.
ware as the environment adjacent to saltwater is known to be corrosive. Core sample analysis revealed extensive multi-dimensional cracking, with some extending through the full thickness of the stack. The inspection report (please refer to...
AI summary The inspection report identified extensive cracking in the TUC2 stack due to freeze-thaw cycling and corrosive environments. The report recommends applying new protective coatings and refurbishing major cracks to prevent further damage and ensure structural integrity. The project is being undertaken now to avoid long-term asset degradation, structural risks, and safety concerns.
asset life of the stack, pose structural integrity risks, and present safety concerns, particularly the potential for material to spall from the stack column at height. Why do this project this way? Removal of existing coatings, targeted c...
AI summary The project involves removing existing coatings, refurbishing concrete, and applying a two-coat epoxy system to restore a chimney stack. This method ensures structural integrity and long-term protection. Contingency planning accounts for weather-related risks, such as wind, rain, and humidity, which could increase costs or delay the project.
Project Cost Estimate Input Checklist and Maturity Matrix General Construction Required fields: Estimate Classification Project Name: TUC2 Stack Coating and Structural Refurbishment Started or Preliminary Class 5 Class 4 Class 3 Class 2 Cl...
AI summary This document outlines a Project Cost Estimate Input Checklist and Maturity Matrix for the TUC2 Stack Coating and Structural Refurbishment project, detailing required fields, project definition maturity levels, and general project data including scope, capacity, location, and requirements.
Defined (D) NR P D D D Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Management Plan Defined (D) NR P D D D Work Breakdown Structure (WBS) Defined (D) NR P D...
AI summary The text outlines various project planning and regulatory documentation stages, including definitions, risk registers, stakeholder engagement, work breakdown structures, and technical deliverables. It highlights the preliminary and defined status of several components, with some items marked as not applicable.
100% 100% 72% 72% 61% Percentage towards Class Estimate Comments: This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 72% of Class 3 deliverables are completed. A contingency value of...
AI summary The document outlines a Class 3 estimate for a project with 72% of deliverables completed. A 20% contingency was applied to cover contractor cost risks. The text includes a redacted inspection report for Unit #2 at Tufts Cove Generating Station, submitted as part of the 2026 ACE Plan.
TABLE OF CONTENTS I. INTRODUCTION II. DESCRIPTION III. INSPECTION FINDINGS / RECOMMENDATIONS IV. PHOTOGRAPHS & COMMENTARY Exterior photos: Photo Numbers: Column North Drop 1-25 Column East Drop 26-46 Column South West Drop 47-69 Date: Dece...
AI summary This document outlines an inspection conducted by Commonwealth Dynamics Limited on the TUC #2 chimney at the Tufts Cove Generating Station. The inspection involved three core extraction drops and focused on assessing the condition of the concrete wall, particularly column cracking and delamination.
fety cable from elevation 0’-0” to elevation 492’-0” Platforms: Four (4) interior platforms (annular space) locations. One (1) 360° CEMS platform at elevation 125’-0”; one (1) partial 180° AOL balcony at elevation 240’-0”; One (1) par- tia...
AI summary This document describes the structural and technical specifications of the Tufts Cove Generating Station Unit #2, including platform locations, breeching ducts, LPS cables, AOL obstruction lights, and access doors. It is part of the 2026 Annual Capital Expenditure Plan (ACE Plan) under contract number C0080134.
2026 ACE Plan C0080134 Attachment 1 Page 16 of 45 NSPI 16 Tufts Cove Generating station. Unit # 2 Job number 2924 13. Elevation 390’ open pocket along the seam at cold joint, likely from original construc- tion, concrete hammer tests hollo...
AI summary This document is part of the 2026 Annual Capital Expenditure Plan (ACE Plan) and includes details about the Tufts Cove Generating Station, Unit #2. It describes structural issues such as cracks, cold joints, and hollow concrete at various elevations along the station.
REDACTED 2026 ACE Plan C0080133 Page 2 of 5 excess of 50,000 hours since its last major inspection and will be due for overhaul in 2027 based on NS Power’s asset management strategy. Completing this project in a planned manner, assessing c...
AI summary The document discusses the planned refurbishment of the Intermediate Pressure (IP) turbine at Tufts Cove 3 (TUC3) during the 2027 outage to ensure continued safe and reliable operation, mitigate risks of unplanned outages, and align with NS Power’s asset management strategy. The project aims to reduce operational risks and maintain system reliability.
025 Page 291 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED 2026 ACE Plan C0080133 Attachment 2 Page 5 of 7 Nova Scotia Power 2026 TUC3 IP Major 1.0 Executive Summary Siemens Energy will be offering the following scop...
AI summary This document outlines the scope of services Siemens Energy will provide for the Nova Scotia Power 2026 Tufts Cove 3 IP Major outage, including pre-planning activities, resource allocation, and specific tasks such as bearing replacement, casing elevation checks, and rotor bore inspection.
Building Floors Not Applicable (NA) Security System Not Applicable (NA) NR/P LEED Certification Level Not Applicable (NA) NR/P Codes and/or Standards Not Applicable (NA) NR Communication Systems Not Applicable (NA) NR Exterior Closure Desc...
AI summary The document outlines various aspects of a project, including building floors, security systems, LEED certification, and communication systems, which are marked as not applicable. It also covers technology selection, contracting, logistics, and project planning, with some elements defined or in preliminary stages.
D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Management Plan Not Applicable (NA) NR Work Breakdown Structure (WBS)...
AI summary The document outlines project schedules, regulatory approvals, and technical deliverables for a project, including the status of various plans and studies. Some items are marked as complete, while others are in preliminary or not applicable stages.
CI Number: C0068888 Project No. : Continuous Ash Hauling System Avoided Replacement Energy Costs Avoided Unplanned Repair Costs Total Annual Avoided Costs Year 2026 2027 2026 2027 2026 2027 Replacement Energy Cost ($/MWh) 0.00 0.00 Repair...
AI summary The Continuous Ash Hauling System analysis shows no energy replacement or unplanned repair costs for 2026 and 2027, with a 100% capacity factor in 2026 dropping to 50% in 2027. The total capital cost of the alternative is listed as $1,359,984. The 'Do Nothing' option is presented as an alternative.
or expiration of this Agreement including, but not limited to, the following provisions: Section 9 (Insurance), Section 20 (Limitation of Liability), Section 23 (Governing Law), Section 28 (Confidential Information) and this Section 31 (Su...
AI summary This document outlines the refurbishment of the Burnside Unit #2 Combustion Turbine engine, including the scope of work, cost, and timeline. The project is necessary due to damage observed on stage 9 blades and aims to restore the unit's functionality and reliability within the NS Power electrical system.
Original Equipment Manufacturer (OEM) procedures. Without this teardown, there remains a significant risk that hidden defects could evolve into unplanned unit failures. Why do this project this way? A “run to failure” strategy is not appro...
AI summary The document discusses the decision to refurbish an existing engine rather than replace it, citing risks of unplanned failures and the cost-effectiveness of refurbishment. It references the 2025 10-Year System Outlook and the Evergreen IRP scenario, emphasizing the need to maintain system reliability and align with the Province’s Clean Power Plan.
Defined (D) NR P D D D G. Planning Logistics Plan Defined (D) P P P D D Integrated Project Plan Not Applicable (NA) NR Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting D...
AI summary The document outlines various planning and study components for a project, including logistics, integrated project plans, risk registers, and environmental assessments. Some sections are marked as not applicable or preliminary, indicating the current status of planning and documentation.
782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0080135 Attachment 1 Page 19 of 21 BGT2 BSI March 25, 2025 Date: December 12, 2025 Page 350 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C...
AI summary This document outlines a transmission line replacement project for L-7012, a 230 kV line built in 1982, requiring upgrades due to deteriorated assets identified through NS Power’s inspection program. The project involves replacing assets on 72 structures and is part of the 2026 ACE Plan.
replace deteriorated assets that have been identified through NS Power’s transmission line inspection program. This project includes the replacement of deteriorated assets on a total of 72 structures. The project scope includes: - Structur...
AI summary The project involves replacing deteriorated assets on 72 transmission line structures to ensure the reliable operation of the transmission line and mitigate the risk of unplanned interruptions. The work is prioritized based on the condition of the assets and the criticality of the line to the overall system.
ansmission line inspection program results, as well as the criticality of the line to the overall system operation. This project is required to support the reliable operation of the transmission line. This project is deemed in-service when...
AI summary The document discusses a transmission line replacement and upgrade project, emphasizing the need to replace deteriorated assets for reliable system operation. The project is classified as Class 3 with a 15% contingency due to risks such as overtime work, material cost increases, and remote access challenges. The project is expected to be in-service by January 2026, with the final cost date set for January 2028.
VED) 2026 ACE Plan C0080110 Page 4 of 5 Instructions: Select option in Column B. Document No: XXX-XX-XXXX-XXXX Columns C through G will auto-populate. Project Cost Estimate Input Checklist and Maturity Matrix Transmission Line Infrastructu...
AI summary The document outlines a project cost estimate input checklist and maturity matrix for the L7012 Replacements and Upgrades Phase 1 transmission line infrastructure project. It includes fields for project maturity levels and estimate classifications.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Preliminary (P) NR P B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Project...
AI summary The document outlines general project data for an infrastructure project, detailing scope, capacity, location, requirements, technology selection, strategy, and planning. It specifies the status of various project components as defined or preliminary, and includes information on environmental monitoring and logistics.
Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Managem...
AI summary The text outlines various project management and regulatory documents related to a project, including the Code of Accounts, Schedule, Risk Register, and Stakeholder Management Plan. It also mentions studies such as Routing Options, Environmental Impact Assessment, and Topography, with some sections marked as preliminary or not applicable.
Technical Deliverables (Specifications and/or Drawings) Conductor, Insulator, Grounding, Joint Design (including protection for buried or subsea) Complete (C) S P C C C Foundation/Structure (Tower) Design Not Applicable (NA) Route Mapping/...
AI summary The text outlines technical deliverables and their status for a project, including conductor, insulator, grounding, joint design, foundation/structure design, route mapping, and other specifications. Most items are marked as complete or preliminary, with some noted as not applicable.
required to complete the project within the available outage window, unforeseen material or contract cost increases, or unforeseen costs related to accessing structures in wet or remote locations. Date: December 12, 2025 Page 361 of 782 RE...
AI summary The document outlines the 70W-T52 transformer addition project at the 70W High St. Bridgewater substation, aimed at enhancing system reliability, supporting load growth, and future voltage conversion. The new transformer will operate in parallel with 70W-T53 and allow for the eventual retirement of 70W-T51 once feeder conversions are complete.
mobile transformer connection capable of accommodating larger mobile units, addressing long-standing substation access challenges and eliminating the need for foreseeable future upgrades at the site. Summary of Related CIs +/- 2 years Purs...
AI summary The project involves adding a new 69kV-12kV transformer in Bridgewater to address aging infrastructure, increase capacity, and support long-term distribution planning. The existing 69-4.2kV transformer is over 68 years old and has exceeded its service life. The new transformer will operate in parallel with an existing one, providing redundancy and enabling the conversion of 4kV feeders to 12kV.
ructure readiness ahead of the 4kV feeder conversion project. Keeping 70W-T51 in service during the transition maintains 4kV system supply as load is converted to 12kV. Why do this project this way? This project takes a phased approach by...
AI summary This project involves a phased approach to upgrade the 4kV feeder system by adding a new transformer to off-load an existing one and provide contingency capacity. The plan includes retiring an old transformer once the conversion is complete, which will free up space for larger mobile units. The project aligns with NS Power’s asset management strategy and has a 15% contingency for risks like material costs and schedule delays.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data including scope, capacity, location, requirements, technology selection, strategy, and planning for a project. It details the defined and preliminary status of various aspects such as site infrastructure, voltage, environmental monitoring, and logistics planning.
P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Defined (D) NR P D D D Sta...
AI summary The text outlines various project management components and their status, including Integrated Project Plan, Project Code of Accounts, Project Schedule, and others, with some items marked as 'Defined (D)' and others as 'Preliminary (P)' or 'Not Applicable (NA)'.
REDACTED 2026 ACE Plan C0070909 Attachment 1 Page 2 of 16 Bridgewater Area Planning Study Addendum EXECUTIVE SUMMARY This addendum to the 2006 Bridgewater Distribution Planning Study 211-0606-W62 provides updated justification and context...
AI summary This addendum updates the 2006 Bridgewater Distribution Planning Study, justifying the retirement of an aging transformer and its replacement with a higher-capacity unit. The upgrade is needed due to evolving load profiles and approaching system limits, with construction scheduled to begin in 2026 and complete by 2029.
TABLE OF CONTENTS EXECUTIVE SUMMARY ................................................................................................................................... i TABLE OF CONTENTS.......................................................
AI summary The document outlines the scope and findings of a study related to system upgrades and conditions in the Nova Scotia power system, including feeder voltage levels, substation loading, and deteriorated plant conditions.
W-AREA-2025-017 Nov 10, 2025 ii Date: December 12, 2025 Page 370 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED 2026 ACE Plan C0070909 Attachment 1 Page 4 of 16 Bridgewater Area Planning Study Addendum 1.0 SCOPE This...
AI summary This addendum updates the Bridgewater Area System Planning Study, focusing on transformer 70W-T51 and the conversion of the distribution system from 4 kV to 12 kV. It highlights stable loading on 70W-T51, increased loading on 70W-T53, and the need for a new 69 kV-12 kV transformer to support the conversion and improve system reliability.
W-AREA-2025-017 Nov 10, 2025 3 Date: December 12, 2025 Page 371 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED 2026 ACE Plan C0070909 Attachment 1 Page 5 of 16 Bridgewater Area Planning Study Addendum 2.0 SUMMARY OF O...
AI summary The Bridgewater Area System Planning Study identified the 70W-High Street substation as a critical supply point. It outlined three reinforcement alternatives, with Alternative A-1 proposing replacing a transformer and converting 4 kV feeders to 12 kV to relieve the 89W substation. This alternative was not pursued due to higher costs, but a later transformer replacement at 89W resolved the issue. Alternative B-1 suggested replacing 70W-T51 while maintaining the 4 kV system.
ely recommended proceeding with Alternative B-2, establishing a long-term plan for 70W-High Street Substation to transition entirely to 12 kV operation once all remaining 4 kV loads were converted. W-AREA-2025-017 Nov 10, 2025 4 Date: Dece...
AI summary The document discusses the deferred conversion of the 70W-High Street Substation from 4 kV to 12 kV operation, highlighting the need for a long-term plan to complete the transition initiated in the 2006 Bridgewater Area Study. System upgrades since 2006 have not fully resolved the need for additional 12 kV capacity.
Date: December 12, 2025 Page 375 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED 2026 ACE Plan C0070909 Attachment 1 Page 9 of 16 Date: December 12, 2025 Page 376 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMO...
AI summary The Bridgewater Area Planning Study Addendum evaluates two alternatives to address transformer and contingency capacity issues at 70W-High Street Substation. Alternative A involves replacing transformer 70W-T51 in 2026 and adding a new transformer in 2027, with an estimated investment of $5.4 million.
lternative resolves the immediate Deteriorated Plant Criteria Violation associated with the existing transformer, it retains the 4 kV system in service, requiring ongoing maintenance of aging assets. 5.2 Alternative B – Add T52 (69-12 kV,...
AI summary Alternative B proposes installing a new transformer and converting remaining 4 kV feeders to 12 kV, retiring an aging transformer and eliminating the need for ongoing investment in the 4 kV system. This option aligns with Nova Scotia Power’s voltage standardization strategy and offers long-term operational benefits.
removes the need for ongoing investment in the 4 kV system. Alternative B is therefore the recommended solution, offering the lowest cost with significantly higher system and operational benefits. W-AREA-2025-017 Nov 10, 2025 9 Date: Decem...
AI summary The Bridgewater Area Planning Study Addendum concludes that Alternative B is the recommended solution for replacing transformer 70W-T51 and completing voltage conversions at 70W-High Street Substation. The project will retire 4 kV assets, upgrade to 12 kV transformation, and align with Nova Scotia Power’s long-term distribution strategy. The estimated investment is $4.3 million, with completion planned for January 2029.
iorated transmission assets that have been identified through NS Power’s transmission line inspection program. This project includes the replacement of deteriorated assets on a total of 59 structures. The project scope includes: - Structur...
AI summary This project involves replacing deteriorated transmission assets identified through NS Power’s inspection program, including 12 structure replacements and others. The work is necessary to maintain system reliability and redundancy, and the project is prioritized based on asset condition and system criticality.
ansmission line inspection program results, as well as the criticality of the line to the overall system operation. This project is required to support the reliable operation of the transmission line. This project is deemed in-service when...
AI summary This document discusses a transmission line replacement and upgrade project, emphasizing the need to replace deteriorated assets as the only technically feasible option. It outlines the project timeline, with the first portion expected to be completed in January 2026 and the final cost date set for January 2028. A contingency of 15% is applied based on past project experiences and risk factors.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Preliminary (P) NR P B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Project...
AI summary The text outlines general project data for a development, including scope, capacity, location, requirements, technology selection, strategy, and planning. It categorizes various aspects of the project as either defined (D) or preliminary (P), with some sections marked as not applicable (NA) or not rated (NR).
ntegrated Project Plan Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Preliminary (P) NR P Stakeholder Consulta...
AI summary The document outlines various project management components, including the Integrated Project Plan, Project Code of Accounts, Project Schedule, and Risk Register, with some items in preliminary or defined stages. It also includes sections on studies such as routing options, environmental impact assessments, and topography, with some sections marked as not applicable.
Technical Deliverables (Specifications and/or Drawings) Conductor, Insulator, Grounding, Joint Design (including protection for buried or subsea) Complete (C) S P C C C Foundation/Structure (Tower) Design Not Applicable (NA) Route Mapping/...
AI summary The text outlines technical deliverables and their status for a project, including conductor, insulator, grounding, joint design, foundation/structure design, route mapping, and other specifications. Most items are marked as complete or preliminary, with some noted as not applicable.
required to complete the project within the available outage window, unforeseen material or contract cost increases, or unforeseen costs related to accessing structures in wet or remote locations. Date: December 12, 2025 Page 387 of 782 RE...
AI summary This document outlines the 76W-T1 Transformer Replacement project at Mahone Bay Substation, which involves replacing an aging transformer with a higher capacity unit, upgrading infrastructure, and improving safety standards. The project is part of the 2026 ACE Plan and has a forecasted cost of $2,818,855.
The project also includes redesigning and installing new transformer foundation, adding a new transmission structure, improving oil containment, and updating the ground grid to meet modern standards. Summary of Related CIs +/- 2 years: Pur...
AI summary The project involves replacing the 76W-T1 transformer in Mahone Bay due to its end-of-life status, internal overheating signs, and anticipated load growth. The transformer is the sole supply to the town, and replacement is necessary for reliable and safe power delivery.
icates that replacing the unit with a new, higher-capacity transformer is the best approach. Overall, this project is crucial to maintain reliable, safe, and efficient power delivery to Mahone Bay. Date: December 12, 2025 Page 389 of 782 R...
AI summary This project involves replacing a transformer (76W-T1) to prevent unplanned failure and ensure reliable power delivery to Mahone Bay. The presence of ethylene in the main tank indicates internal degradation, and delaying replacement increases the risk of sudden failure. The project also aligns with the Town of Mahone Bay’s planned low-voltage infrastructure upgrades and NS Power’s asset management strategy.
uire similar upgrades to another transformer elsewhere on the system to handle the increased load. Therefore, replacing the existing transformer at 76W is the most practical and cost-effective choice. Upgrading the high voltage substation...
AI summary The document discusses the replacement of a transformer at 76W and upgrades to a high voltage substation structure to ensure reliability and alignment with modern design standards. A 15% contingency is applied to project costs, excluding the transformer, to account for potential risks such as overtime work and unexpected service wire deterioration.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data for an infrastructure project, covering scope, capacity, location, requirements, technology selection, strategy, and planning. Key elements include defined and preliminary status for various project components, with some sections marked as not applicable.
Defined (D) P P P D D Integrated Project Plan Not Applicable (NA) NR Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Not Applicable...
AI summary The text outlines the status of various project management and regulatory components for an integrated project plan, including definitions, preliminary stages, and not applicable items, with a focus on environmental and stakeholder considerations.
Preliminary (P) NR S/P P Erosion Control Plan & Drawings Preliminary (P) NR S/P P Foundation/Structure (Tower) Discipline Drawings Preliminary (P) NR S/P P Tower/Structure Location/Spotting Complete (C) NR S/P P C C Instrument Datasheets C...
AI summary The text provides a summary of project deliverables and their completion status across different disciplines, including erosion control plans, foundation/structure drawings, and electrical discipline drawings. It lists the number of deliverables and their percentage completion towards the class estimate.
ently not capable of live-line operation. Live line switches can be operated while the circuit is energized. These switches isolate line L-6536 and have reached end-of-life, with one being inoperable. Due to the existing switches not being...
AI summary The existing switches on line L-6536 are not capable of live-line operation and have reached end-of-life, requiring an outage for safe work. The project involves upgrading switches to support live-line operation, with no related projects planned in the next five years. The asset has an estimated life of 35 years and falls under the Transmission Plant depreciation class.
f Retirement: Accounting Policy 6420 – Retirement and disposal of Capital Assets • Percentage of Asset Pool: 0.23% JUSTIFICATION: Justification Criteria: Transmission Plant Why do this project? The installation of the new switches will ena...
AI summary The project involves replacing two end-of-life switches (22N-603 and 22N-604) to enable live-line operation, reducing outages and improving reliability. The current switches are difficult to operate and their failure could lead to unplanned outages. A new ground grid and switches will allow more efficient operations and mitigate risks.
e of salaries across a variety of jobs within similar classifications including fringe, and are used solely for budgeting purposes. Note 2: Small differences in totals are attributable to rounding. Date: December 12, 2025 Page 396 of 782 R...
AI summary The text provides a project cost estimate input checklist and maturity matrix for the L6536 Switch Replacements transmission line infrastructure project, including classification levels and required fields for project definition deliverables.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data, including scope, capacity, location, requirements, technology selection, strategy, and planning for a project. It details the status of various components as defined or preliminary, with some elements marked as not applicable.
P P Integrated Project Plan Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Preliminary (P) NR P Stakeholder C...
AI summary The text outlines various project planning and regulatory components for an initiative, including the Integrated Project Plan, Project Code of Accounts, Project Schedule, Regulatory Approval & Permitting, Risk Register, and Stakeholder Consultation/Management Plan. It also references studies such as Routing Options, Topography & Bathymetry, and Environment/Existing Conditions, with varying levels of definition and applicability.
ng Station to the transmission grid, enabling the delivery of renewable hydroelectric energy. Its continued degradation poses operational, financial, and environmental risks. Why do this project now? The 96H-T1 transformer is consistently...
AI summary The document discusses the need to replace a transformer due to oil leaks and its location near a river, which poses environmental risks. Replacement is deemed necessary due to the transformer's degraded condition, lack of OEM support, and the cost-effectiveness of replacement over refurbishment.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data for an infrastructure project, including scope, capacity, location, requirements, technology selection, strategy, and planning aspects. It details the project's defined parameters and requirements across various categories.
Defined (D) P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Preliminary (P...
AI summary The text outlines various project management and regulatory planning documents, including the Integrated Project Plan, Project Code of Accounts, and Work Breakdown Structure. It also mentions preliminary stages of regulatory approval and permitting, risk registers, and stakeholder engagement plans. Some studies, such as routing options and environmental assessments, are defined or not applicable.
for specific risks associated with additional overtime work that may be required to complete the project within the available outage window, and any unforeseen material or contract cost increases. Date: December 12, 2025 Page 406 of 782 RE...
AI summary This document discusses the replacement of four Pennsylvania circuit breakers on NS Power’s system, including the risks associated with additional overtime work and unforeseen cost increases. The project involves replacing one 69 kV and three 138 kV circuit breakers, which are considered high risk due to reliability concerns.
uch larger portion of the transmission system and in some cases affects a higher number of customers. This project will complete replacement of four Pennsylvania circuit breakers on NS Power’s system. Summary of Related CIs +/- 2 years: Pu...
AI summary The document discusses the replacement of Pennsylvania circuit breakers on NS Power’s transmission system due to poor performance and reliability concerns. The project is justified based on safety, system reliability, and the unavailability of replacement parts from the original equipment manufacturer. Related capital items and depreciation class information are also provided.
s limited ability to maintain and repair these breakers, combined with their poor operation history, results in an unacceptably high risk associated with continued operation. Why do this project now? These circuit breakers are required to...
AI summary The project aims to replace aging circuit breakers to reduce the risk of failure and ensure reliable transmission system operation. It is part of a multi-year initiative, with the first replacement expected in August 2026 and the final cost date set for June 2029.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data for an infrastructure project, including scope, capacity, location, requirements, technology selection, strategy, and planning aspects. It details the project's defined parameters and requirements across various categories.
Defined (D) P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Preliminary (P) NR P Risk Register Defined (D) NR...
AI summary The text outlines various project management documents and studies related to a project, including the Integrated Project Plan, Project Code of Accounts, Project Schedule, and others. It also mentions studies such as Routing Options, Topography & Bathymetry, and Environmental Impact/Sustainablity Assessment, with some marked as not applicable.
for specific risks associated with additional overtime work that may be required to complete the project within the available outage window, and any unforeseen material or contract cost increases. Date: December 12, 2025 Page 411 of 782 RE...
AI summary The document outlines a project to establish new distribution rights-of-way in 2026, targeting areas where existing vegetation management practices are insufficient to prevent tree contacts and ensure reliable system operation. The project is part of the 2026 ACE Plan and is expected to cost $20,889,694.
wer’s distribution system. The new rights-of-way will primarily be established adjacent to the road right-of-way edge, where most distribution feeders are currently located and bordered by vegetation. Phase 11 continues the step change in...
AI summary NS Power is advancing Phase 11 of its distribution rights-of-way program, focusing on improving system resiliency through new rights-of-way establishment and using satellite imagery and AI for prioritization. The project is influenced by vegetation data and landowner cooperation, with targeted circuits subject to change based on permissions and risk factors.
• 2025 CI C0061521 New Distribution Rights-of-Way Phase 10 $20,890,176 • 2027 CI TBD New Distribution Rights-of-Way Phase 12 $TBD • 2028 CI TBD New Distribution Rights-of-Way Phase 13 $TBD Depreciation Class: Distribution Plant - Land Righ...
AI summary This project involves establishing new distribution rights-of-way to support storm hardening and vegetation management, reducing outages by mitigating tree contact issues, particularly outside existing corridors. It aligns with NS Power’s Five-Year Reliability Plan and aims to improve system resilience during normal and extreme weather conditions.
outside existing corridors and contributes to the Plan’s goal of reducing SAIDI through targeted vegetation strategies that improve system resilience during both normal and extreme weather conditions. Tree contacts are a leading cause of o...
AI summary The text discusses the impact of tree contacts on power outages, highlighting that 80% of these contacts occur from trees outside the right-of-way. It outlines how establishing new rights-of-way can reduce such incidents by increasing the separation between trees and distribution feeders, contributing to the Plan’s goal of reducing SAIDI through improved vegetation management strategies.
e of salaries across a variety of jobs within similar classifications including fringe, and are used solely for budgeting purposes. Note 2: Small differences in totals are attributable to rounding. Date: December 12, 2025 Page 416 of 782 R...
AI summary The text includes a checklist and maturity matrix for estimating project costs related to a new distribution right of way infrastructure project, with classifications based on the maturity level of project definition deliverables.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data, including scope, capacity, location, requirements, technology selection, strategy, and planning for a project. Key details cover infrastructure, voltage, environmental monitoring, right-of-way, and logistics planning, with various sections defined or not applicable.
P P P D D Integrated Project Plan Not Applicable (NA) NR Project Code of Accounts Defined (D) NR P D D D Project Schedule Defined (D) NR P D D D Regulatory Approval & Permitting Not Applicable (NA) NR Risk Register Not Applicable (NA) NR S...
AI summary The text outlines the status of various project management components for an integrated project plan, including the project code of accounts, schedule, and stakeholder engagement plan. Several items, such as regulatory approval, risk register, and environmental impact assessment, are marked as not applicable.
of Kms 2023 2024 Feeder Change Completed Condition Condition 103W-312 15 5 3 2 10C-211 7 3 2 1 126H-313 7 4 3 1 127H-411 12 5 3 2 12V-302G 6 5 3 2 16N-301 8 5 3 2 16V-315 10 3 3 0 16V-315G 8 5 3 2 16W-302J 9 3 3 0 18V-412 22 3 3 0 1N-402 5...
AI summary The document presents a table with data on feeder lines, including the number of kilometers, conditions in 2023 and 2024, and changes over time. This appears to be related to infrastructure planning and asset management in the electricity distribution system.
d past outage performance has confirmed that conductor replacement is necessary. Delaying this project increases the likelihood of additional unplanned interruptions for customers served by this line. This project is deemed in service when...
AI summary The document discusses a conductor replacement project necessary to prevent additional unplanned outages. The project is phased, with the first distribution transformer replacement expected in August 2026 and the final cost date set for July 2027. The approach focuses on replacing the most deteriorated sections of the line. A 10% contingency has been applied to cover potential risks such as additional equipment replacement and tree trimming.
Document No: XXX-XX-XXXX-XXXX Columns C through G will auto-populate. Project Cost Estimate Input Checklist and Maturity Matrix Transmission Line Infrastructure Required fields: Estimate Classification Project Name: 36V-303 Baxter's Harbou...
AI summary The document outlines a project cost estimate input checklist and maturity matrix for the 36V-303 Baxter's Harbour Rd Reconductor Phase 1 transmission line infrastructure project, detailing maturity levels and estimate classifications.
d Project Plan Defined (D) NR P D D D Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Defined (D) NR P D D D Risk Register Defined (D) NR P D D D Stakeholder Consultati...
AI summary The text outlines various project management components, such as the project plan, code of accounts, schedule, and risk register, with varying levels of definition and development. Several studies and assessments are marked as not applicable.
ent. The contingency will also provide coverage for further project requirements including the balancing of load for transformers, and any additional tree trimming required along the service lines. Date: December 12, 2025 Page 424 of 782 R...
AI summary The text discusses a contingency plan for a project, including load balancing for transformers and additional tree trimming along service lines. It also includes a description of a capital item related to a reconductor and line extension project with specific dates and a forecasted cost.
oles and Fixtures Distribution Plant – Overhead Conductors and Devices Distribution Plant – Line Transformers Estimated Life of the Asset: 45 years Retirement Information: • Categorization of Retirement: Accounting Policy 6420 - Retirement...
AI summary The document discusses a project to replace deteriorated poles and conductors on feeder 57C-426H to improve outage performance and enable future customer connections. The project is part of a broader effort to enhance the reliability of the distribution feeder, which has historically had poor performance due to an off-road section.
782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0080612 Page 2 of 5 distribution assets on this feeder section in this manner is imperative, as delaying further upgrades or continuing to operate overhead equipment i...
AI summary The 2026 ACE Plan outlines a project to reconfigure and upgrade the 57C-426H feeder section between Country Harbour and Indian Harbour Lake, which serves nearly 1,000 customers. The project involves constructing new 3-phase distribution lines and reconductoring existing 1-phase lines. The project is classified as a Class 3 estimate with a 10% contingency to cover risks like equipment replacement and tree trimming.
General Project Data A. Scope Project Scope of Work Description Defined (D) P P D D D Site Infrastructure (Access, Construction Power, Camp, etc.) Defined (D) NR P D D D B. Capacity Voltage (kV) and Circuits Defined (D) P P D D D C. Projec...
AI summary The document outlines general project data for a proposed initiative, detailing scope, capacity, location, requirements, technology selection, strategy, and planning. It includes information on infrastructure, voltage, environmental monitoring, and logistics.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0080612 Page 5 of 5 Legend: Inclusions: Date: December 12, 2025 Page 430 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0080111 Page 1 of 5 CI Number: C...
AI summary This document outlines the 2026 RTU Deployment project, which involves installing 21 Remote Terminal Units (RTUs) in Nova Scotia substations to improve grid operation and emergency response times. The project is part of General Plant function and has a forecasted cost of $8,322,655.
Defined (D) NR P D D D G. Planning Logistics Plan Defined (D) P P P D D Integrated Project Plan Preliminary (P) NR P Project Code of Accounts Defined (D) NR P D D D Project Schedule Preliminary (P) NR P Regulatory Approval & Permitting Def...
AI summary The text outlines various planning and technical deliverables for a project, including logistics, integrated project plans, risk registers, and stakeholder management plans. It also mentions the status of network infrastructure and data architecture as complete.
k. These capabilities will provide detailed asset information to be used in supporting the prioritization of various work streams across Energy Delivery. This project scope includes two key elements: The first component is the establishmen...
AI summary The project involves creating a data capture platform using photographic documentation and machine learning to enhance asset recognition and integration with NS Power's GIS system, improving efficiency and data accessibility across various business units.
REDACTED 2026 ACE Plan C0080252 Page 2 of 5 JUSTIFICATION: Justification Criteria: Distribution System Why do this project? This project advances NS Power’s overall asset intelligence in a way that is sustainable through the use of the enh...
AI summary This project aims to enhance NS Power’s asset intelligence by integrating advanced technology into their field resources and GIS system, enabling continuous data updates and streamlining customer request processing. The project is being executed now due to the limited timeframe for federal funding, which covers most costs except administrative overheads and contingency.
the work is completed (January 2026); therefore, the Final Cost Date (June 2027) is listed as six months after the last portion of the work is forecast to be completed). Why do this project this way? This project establishes an effective w...
AI summary The project aims to improve data intelligence on distribution assets using technology and machine learning automation, replacing manual and outdated methods. It is fully funded by the federal government except for administrative overheads and is classified as a Class 1 estimate with a 2% contingency applied for unforeseen issues.
D Solution Contracting / RFP Defined (D) NR P D D D G. Planning Cross Team Planning (i.e., ECC/Energy Delivery ROPS/Corporate Security/IT Sec Defined (D) P P P D D Integrated Project Plan Defined (D) NR P D D D Project Code of Accounts Def...
AI summary The text outlines various planning and technical deliverables for a project, including the definition of solution contracting, planning processes, and technical specifications such as network infrastructure and data architecture.
5,149,415 13,954,518 Deferred 2026 Subsequent Submittal Additional engineering is required before project can progress to construction. C0053214 76W-T1 Transformer Replacement 1,938,848 2,279,295 Deferred 2026 Subsequent Submittal Project...
AI summary The text outlines several deferred and cancelled projects, primarily related to infrastructure and IT upgrades, with reasons including the need for additional engineering, reprioritization, and integration with other projects. These projects are scheduled for future submissions or approvals, notably in 2026.
SEB on December 1, 2025 52314 1C-GT1/UT1 Replacement 11/30/2020 2,032,393 1,678,006 FIN CWO submitted to NSEB on December 1, 2025 This project is now complete; however, the final cost application is being held until the functionality C0042...
AI summary The text provides information on several completed projects with pending final cost applications, including IT security upgrades, wood pole retreatment, and smart grid initiatives. These projects are being processed by the Nova Scotia Energy Board (NSEB) under various proceedings, with final costs contingent on investigations and asset disposition processes.
project. The so ware takes capital costs, avoided costs, revenue, expenses, and taxes into considera on to give a Net Present Value (NPV), internal rate of return (IRR), and discounted payback period. Economically JusƟfied Project: A capit...
AI summary The text outlines various types of capital projects, including economically justified, environmental, and essential projects, and explains the use of the Economic Analysis Model (EAM) to assess their benefits. It also defines terms such as 'Final Cost (FIN)' and 'Individual Capital Item' and discusses the Integrated Resource Plan as a long-term planning framework for evaluating utility resources.
179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Summary Document 17.0 Capital Expenditure JusƟficaƟon Criteria 17.1 IntroducƟon - General ConsideraƟons The following considera ons are used to evaluate...
AI summary Nova Scotia Power outlines criteria for justifying capital expenditures, emphasizing evaluation of alternatives, technology suitability, cost-effectiveness, compliance with reliability standards, and minimizing operational costs. The approach prioritizes meeting industry performance norms and selecting the least-cost option that satisfies requirements.
ensure compliance with NPCC and, or NERC Reliability Standards. The least cost op on mee ng the requirements and constraints specified above shall be selected. 17.1.1 Integrated Resource Plan An Integrated Resource Plan (IRP) assesses vari...
AI summary NS Power's Integrated Resource Plan (IRP) is a strategic planning tool ensuring compliance with NPCC and NERC standards, aiming to meet future electricity needs with a 20% reserve margin through stakeholder consultation and cost-effective solutions.
nd cost effec vely in compliance with current and emerging opera onal and environmental constraints; • A reference against which to assess demand and supply-side applica ons; • A living document that will be updated as condi ons change mate...
AI summary NS Power's Integrated Resource Plan (IRP) serves as a living document for assessing energy demand and supply applications, incorporating expert input, stakeholder data, and predictive modeling. It emphasizes a 25-year planning horizon with realistic value ranges, clarifying it is not a commitment to specific initiatives or a regulatory approval request.
2026 ACE Plan Appendix D Page 61 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Summary Document Forced Outage Rate Unplanned outages result in replacement genera on, o en at a higher cost than the...
AI summary Nova Scotia Power Inc. outlines capital expenditure justification criteria, emphasizing unplanned outages' cost impacts via probabilistic production models. System design adheres to NPCC and NERC standards, with NERC requirements enforced through NSEB regulatory approval. Transmission criteria combine protection performance and system dynamics, ensuring compliance with single contingency design principles.
Bulk Electric System is planned, designed, and operated in accordance with single con ngency criteria. NS Power System Design Criteria are applied for all other por ons of the interconnected system. NERC standards and NPCC criteria are con...
AI summary The document outlines Nova Scotia Power's system design criteria for transmission and distribution systems, emphasizing compliance with evolving NERC and NPCC standards. It details conditions for upgrading, replacing, or modifying transmission plant to ensure safety, reliability, and cost efficiency, while aligning with capital expenditure justification criteria.
llows selec ve sampling of standard induc on type meters both in verifica on and re-verifica on. Month DD, YYYY Page 51 of 54 Date: December 12, 2025 Page 516 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Append...
AI summary Nova Scotia Power Inc. outlines criteria for replacing metering equipment and upgrading work support facilities. Replacements occur when meters fail standards or customer rate classes change. Facilities are modified to ensure safety, comply with laws, and maintain asset longevity.
legal, safety, regulatory or environmental direc ves. ExecuƟve: A member of the NS Power Execu ve Team including General Managers, Vice Presidents, Execu ve Vice Presidents and the President and CEO. Final Cost (FIN): A capital work order...
AI summary The text defines key terms related to capital projects, financial metrics, and regulatory processes, including 'Final Cost (FIN)', 'Integrated Resource Plan (IRP)', and 'Internal Rate of Return (IRR)'. It outlines NS Power's Executive Team and the NSEB's role in reviewing capital projects.
179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document 17.0 Capital Expenditure JusƟficaƟon Criteria 17.1 IntroducƟon – General ConsideraƟons The following considera ons are used to evaluate...
AI summary Nova Scotia Power Inc. outlines capital expenditure justification criteria, emphasizing evaluation of alternatives, technology suitability, cost analysis, compliance with reliability standards, and selection of the least-cost option meeting requirements. The Integrated Resource Plan (IRP) is referenced as a framework for decision-making.
ensure compliance with NPCC and, or NERC Reliability Standards. The least cost op on mee ng the requirements and constraints specified above shall be selected. 17.1.1 Integrated Resource Plan An Integrated Resource Plan (IRP) assesses vari...
AI summary The document outlines Nova Scotia Power's Integrated Resource Plan (IRP), emphasizing its role in assessing supply/demand scenarios, ensuring compliance with emission standards, and maintaining a 20% capacity reserve margin. The IRP serves as a strategic, stakeholder-informed roadmap for long-term electricity planning and capital expenditure justification.
cost effec vely in compliance with current and emerging opera onal and environmental constraints; • A reference against which to assess demand and supply-side applica ons; • A living document that will be updated as condi ons change materia...
AI summary NS Power's Integrated Resource Plan (IRP) serves as a strategic planning tool for energy demand and supply, incorporating expert input, stakeholder feedback, and predictive modeling over a 25-year horizon. It emphasizes adaptability to changing conditions and clarifies it is not a binding commitment or approval application for specific initiatives.
REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix D Page 133 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document • Wood stave pipelines shall be replaced when an engin...
AI summary Nova Scotia Power Inc. outlines criteria for capital expenditures, including replacing wood stave pipelines based on engineering risk assessments, turbine runners due to degradation or efficiency gains, and dams/hydraulic structures failing to meet safety standards. Decisions hinge on formal engineering evaluations and risk analyses.
e undertaken unless the customer requests to contribute the incremental cost difference. Extension of service will conform to the latest version of the NS Power Rates, Regula ons and Procedures Manual. Pole Strength Compliance with Standard...
AI summary NS Power outlines criteria for replacing distribution pole lines based on safety hazards, distribution planning, legal obligations, and cost minimization. Pole replacement is mandated by CSA standards and guided by a 1993 report on inspection procedures and replacement criteria.
ure is used to evaluate alterna ve solu ons to correc ng voltage condi ons to CSA Standards on the Nova Sco a Power Inc. distribu on system. • Local Voltage For local voltage issues the costs are iden fied to determine a least cost solu on...
AI summary The text outlines methods and associated costs for addressing voltage issues on Nova Scotia Power Inc.'s distribution system, including transformer adjustments, reconductoring, and infrastructure upgrades, with costs calculated in current-year or present-worth dollars.
t feeders has been fully u lized. In addi on, cable ra ngs for normal and emergency condi ons should be determined by reference to the “Underground Standards Manual”. • Conductors Overhead conductors are considered to be overloaded when th...
AI summary The document outlines procedures for identifying and addressing overloaded equipment on Nova Scotia Power Inc.'s distribution system, referencing specific manuals and criteria for conductor loading, equipment ratings, and economic justification of solutions.
6 ACE Plan Appendix D Page 145 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document • Grounding – Economic Jus fica on Procedure To reduce the earth poten al the costs are iden fied suc...
AI summary Nova Scotia Power Inc. outlines capital expenditure justification criteria for grounding, joint use agreements, highway relocation, radio interference voltage, and voltage unbalance. Costs include labor, materials, and compliance with regulations like DEP 5.50 and the Radio Communication Act. Joint use agreements with Bell Aliant aim to reduce costs for both parties.
ce Network & Systems This includes PBX Cards, disk drives, power supplies, so ware & component upgrades, telephone sets, fax machines, and wiring due to office moves. Month DD, 2025 Page 92 of 113 Date: December 12, 2025 Page 611 of 782 REDA...
AI summary This document outlines Nova Scotia Power Inc.'s capital planning and expenditure justification criteria for telecom systems, including broadband networks, cable systems, voice networks, and network management systems, as part of the 2026 ACE Plan.
2026 ACE Plan Appendix D Page 160 of 179 Nova ScoƟa Power Inc. Capital Planning & Capital Expenditure JusƟficaƟon Criteria Detailed Document This rou ne includes the purchase of hardware and so ware products required for the con nuing oper...
AI summary The document outlines Nova Scotia Power Inc.'s capital expenditure plans for 2026, including IT infrastructure upgrades, property improvements (e.g., environmental compliance, building replacements), and furniture/equipment replacement. It references Appendix B's documentation policy for capital item reviews, though content is redacted.
heets and analysis Re rement Informa on x Tenders and bid evalua ons x Financial reports, including x - Power Plant Informa on- General ledger - Purchasing & Accounts Payable - Labour Distribu on - Documenta on to support assump ons, decis...
AI summary The document outlines Nova Scotia Power Inc.'s capital planning and expenditure justification criteria, including system design standards and a revision record for the 2026 ACE Plan Appendix D. It emphasizes detailed financial reporting and project documentation requirements.
the following: a. Economic dispatch or outage of genera on. b. Loading of transformer(s) to their (or their associated equipment) thermally limited ra ngs. Reinforcement is required in all cases when a single con ngency results in either t...
AI summary The text outlines reinforcement requirements for power systems under contingency scenarios, emphasizing economic considerations and transformer loading practices. It references IEEE standards for transformer loading and discusses scenarios where reinforcement may be economically justified despite meeting technical criteria.
2026 ACE Plan Appendix E Page 4 of 17 Mersey Hydro Update Non-Confidential 1 The sections below provide NS Power’s response, including: 2 3 • An update on the incremental sustaining investments that have been incorporated into the 4 Hydro...
AI summary NS Power outlines updates on Mersey Hydro redevelopment, including sustaining investments in the Hydro Interval Plan (HIP), stakeholder engagement with First Nations and government, an NPV analysis comparing redevelopment options, and cost estimates for preliminary engineering and procurement for 2028. The analysis includes assumptions and engagement details.
ower Great Brook (CI C0070486) and preparation for drawdown at Deep Brook in 2026 (CI C0080219) Safe and Reliable Hoist replacement for stop logs at Cowie Falls to safely and Management of Water reliably manage water (CI C0049032) Dam Safe...
AI summary The document outlines infrastructure maintenance projects for dam safety and powerhouses, including hoist replacements, concrete assessments, and crane column refurbishments at sites like Cowie Falls, Upper Lake Falls, and Big Falls, with associated Capital Item (CI) identifiers.
tes submitting CI 39472 HYD – Mersey Redevelopment 13 Phase 1 only once the IRP process has concluded and a full-scope review confirms the 14 redevelopment remains the best value for customers. Page 17 of 17 Date: December 12, 2025 Page 64...
AI summary The Mersey Redevelopment Phase 1 is contingent on the completion of the Integrated Resource Plan (IRP) process and a full-scope review confirming its value to customers. A WACC rate of 5.08% is noted in the 2026 ACE Plan Appendix E.
1 TABLE OF CONTENTS 2 3 1.0 EXECUTIVE SUMMARY ................................................................................................. 5 4 2.0 INTRODUCTION .............................................................................
AI summary The document outlines Nova Scotia's 2030 decarbonization goals, including 80% renewable electricity sales and coal phase-out, along with initiatives like the Clean Power Plan, Independent Energy System Operator, and Resource Development Plan focusing on wind, solar, and community programs.
ration Phase-Out................................................................................... 35 30 7.0 ADDITIONAL IRP ACTION PLAN AND ROAD MAP ITEMS ................................... 38 Page 2 of 55 Date: December 12, 2025 Page 65...
AI summary This document outlines the 2026 ACE Plan's update, covering demand-side management, hybrid peak/load management, green hydrogen projects, offshore wind, and project accountabilities, coordination, and risk management strategies for Nova Scotia's energy sector.
1 1.0 EXECUTIVE SUMMARY 2 3 This The Path to 2030 report is submitted to the Nova Scotia Energy Board (NSEB) in compliance 4 with the Board’s direction to “[f]ile a detailed and specific plan outlining how the Company will 5 achieve the 20...
AI summary The Path to 2030 report outlines NS Power's alignment with Nova Scotia's 2030 Clean Power Plan and its Evergreen IRP Action Plan. It details steps to meet 2030 decarbonization goals, including 80% renewable electricity and coal phase-out by 2030. The report also mentions the creation of the Independent Electricity System Operator (IESO-NS) in 2024 and references Matter M11307.
icity planning landscape in 24 Nova Scotia including several changes to the Project Accountability Matrix. 25 26 • As described in Section 5.0 and Section 6.2.2, any future Battery Storage projects will be 27 scoped and procured by the IES...
AI summary The document outlines changes in project accountability for Battery Storage and Fast-Acting Generation projects, to be managed by IESO-NS. NS Power supports this transition, aligning with the 2030 Clean Power Plan updates in the 10 Year System Outlook (10YSO) report. Key references include the 2023 ACE Plan (M11017) and updated resource timelines.
for this year’s Path to 2030 update. With respect to 12 resources, sizing, and timing, this update to The Path to 2030 report is consistent with the 2025 13 10YSO report unless otherwise noted. 14 15 Figure 1 - 2030 Clean Power Plan Resour...
AI summary The document updates the 2030 Clean Power Plan resources, aligning with the 2025 10YSO report. It details renewable energy projects (wind, solar, storage) with their capacities and construction dates, including the NS Power BESS Project, Green Choice Program, and future procurement timelines.
: 30 31 • The 2030 Decarbonization Goals 32 • The Province of Nova Scotia’s 2030 Clean Power Plan 33 • Creation of the Independent Energy System Operator of Nova Scotia (IESO-NS) Page 8 of 55 Date: December 12, 2025 Page 661 of 782 REDACTE...
AI summary The document outlines Nova Scotia's 2030 Clean Power Plan, the Integrated Resource Plan (IRP) Action Plan, and the creation of the Independent Energy System Operator of Nova Scotia (IESO-NS). It details resource development, project management, and timelines for meeting decarbonization goals.
urce outside Nova Scotia. 22 23 This requirement was incorporated into the most recent Evergreen IRP and is considered in the 24 2030 Clean Power Plan. 25 2 N.S. Reg. 110/2021. Page 10 of 55 Date: December 12, 2025 Page 663 of 782 REDACTED...
AI summary Nova Scotia's Environmental Goals and Climate Change Reduction Act mandates 80% renewable electricity by 2030 and coal phase-out by 2030. These targets are integrated into the Evergreen IRP and 2030 Clean Power Plan, with the 2026 ACE Plan Appendix F detailing implementation steps.
1 2 (IR 675) is forecast to reach commercial operation in Q1 2027, with the supporting operating 2 study to be completed beforehand to assess system impact. This will bring the total installed 3 capacity of the Mersey River Wind projects t...
AI summary The document outlines the progress of Mersey River Wind projects (Phases I and II) with capacities of 90 MW and 112.5 MW, respectively, and their expected commercial operation dates. It also notes the status of other interconnection requests (IR 739, IR 785) and the Generator Interconnection Process (GIP) for Renewable to Retail (RtR) projects.
1 • The remaining 18 percent of requests were for Class 2 Commercial Net Metering Service 2 (Generators greater than 100 kW up to 1 MW). 3 • 12 percent of requests were for generators having a nameplate capacity greater than 200 4 kW (Name...
AI summary NS Power has completed 16 preliminary assessments under the Commercial Net Metering Program (CNMP), totaling 3.5 MW of potential capacity. Over 12.4 MW of capacity has been assessed since the program's start. Additional renewable energy procurement is needed beyond current projects to meet the 2030 80% renewable energy standard, with responsibility for future procurements falling to the government and IESO-NS.
1 Incorporated (WTI) was formed in Nova Scotia as an ownership arrangement pursuant to the 2 Prescribed Projects Regulations made under the NS Public Utilities Act, to facilitate a low-cost 3 equity investment in the Project by the Canada...
AI summary WTI, a deemed utility under the Public Utilities Act, submitted an application for project cost approval and rate base establishment for the NS-NB Reliability Intertie Project. The NSEB approved the project in November 2025, directing WTI to update progress on the Path to 2030 timeline and participate in NS Power’s ACE Plan proceedings. Land acquisition and right-of-way clearing in Nova Scotia and New Brunswick are progressing ahead of schedule.
1 The Decision Gate 3 (DG3) governance milestone is planned for December 2025. Advancement 2 of the project through DG3 enables project sanction, with kickoff of the construction contract in 3 Q1 2026. This will be followed by the mobiliza...
AI summary The document outlines project milestones for the Reliability Intertie, including Decision Gate 3 (DG3) in December 2025 and Stage 2 transmission planning. It also highlights the need for 300MW of new fast-acting generation by 2030, as per the 2030 Clean Power Plan and Evergreen IRP analysis. NS Power is not currently engaged with NB Power on Stage 2 but plans to collaborate with stakeholders on interregional transmission expansion.
was reflected in The Path to 2030 – 2024 Update filed under M12012. 23 24 Upon receiving direction from the Province that procurement of fast-acting generation would be 25 led by the IESO-NS, NS Power worked to consolidate and transfer all...
AI summary NS Power transferred project materials to the Province and IESO-NS by November 2024, committing to an ongoing advisory role and supporting the IESO-NS in 2025 with technical input and project momentum.
ls (fuel switching). 22 23 6.5 Fuel Conversions at Existing Units 24 25 The 2030 Clean Power Plan includes alternate fuel operation at four of NS Power’s existing 26 thermal units. Similarly, the Evergreen IRP identified that alternate fue...
AI summary The 2030 Clean Power Plan and Evergreen Integrated Resource Plan (IRP) propose alternate fuel operations at four NS Power thermal units. References include IESO-Nova-Scotia-REOI-for-Capacity.pdf and exhibits from M12412 related to expenditure and revenue requirements.
1 a common resource plan element across IRP scenarios, and these were included in the IRP Action 2 Plan under item #3e. 3 4 6.5.1 Gas Conversion at Point Tupper Generation Station 5 6 The coal-to-natural-gas conversion of Point Tupper Gene...
AI summary The 2023 Evergreen Integrated Resource Plan (IRP) identifies coal-to-natural-gas conversion at Point Tupper Generating Station Unit 2 as a cost-effective peaking resource aligned with the Clean Power Plan and 2030 coal phase-out. NS Power aims to complete the project by 2028. Similarly, the 2030 Clean Power Plan and 2023 IRP scenarios support transitioning Lingan Generation Station units to heavy fuel oil (HFO) peaking operations due to low capital costs and operational benefits.
rged as a consistent outcome 26 across all 2023 Evergreen IRP scenarios. The value of this conversion is supported by the low 27 capital cost (these units already operate on HFO) and the ability for these units to operate in a 28 peaking c...
AI summary The analysis highlights the conversion of existing HFO-operating units to peaking capacity as a consistent outcome across 2023 Evergreen IRP scenarios, citing low capital costs and suitability for net peak demand periods. This aligns with the 2026 ACE Plan Appendix F.
2026 ACE Plan Appendix F Page 35 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 The 2029 timing for conversion to exclusive HFO operation for Lingan Units 1, 3, and 4 aligns 2 with the planned phase-out of coal generation by 2030...
AI summary The 2026 ACE Plan outlines the 2029 transition of Lingan Units 1, 3, and 4 to HFO operation, aligning with Canada's Clean Electricity Regulations and the 2030 coal phase-out. Preliminary engineering for auxiliary boilers and HFO logistics improvements at Sydney International Pier are underway to support operational readiness and reduce emissions.
le generation units. 21 22 6.6 Coal Generation Phase-Out 23 24 The significant addition of new resources described above is designed to both enable coal phase- 19F 25 out and support the forecast of continued load growth on the system. In...
AI summary The document discusses NS Power's analysis of coal unit retirement timelines as part of the Evergreen IRP process, concluding that retaining coal units as late as possible is optimal. This aligns with broader resource additions to support coal phase-out and load growth forecasts.
electrification load profiles 24 considered, the hybrid peak electrification profile emerged as an opportunity for reduction of 25 system peak load requirements and was studied as part of the Evergreen IRP. This scenario 26 assumes the ado...
AI summary The text discusses electrification load profiles, highlighting a hybrid peak electrification scenario studied in the Evergreen IRP, which reduces system peak load by adopting mini-split heat pumps. It references regulatory proceedings (M12249, M12282) involving EfficiencyOne and Nova Scotia Power Inc., including a 2026 DSM Extension and a new benefit-cost analysis test for DSM plans.
1 sources (such as oil and natural gas) to operate during the colder/peak system demand periods in 2 the winter when heat pumps are less efficient. This potential program has been considered and 3 discussed in NS Power’s Load Forecast Repo...
AI summary NS Power is evaluating a hybrid peak program to reduce winter demand by using alternative energy sources during peak periods. A study by Net Zero Atlantic, involving DOE and E1, aims to assess the program's cost impacts and operational models, with a completion timeline of Q1 2026.
1 2 Through 2025, NS Power has made steady progress on the DERIR initiative. The initial 3 framework, first stakeholder workshop, development of list of DER-related initiatives, second 4 stakeholder workshop, and one-on-one interviews with...
AI summary NS Power has advanced the DERIR initiative through stakeholder engagement and planning, while exploring green hydrogen projects with developers like EverWind Fuels and Nova Sustainable Fuels. These projects require incremental resources beyond current load forecasts, highlighting the need for additional capacity and renewable energy integration.
1 Nevertheless, there are growing risks with some aspects of the plan, including: 2 3 • Delays in procuring new fast-acting generation, combined with the growing lead times seen 4 across the industry for new combustion turbines, create unc...
AI summary The text outlines risks in a plan, including delays in procuring fast-acting generation, attrition of Green Choice projects risking 80% renewable energy targets, and unclear timelines for energy storage beyond NS Power’s BESS project. NS Power notes flexibility in coal retirement timelines but emphasizes collaboration with IESO-NS and the Province to address procurement challenges.
l need to be developed in collaboration with the IESO-NS. In the meantime, 25 NS Power continues to support the transition of accountabilities to the IESO-NS in collaboration 26 with the Province. Page 55 of 55 Date: December 12, 2025 Page...
AI summary NS Power is collaborating with the IESO-NS to transition accountabilities related to the Five-Year (2025-2029) Reliability Plan Update, reflecting ongoing efforts to align with the IESO-NS's role in system operations and planning.
1 TABLE OF CONTENTS 2 3 1.0 INTRODUCTION .............................................................................................................. 6 4 1.1 Five-Year Reliability Plan Commitment.............................................
AI summary The document outlines a five-year reliability plan focusing on vegetation management, storm hardening, and targeted equipment upgrades. It emphasizes wildfire mitigation, corridor widening, and tree trimming to enhance grid resilience. Section 3.0 highlights the 2025 overview as the first year of the plan, while sections 4.0–4.5 detail vegetation management strategies and infrastructure improvements.
. 26 17 4.5 Trimming and Removal of Trees Around Existing Power Lines .......................... 27 18 5.0 STORM HARDENING – TARGETED EQUIPMENT REPLACEMENTS AND 19 UPGRADES .....................................................................
AI summary The document outlines infrastructure upgrades for Nova Scotia's power grid, including tree trimming, storm hardening, equipment replacements, and grid modernization programs. It is part of the 2026 Annual Capital Expenditure (ACE) Plan, focusing on distribution, transmission, and substation improvements.
1 6.1.2 Downline Connectivity ............................................................................. 45 2 6.2 Fault Location Isolation and Service Restoration ................................................. 47 3 6.3 Distributed En...
AI summary The document outlines Nova Scotia Power's 2026 Five-Year Reliability Plan, focusing on storm hardening through vegetation management, corridor widening for distribution/transmission lines, equipment upgrades, and advanced grid modernization programs including connected assets and infrastructure improvements.
2026 ACE Plan Appendix G Page 4 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential
AI summary The 2026 Annual Capital Expenditure (ACE) Plan Appendix G outlines updates to NS Power's Five-Year Reliability Plan, focusing on infrastructure and operational reliability measures. The document is part of a non-confidential regulatory proceeding.
1 LIST OF FIGURES 2 3 Figure 1: Forecast Investment by Reliability Program 2025-2029 ($ millions) ............................. 7 4 Figure 2: Contribution to CHI by Outage Cause (2020 – 2024) Performance Standards ............11 5 Figure 3...
AI summary The document outlines a list of figures related to reliability programs, vegetation management, corridor widening, and rights-of-way establishment in Nova Scotia. Key themes include reliability investments, outage cause analysis, customer interruption metrics (CHI), SAIDI improvement targets, and infrastructure planning initiatives for 2025.
............................... 26 18 Figure 13: Map of 2025 Completed and Planned Establishment of New Rights-of-Way ........... 27 19 Figure 14: Trimming and Removal of Trees Around Existing Powerlines - 2025 ....................... 28 2...
AI summary The document outlines NS Power's 2025 infrastructure projects, including rights-of-way establishment, tree trimming, equipment upgrades, and transmission work. It references the Five-Year Reliability Plan update and the 2026 ACE Plan Appendix G, focusing on grid modernization and reliability improvements.
1 Figure 26: In Progress Construction of New Mount Uniacke Substation .................................... 42 2 Figure 27: 2025/2026 Advanced Grid Modernization Progress Overview ................................. 44 3 Figure 28: 2025 Plann...
AI summary The document outlines infrastructure projects and planning for grid modernization, reliability, and expansion in Nova Scotia, including substation construction, remote terminal unit installations, vegetation management, right-of-way widening, and conductor upgrades for 2025/2026.
ments 8 detailed in year one of the Plan. The Plan has a goal of reducing the overall duration and frequency 9 of outages while balancing the affordability of these investments for customers. 10 11 1.1 Five-Year Reliability Plan Commitment...
AI summary NS Power's Five-Year Reliability Plan aims to reduce outage duration and frequency through three core programs: vegetation management, storm hardening, and grid modernization. The plan balances reliability improvements with customer affordability, focusing on infrastructure upgrades and advanced grid technologies.
2026 ACE Plan Appendix G Page 7 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential
AI summary The 2026 ACE Plan Appendix G outlines NS Power's Five-Year Reliability Plan, focusing on infrastructure and capital expenditures. The document is non-confidential and part of a regulatory proceeding related to energy reliability and planning.
3,500 700,000 3,000 600,000 2,500 500,000 2,000 400,000 1,500 300,000 1,000 200,000 100,000 500 - - 2020 2021 2022 2023 2024 2025 (Projected) Customer Hours Projected Outage Event Count Projected 4 5 6 2.2 Distribution Targeted Devices 7 8...
AI summary Figure 4 illustrates trends in customer hours of interruption and outage frequency from 2020 to 2025, showing reductions attributed to distribution equipment upgrades and storm hardening initiatives. Projections for 2025 include actual data through October and estimates for November-December based on historical performance.
025 based on the prior five years’ performance. Storm hardening initiatives and 13 equipment upgrades are core elements of the plan, which will continue to build on these positive 14 trends. 15 Page 12 of 71 Date: December 12, 2025 Page 72...
AI summary NS Power's Five-Year Reliability Plan emphasizes storm hardening and equipment upgrades to improve system reliability. Performance standards target reducing Annual Customer Hours of Interruption (CHI) from equipment failures, with metrics shown in Figure 4.
1 3.0 2025 Overview – Year One of Five Year Reliability Plan 2 3 In 2025, NS Power’s Reliability team has been focused on executing the projects identified in year 4 one of the Plan, with $206.6 million committed to strengthen the grid and...
AI summary NS Power's 2025 reliability efforts focused on $206.6 million in grid upgrades, including distribution system improvements like replacing insulators, conductors, and transformers, as well as tree clearing to enhance resilience against weather events and support growing energy demand.
s in addition to the 617 kilometers of corridor widening have been 26 proactively identified and addressed from beyond cleared rights-of-way. This work 27 involves coordination with customers and landowners to remove each individual tree....
AI summary NS Power is updating its Five-Year Reliability Plan, focusing on corridor widening and tree removal activities beyond cleared rights-of-way. Coordination with customers and landowners is required for individual tree removal, including locations with multiple trees. The 2026 ACE Plan Appendix G is referenced as part of this update.
2026 ACE Plan Appendix G Page 15 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 • Addition of six RTUs improving substation communication and control, supporting 2 quicker response and restoration of service in the e...
AI summary NS Power's 2026 ACE Plan Appendix G outlines infrastructure upgrades to enhance grid reliability, including RTU additions, substation transformer replacements, new substation construction in Mount Uniacke, transmission structure work, and reconductoring of 33.7 km of transmission lines to improve resilience and winter peak capacity.
Complete in Remainder of Year Distribution 297 kms 183 kms 59 kms 242 kms (Revised due to Corridor Wildfire Mitigations) 1 Widening with Managed Distribution ROWs Vegetation Establish 330 kms 229 kms 89 kms 318 kms (Revised due to Manageme...
AI summary The document outlines vegetation management activities for distribution and transmission corridors, noting revisions to project distances due to wildfire mitigation measures. Additional controls by the Department of Natural Resources reduced work efficiency, with details in the Storm Hardening – Vegetation Management section.
4 3 2 1 0 2024 2025 2026 2027 2028 2029 SAIDI Actual Projected SAIDI Average SAIDI (2019 - 2023) 2029 5YR Plan Target Performance Standards Target 9 10 11 3.2 2025 Priority Feeders Update 12 13 Please refer to APPENDIX A: 2025 Highest Prio...
AI summary The document discusses NS Power's Five-Year Reliability Plan Update, focusing on targeted reliability improvements for priority feeders identified in Appendix A. It emphasizes data-driven approaches to address feeder conditions and performance, aligning with projected SAIDI (System Average Interruption Duration Index) targets and reliability standards.
2026 ACE Plan Appendix G Page 18 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 All feeder plans for 2025 are underway or complete; work will continue on all in progress work 2 until completed. 3 4 APPENDIX B: Work C...
AI summary NS Power's 2026 ACE Plan Appendix G outlines progress on 2025 feeder reliability initiatives, noting that all plans are underway or complete. Appendix B summarizes completed and ongoing work, indicating which feeders remain on the 2026 priority list. Multi-year projects are planned for select feeders to enhance reliability and mitigate outage risks.
2026 ACE Plan Appendix G Page 19 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 4.0 STORM HARDENING – VEGETATION MANAGEMENT 2 3 2025-2029 Forecast Investment: $265.0 million 4 Estimated Performance Standards SAIDI Re...
AI summary NS Power's 2025-2029 Storm Hardening Vegetation Management Plan allocates $265 million for reducing tree-related outages, targeting a 0.70–1.25 hour SAIDI reduction. Daily operations involve 75 crews clearing trees from distribution and transmission ROWs, with strategies including corridor widening and trimming.
be Completed by YE Distribution 12.5 183 59 Corridor Widening Transmission 3.0 105 15 Corridor Widening Establishment 16.4 229 89 of New Rights-of-Way Trimming and 6.9 205 55 removal of trees 2 3 As of October 31, 2025 NS Power has complet...
AI summary NS Power has completed 617 km of distribution and 105 km of transmission vegetation management by October 2025, including rights-of-way establishment, hazard tree removal, and aerial pruning. These efforts aim to improve system reliability and reduce vegetation-related outages, informed by satellite-based assessments of distribution rights-of-way.
of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 21 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 This enhanced detail of vegetation condition is used to improve the Company’...
AI summary NS Power's Five-Year Reliability Plan update utilizes enhanced vegetation condition data to guide risk-based interventions. Figure 8 illustrates regional progress in distribution vegetation management, showing spans cleared and ROW treated as of October 2025.
nt work programs. 5 6 Figure 8: 2025 (YTD End of October) Distribution Vegetation Management Completed by 7 Region Region Distribution Vegetation Management Spans Kms Metro 1,114 61 NE 3,913 217 CB 1,874 104 West 4,230 235 Total 11,131 617...
AI summary NS Power adjusted its 2025 vegetation management program due to provincial restrictions from the Department of Natural Resources (DNR) imposed during drought and wildfire conditions in 2025. Restrictions included halting heavy equipment operations during extreme fire weather and conducting fire watches, leading to revised work prioritization and scheduling to maintain reliability while complying with safety protocols.
2026 ACE Plan Appendix G Page 25 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 As of October 31, approximately 87 percent of the 2025 program has been completed and is on 2 track to have the full project work comple...
AI summary NS Power reports that 87% of the 2025 program has been completed and is on track for full completion by year-end. Figure 11 outlines vegetation transmission widening projects, including the L-6503-added line from Onslow to Trenton, which has 17 km completed year-to-date.
Y/N Line Kms Kms L-6503-added Onslow to Trenton 0 17 L-6002-added Sackville to 0 12 Bridgewater L-7005 Onslow to 16 9 Hopewell L-7003 Onslow to Port 29 22 Hastings L-7004 Dalhousie 23 18 Mountain to Port Hastings L-7009 Brushy Hill to 18 1...
AI summary NS Power updated transmission lines (e.g., L-6503, L-7005) in 2026 based on asset management priorities, reflecting shifts in infrastructure planning. The note highlights ongoing adjustments to targeted lines throughout the year.
2026 ACE Plan Appendix G Page 26 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 4.4 Establish New Rights-of-Way (ROW) 2 3 2025-2029 Forecast Investment: $86 million 4 2025 Anticipated Year End Investment: $16.4 milli...
AI summary NS Power's 2025-2029 program to establish new distribution rights-of-way aims to improve reliability, with $86 million in forecasted investment and 229 km completed by year-end, as detailed in Figures 12 and 13.
ge 739 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 32 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 Figure 18: 2025 Targeted Equipment Upgrades Progress Overview Program...
AI summary NS Power outlines its 2025 targeted equipment upgrades, including $81 million in distribution and transmission system investments. Key initiatives focus on replacing aging infrastructure, expanding protective devices, and ensuring environmental compliance to enhance system reliability and customer experience.
standards to align with the current CSA 21 C22.3 overhead line standards. In the Board’s decision on the 2025 Annual Capital Expenditure 22 (ACE) Plan (M12012), the Board directed the following: Page 35 of 71 Date: December 12, 2025 Page 7...
AI summary The Nova Scotia Energy Board directed NS Power to monitor upgraded pole installations and evaluate their impact on system reliability, aligning with the 2025 ACE Plan (M12012). Appendix C details pole monitoring projects across regions, focusing on resilience improvements and outage reduction.
dentifies the region, feeder, 9 location, and the number of poles scheduled for upgrade to the new class standard. These assets 10 will be monitored on an ongoing basis following storm events. 11 12 5.1.3 Distribution System Build to Roads...
AI summary NS Power's Distribution System Build to Roadside program aims to enhance reliability by relocating distribution lines to roadside locations, reducing tree-related contacts. In 2025, the program exceeded its 8 km target, completing 8.8 km and advancing 2 km of additional work, improving infrastructure accessibility and outage management.
2026 ACE Plan Appendix G Page 37 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 Figure 21: 2025 Build to Roadside Projects by Region YTD BTR Project BTR Project Status 2025 Planned Completed Comments Region BTR kms B...
AI summary The 2026 ACE Plan Appendix G details NS Power's 2025 Build to Roadside (BTR) project progress by region, showing planned vs. completed kilometers and project statuses (e.g., 'On Track – Ongoing' or 'Exceeded – Ongoing') for East, Northeast, Metro, and West regions.
nductor Region Reconductored Reconductored Reconductored Reconductored Target Status East 2 5.4 4 17.1 West 5 9.7 13 28.4 Metro 18 10.6 12 15.0 Northeast 7 12.8 10 13.2 2 3 5.1.5 Distribution System Underground Upgrades 4 5 The Distributio...
AI summary NS Power's Distribution Underground Program focuses on replacing aging underground infrastructure, including padmount transformers, vaults, and manholes. In 2025, NS Power exceeded its target of replacing 50 padmount transformers, completing 64 replacements by November. Additional upgrades, including three vaults and one manhole, are also underway.
ge 746 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 39 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 2 Figure 23: 2025 Completed Padmount Transformer Replacements and Upg...
AI summary NS Power outlines its 2025-2029 transmission system upgrade plan, allocating $196 million over five years and $32.6 million for 2025 alone. Projects focus on replacing structures, reinforcing conductors, and realigning lines to enhance reliability and resiliency, informed by risk profiles and past performance.
2026 ACE Plan Appendix G Page 42 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 2 NS Power has purchased and received a spare substation transformer. Replenishing this spare unit 3 supports the overall NS Power Trans...
AI summary NS Power is updating its Five-Year Reliability Plan by acquiring spare transformers, advancing substation projects (Bayers Lake, Stellarton), and completing the Mount Uniacke substation. These actions aim to improve system reliability and capacity while managing inventory costs.
RTUs planned for deployment in 2025. The remaining units are in progress and remain a priority 18 to have two completed before year-end, and the final three installations to be completed early in Page 44 of 71 Date: December 12, 2025 Page...
AI summary NS Power outlines its 2025 RTU deployment plan, with Phase 6 under regulatory review. The company emphasizes its commitment to the Board's oversight in ensuring project value for customers. Progress updates include completed and on-track installations across multiple substations, with final installations targeted for early 2026.
Complete West Kingston 63V Complete West Ohio Road 25W Complete West Central Argyle 19W On Track West Wolfville Ridge 83V Complete West Indian Path 80W On Track 7 8 6.1.2 Downline Connectivity 9 10 2025-2029 Forecast Investment: $44 millio...
AI summary The document outlines infrastructure projects with statuses (e.g., 'Complete', 'On Track'), a $44M 2025-2029 investment forecast, and a $5.2M 2025 investment. It references a cost reasonableness review (M12588) for NS Power's RTU Replacements Program and the 2026 ACE Plan Appendix G. The NS Power Five-Year Reliability Plan Update is also mentioned.
Region Area/Community Feeder/Substation Installation Status West Three Mile Plains 79V-401 In Progress/On Track Musquodoboit Metro Harbour 87H-313 In Progress/On Track Musquodoboit Metro Harbour 87H-313 In Progress/On Track Northeast Dicki...
AI summary The table outlines the installation status of infrastructure projects across Nova Scotia, with most projects in 'In Progress/On Track' and some planned for 2026 execution. Locations include regions like West, Metro, Northeast, and East, with specific feeders and communities listed.
2026 ACE Plan Appendix G Page 49 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.0 2026 – YEAR TWO – FIVE-YEAR RELIABILITY PLAN 2 3 2026 is year two of the Five-year Reliability Plan. NS Power has committed to an ov...
AI summary NS Power's 2026 reliability plan allocates $234 million for grid improvements, including storm hardening ($178.9M), vegetation management ($45M), and advanced grid modernization ($10.7M). This follows $206M in 2025 and over $185M annually in prior years, focusing on corridor widening, ROW establishment, and tree trimming.
ribution Establish New ROWs 377 kms Vegetation Management Trimming and Removal of Trees 192 kms Transmission Transmission Corridor Widening 121 kms Vegetation Management Distribution System Equipment 15 Trip Saver Additions Targeted Upgrad...
AI summary The document outlines infrastructure projects for Nova Scotia Power's reliability plan, including new right-of-way establishment, vegetation management, transmission corridor widening, and distribution system upgrades. Specific initiatives include conductor replacements, substation transformer replacements, and targeted equipment additions to enhance grid reliability.
Transmission System Upgrades 28 lines Substation Upgrades and 8 Transformers Replacements Remote Terminal Units (RTUs) 8 RTUs Downline Connectivity 35 Devices Advanced Grid Modernization Fault Location Isolation and 24 Devices Service Rest...
AI summary The 2026 ACE Plan Appendix G outlines NS Power's priority transmission system upgrades, including substation upgrades, RTUs, and FLISR devices. The 2026 priority feeder list includes 40 feeders, 31 newly identified and 9 carried over from 2025, based on outage data and load growth analysis. The list may be revised following full 2025 outage data analysis.
age 759 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 52 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.1 STORM HARDENING – VEGETATION MANGEMENT 2 3 2026 Forecast Investm...
AI summary NS Power's 2026 ACE Plan allocates $45 million for vegetation management to enhance power system reliability across 860 km of infrastructure. Regional breakdowns (Metro, Northeast, East, West) are detailed in Figure 33, with plans to refine the strategy based on 2025 performance data.
lowing analysis of 2025 16 year-end system performance, with potential refinements to address emerging priorities. 17 18 7.1.1 Distribution Corridor Widening with Managed Rights-of-Way (ROW) 19 20 2026 Forecast Investment: $13.2 million 21...
AI summary NS Power's 2026 ACE Plan outlines a $13.2 million investment to widen 293 kilometers of distribution corridors using existing rights-of-way across Central/Metro, East, Northeast, and West regions, as detailed in Figure 34 of the Five-Year Reliability Plan Update.
2026 ACE Plan Appendix G Page 54 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 In 2026, NS Power is forecasting an investment of $3.3 million to widen approximately 121 2 kilometers of transmission rights-of-way by...
AI summary NS Power plans to invest $3.3 million in 2026 to widen 121 km of transmission rights-of-way by five meters, enhancing storm hardening and reliability by increasing vegetation clearance from infrastructure. Figures 35 and 36 detail project spans and locations.
2026 ACE Plan Appendix G Page 55 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.1.3 Establish New Rights-of-Way (ROW) 2 3 2026 Forecast Investment: $18.5 million 4 5 The 2026 Vegetation Management Reliability progr...
AI summary NS Power's 2026 ACE Plan allocates $18.5M to establish 377km of new rights-of-way using satellite-driven vegetation management and $6.9M for trimming/removing trees along 192km of distribution lines, targeting reliability improvements across Central/Metro, East, Northeast, and West regions.
mming along approximately 192 kilometers of distribution line in 22 2026. Figure 38 provides a detailed breakdown of the communities and circuits where this work 23 is scheduled to take place 24 Page 55 of 71 Date: December 12, 2025 Page 7...
AI summary The document outlines NS Power's 2026 maintenance plans for 192 km of distribution lines across Central/Metro, East, Northeast, and West regions, with $83.9 million allocated for equipment upgrades under the 2026 ACE Plan. Storm hardening initiatives are forecasted to cost $178.9 million.
TS AND 4 UPGRADES 5 6 2026 Forecast Investment: $178.9 million 7 8 7.2.1 Distribution System Equipment Upgrades and Replacements 9 10 2026 Forecast Investment: $83.9 million 11 12 7.2.1.1 Modernize and Replace Aging Equipment 13 14 NS Powe...
AI summary NS Power plans $83.9M in 2026 for distribution upgrades, including PCB replacement and 7.1km of line relocation to roadside to improve reliability. Modernization efforts align with federal regulations and prioritize infrastructure renewal based on inspection data.
Build to Roadside kms Cape Breton 85S-401 Wreck Cove Rebuild 0.4 Cape Breton 103C-314 Grand Étang Water 0.9 Crossing Northeast 57C-426 Country Harbour Cell 2.6 Tower Build to Roadside Northeast 33N-201 Canaan Road Conversion 1.3 Northeast...
AI summary NS Power plans 2026 reconductoring projects to improve system reliability and performance, with Figure 40 detailing regional conductor upgrade kilometers: Cape Breton (20.1 km), West Metro (34.0 km), Northeast (17.2 km), and others. The text highlights infrastructure planning for distribution system upgrades.
34.0 West Metro 9.6 Northeast 17.2 2 3 In 2026, NS Power plans to complete approximately 30.9 kilometers of line and phase extensions 4 to enhance system reliability and operational flexibility. These projects are designed to improve 5 loa...
AI summary NS Power plans to complete 30.9 km of line and phase extensions in 2026 to enhance system reliability, reduce voltage drops, and improve service continuity in rural and developing areas. Projects are regionally distributed, with 5.5 km in the Northeast, 10 km in Metro, and 15.4 km in the West, as outlined in Figure 41.
1 7.2.1.4 Distribution System Underground Upgrades 2 3 In 2026, a planned investment of $10.2 million will support the Distribution Underground 4 program, aimed at strengthening and modernizing NS Power’s underground electrical system. Thi...
AI summary NS Power plans a $10.2M 2026 investment in underground distribution upgrades, including cable replacement in Kentville, SCADA-enabled switch installation in Halifax, and a high-capacity ductbank with QEII Health Sciences Centre. These projects aim to enhance system reliability, reduce outages, and support infrastructure growth in high-density areas.
wth in high-density areas by enabling 25 the extension of existing three-phase circuits. Additionally, the project will establish new feeder 26 ties, contributing to improved reliability and operational flexibility in the distribution netw...
AI summary The project involves extending existing three-phase circuits in high-density areas and establishing new feeder ties to enhance reliability and operational flexibility in the distribution network. Further details are referenced in CI C0074130 (matter M12456).
2026 ACE Plan Appendix G Page 60 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.2.2 Transmission System Upgrades and Replacements 2 3 2026 Forecast Investment: $43.0 million 4 5 In 2026, NS Power plans to invest ap...
AI summary NS Power plans to invest $43.0 million in 2026 for transmission system upgrades and replacements, including traditional infrastructure work, site-specific projects, and ongoing upgrade programs to enhance reliability and resiliency.
2026 ACE Plan Appendix G Page 61 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 Figure 42: Illustration of Targeted NS Power Transmission Projects Planned for 2026 2 3 4 7.2.3 Substation Upgrades and Replacements 5 6...
AI summary NS Power plans to invest $52.0 million in 2026 for substation upgrades and replacements to enhance system reliability and support regional growth, aligning with their asset management framework and community needs.
2026 ACE Plan Appendix G Page 62 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 NS Power plans to invest approximately $19 million in the replacement and addition of substation 2 transformers. Figure 43 lists the tra...
AI summary NS Power plans to invest $19 million in substation transformers, including replacements and additions, across various regions in Nova Scotia. New substations, such as in Stellarton and Bayers Lake, are expected to be energized in 2026, with further enhancements planned to improve system capacity and reliability.
NS Power Five-Year Reliability Plan - Update Non-Confidential 1 Figure 45: 2025/2026 Planned Communications Path with Downline Reclosers Installation
AI summary The document presents an update to NS Power's Five-Year Reliability Plan, focusing on the 2025/2026 planned communications path with downline reclosers installation.
ion 104H In Design. Metro Kempt Rd (multiple devices) Planned for 2026 Execution 2 3 7.3.3 Distributed Energy Resources (DERs) 4 5 As the presence of Distributed Energy Resources (DERs) such as solar, wind, and battery storage 6 continues...
AI summary The document discusses the importance of managing Distributed Energy Resources (DERs) such as solar, wind, and battery storage to maintain grid reliability and efficiency. NS Power plans to implement a DERMS platform through a capital work order in 2026 to enhance grid resilience and intelligence.
e efforts, NS Power will deliver a stronger, more resilient 22 grid capable of meeting the challenges of climate change, supporting electrification, and improving 23 the customer experience. 24 Page 67 of 71 Date: December 12, 2025 Page 77...
AI summary NS Power outlines efforts to enhance grid reliability through its Five-Year Reliability Plan, including updates on distribution feeders and work completed or in progress on 2025 priority feeders.
ED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 70 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 2026 Priority Targeted Equipment Protection Upgrades for Load Build to Vegetation Feeder? R...
AI summary The document outlines a list of targeted equipment replacements and protection upgrades for various regions in Nova Scotia, including details on load growth, vegetation work, and feeder status. The table includes regions, depots, and specific tasks such as protection upgrades and vegetation management.
2026 ACE Plan Appendix G Page 71 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 APPENDIX C– Pole Monitoring Projects – New Pole Class Standard 2 3 Summary of Pole Monitoring Project Locations 4 Region Feeder Location...
AI summary This appendix outlines NS Power's pole monitoring projects, including locations and details of pole removals and installations across different regions in Nova Scotia.
N-6NSPI (NSEB) RIR 1 to 202 - Redacted
84 passages
NON-CONFIDENTIAL 1 Request IR-1: 2 3 General Inquiries and Follow-Up pages 7 to 30 4 5 Page 8 notes that the targeted reliability projects include vegetation management, storm 6 hardening and upgrades, device replacements and grid moderniz...
AI summary The document includes a request (IR-1) asking to identify targeted reliability projects such as vegetation management and grid modernization from specific sections of the filing. The response refers to Attachment 1 for details.
2026 ACE Plan NSEB IR-1 Attachment 1 Page 1 of 3 1987.25 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17.1 17...
AI summary The document outlines a 2026 ACE Plan with a detailed table listing forecasted spending, project titles, combined categories, reliability enhancement, and asset classes. The content appears to be a planning and budgeting document related to energy infrastructure and asset management.
2026 ACE Plan NSEB IR-7 Attachment 1 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) CI# Project # Project Long Title Invesment Trigger 7 about the project to develop a fulsome application. 8 9 • Five projects were IT projects that...
AI summary The document outlines various projects and their investment triggers, including IT projects delayed due to a cyber incident, grid modernization initiatives, substation additions, and deferred projects such as the Synchronous Condenser and Sydney T&D Depot. These delays and deferrals are due to resource constraints, scope definition, and temporary arrangements.
NON-CONFIDENTIAL 1 factor forecasts for each thermal generating unit, as shown in Figure 9 of the 10YSO report. 2 These values represent NS Power's current forecast of expected operating patterns for 3 steam units, combined‑cycle units, co...
AI summary The text discusses NS Power's 10-Year System Outlook (10YSO) report, which includes utilization factor forecasts for thermal generating units and risk profiles for different fleet types, such as Thermal, Hydro, and Combustion Turbine, as outlined in various figures.
2026 Annual Capital Expenditure (ACE) Plan (NSEB M12619) NSPI Responses to NSEB Information Requests 1 Request IR-53: 2 3 Directives & Misc pages 87 to 141 4 5 Section 11.1.4 Impact of Reliability Projects pages 92 to 132 6 7 Page 106 stat...
AI summary NS Power states that it continuously evaluates opportunities to improve equipment resilience to adverse weather, including adopting practices from other utilities in harsher climates. Updates to design and construction standards are made based on lessons learned from extreme weather and evolving industry practices.
1 (c) The forecasted Utilization and Capacity Factors as per the 2025 10-Year System Outlook 2 provided in the table below. 3 2026 2027 2028 2029 Utilization Factor H M L UL Capacity Factor 61% 41% 12% 15% 4
AI summary The 2025 10-Year System Outlook 2 forecasts utilization and capacity factors for the years 2026 to 2029. The utilization factor is expected to range from high (H) to ultra-low (UL), while the capacity factor is projected to decline from 61% in 2026 to 12% in 2028, then slightly increase to 15% in 2029.
INTAKE EXTENSION FOUNDATION PREPARATION NOTES; - 1. CONTRACTOR SHALL FULLY EXCAVATE EXISTING LOOSE SILTY GRAVEL LAYER BENEATH NEW INTAKE EXTENSION - A. MINIMUM TRENCH WIDTH (u/s EXCAVATION) VARIES BASED ON THICKNESS OF EXISTING LOOSE SILTY...
AI summary The document outlines technical specifications for the excavation and installation of a new intake extension, including trench width calculations, slope requirements, and re-placement of excavated material. It emphasizes compliance with NSPI's geotechnical engineer and the need for a work plan for precast components.
3 G03: C0021608 TUC Shoreline Sheetpile Refurbishment
AI summary The text includes a reference to a project identified as G03: C0021608 TUC Shoreline Sheetpile Refurbishment, which may relate to infrastructure or maintenance activities.
8.1 Organizational Capabilities
AI summary This section discusses the organizational capabilities of the Nova Scotia Energy Board and Nova Scotia Power Inc. in the context of capital expenditures, reliability, and grid management. It highlights the importance of infrastructure planning and the role of various programs and initiatives in maintaining system reliability.
8.3 Project Plan
AI summary Section 8.3 of the document outlines the Project Plan, which includes details related to capital expenditures, infrastructure planning, and regulatory compliance. The plan addresses initiatives such as the 2026 Annual Capital Expenditure (ACE) Plan and the Integrated Resource Plan (IRP). It involves various entities and programs aimed at improving grid reliability and energy efficiency.
1. Administration & Mobilization - Complete safety, environmental, and dive plans; NSPI site onboarding. - Partially remove existing bridge and establish barge access. - Mobilize marine vessels, barges, cranes, excavators and other require...
AI summary The text outlines administrative and mobilization activities related to a project, including safety and environmental planning, site onboarding, and the mobilization of marine and construction equipment.
Preliminary Project Schedule JOB No. NSPI RFP 06 2025-545 Baseline Schedule Layout TUFTS COVE SHORELINE SHEET PILE ROCK REVETMENT 26-Aug-25 13:11 Data Date: 28-Sep-26 # Activity Name Original Duration Remaining Duration Start Finish Total...
AI summary The preliminary project schedule outlines the timeline for the Tufts Cove Shoreline Sheet Pile Rock Revetment project, including key activities such as mobilization, removal of an existing bridge, and a 53-day outage for Tufts Cove Unit 3. The schedule spans from September 2026 to November 2026.
3.1 Responsibilities
AI summary This section outlines the responsibilities related to the 2026 Annual Capital Expenditure (ACE) Plan, including the roles of various entities and the processes involved in managing capital expenditures and infrastructure planning.
2026 ACE Plan NSEB IR-71 Attachment 1 Page 43 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document is a redacted page from the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board (NSEB) as part of Information Request 71 (IR-71). It includes confidential information and is part of a larger submission related to capital expenditures and infrastructure planning.
2026 ACE Plan NSEB IR-71 Attachment 1 Page 46 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The text is a redacted page from the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board (NSEB) as part of Information Request 71 (IR-71). The page contains confidential information and is part of a larger document discussing capital expenditures, infrastructure planning, and regulatory compliance.
2026 ACE Plan NSEB IR-71 Attachment 1 Page 62 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document is a redacted page from the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board (NSEB) in response to Information Request 71. It appears to be part of a larger submission, with details about capital expenditures and infrastructure planning, though specific content has been removed due to confidentiality.
6.0 Project Scope of Work The scope of this project is to install an approximately 80-meter-long sloped rock revetment on the shoreline of the Tufts Cove Generating Station (TUC) in Dartmouth, NS. This work is required to mitigate the cond...
AI summary The project involves installing an 80-meter sloped rock revetment at the Tufts Cove Generating Station to restore shoreline structural integrity and accommodate a new intake extension. The work includes underwater excavation, placement of core and filter stone, and construction of a concrete box culvert. Environmental compliance and habitat enhancement are key considerations.
7.0 Site Location, Control, and Access
AI summary This section outlines the considerations related to site location, control, and access in the context of energy infrastructure planning and management. It includes details about regulatory processes, stakeholder involvement, and technical standards for ensuring reliability and safety.
2026 ACE Plan NSEB IR-71 Attachment 1 Page 66 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document is a redacted page from the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board (NSEB) as part of Information Request 71 (IR-71). It includes a table with data related to capital expenditures, potentially involving infrastructure planning and procurement practices.
2026 ACE Plan NSEB IR-71 Attachment 1 Page 77 of 139 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document is a redacted attachment from the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board (NSEB) in response to Information Request 71. It contains confidential information and is part of a larger proceeding related to capital expenditures and infrastructure planning.
Project Health & Safety Plan Tufts Cove Shoreline Sheet Pile Rock Revetment RFP-06/2025-545 Upon project completion, all permanent signs, traffic signals, beacons, and pavement markings impacted by the temporary workplace must be restored.
AI summary The Project Health & Safety Plan mandates the restoration of permanent signs, traffic signals, beacons, and pavement markings affected by temporary workplace activities upon project completion at Tufts Cove Shoreline Sheet Pile Rock Revetment RFP-06/2025-545.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 3 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a shoreline revetment project at Tufts Cove, identified by RFP-06/2025-545, as part of the 2026 ACE Plan. The text is redacted, indicating confidential information has been removed.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 7 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a request for proposal (RFP) for the Tufts Cove Shoreline Sheet Pile Rock Revetment project, identified as RFP-06/2025-545. No further details about the project's scope, costs, or stakeholders are provided in the excerpt.
8.3 PROJECT PLAN To complete this project, we will need to remove a section of bridge to the wharf. Nova Scotia Power will either remove piping on bridge or have it assembled in such a manner that it can be unbolted at the bridge joint. We...
AI summary The project plan outlines removing a bridge section to the wharf, utilizing specific equipment like a spud barge and excavators, with Nova Scotia Power managing the work. Material will be stockpiled at Tufts Cove, and a silt boom will be installed to prevent harbor contamination. Elliot Excavators Limited and Connors Diving Services Ltd. are involved in the project.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 10 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a shoreline revetment project at Tufts Cove, identified by RFP-06/2025-545, as part of the 2026 ACE Plan. No detailed discussion or arguments are present in the provided text.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 14 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a Request for Proposal (RFP) titled 'Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545' and includes a redacted page from the 2026 ACE Plan. The text highlights infrastructure-related procurement activities, though specific details are confidential.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 15 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary A redacted attachment from the 2026 ACE Plan discusses infrastructure planning related to a shoreline revetment project, referencing a Request for Proposal (RFP) numbered #RFP-06/2025-545. The document is part of a larger regulatory proceeding.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 16 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a shoreline revetment project at Tufts Cove, identified by RFP-06/2025-545, indicating a procurement process for infrastructure development.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 21 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document is part of the 2026 ACE Plan, referencing the Tufts Cove Shoreline Sheet Pile Rock Revetment project under RFP-06/2025-545. The content is redacted, with only an image placeholder and project details visible.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 29 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a Request for Proposal (RFP) for the Tufts Cove Shoreline Sheet Pile Rock Revetment project under the 2026 ACE Plan, indicating a procurement process for coastal infrastructure.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 32 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document references a shoreline revetment project at Tufts Cove, identified by RFP-06/2025-545, as part of the 2026 ACE Plan. The page is redacted, indicating confidential information has been removed.
2026 ACE Plan NSEB IR-71 Attachment 2 Page 46 of 53 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Tufts Cove Shoreline Sheet Pile Rock Revetment #RFP-06/2025-545
AI summary The document refers to a shoreline protection project at Tufts Cove with a specific request for proposal (RFP) number.
Rock Revetment - Armour Stone Layer Success: All values provided #8-1 Labour (Site Labour) 1 Lump Sum $ 125,000.00 $ 125,000.00 Success: All values provided #8-2 Materials 1 Lump Sum $ 515,000.00 $ 515,000.00 Success: All values provided #...
AI summary The text presents a detailed breakdown of costs for the Rock Revetment - Armour Stone Layer project and the Project Closeout, including labour, materials, equipment, and surveying expenses, with a total cost of $4,169,750.00.
1.1 Design Parameters Nova Scotia Power has indicated that the target design life for the structure is 50-years, with a design return period event of 200-years. This corresponds to an encounter probability of 22% over the structure's desig...
AI summary Nova Scotia Power has set a 50-year design life for the structure with a 200-year return period event, resulting in a 22% probability of occurrence during the structure's lifetime.
Return Design life [years] period [years] 1 5 10 20 30 40 50 75 100 1 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 20% 67% 89% 99% 100% 100% 100% 100% 100% 10 10% 41% 65% 88% 96% 99% 99% 100% 100% 25 4% 18% 34% 56% 71% 80% 87% 95% 98% 50...
AI summary The table presents return period and design life percentages, likely related to infrastructure planning or risk assessment, with data spanning from 1 year to 200 years. It is part of the 2026 ACE Plan and is attached to NSEB IR-78.
REDACTED 1 • The style of intake extension was changed from a king-pile canal to a pre-cast box 2 culvert canal, possibly introducing additional material, engineering and labour 3 expense. This change was made to better align with the proj...
AI summary The text discusses changes in project design, including a shift in intake extension style, increased equipment costs due to marine-based work, lack of inflation consideration, and additional rock revetment material due to sea level rise and geotechnical factors. It also addresses the replacement of turbine blades in the 2026 ACE Plan, emphasizing long-term reliability.
NON-CONFIDENTIAL 1 Request IR-81: 2 3 G04: C0068898 TUC1 IP LP Last Stage Blade Replacement 4 5 Please provide the forecast capacity factor and utilization factor for TUC1 for each year 6 from 2026 up to and including 2035. 7 8 (a) Given t...
AI summary The response to Request IR-81 discusses the forecast capacity and utilization factors for TUC1 from 2026 to 2035, citing figures from the 2025 10-Year System Outlook. It highlights that maintaining TUC1 beyond 2035 is the lowest-cost option for providing essential firm capacity and winter reliability, as outlined in the Evergreen Integrated Resource Plan.
Line No 17012 Work Order Report Line No: L 701 . 2 Work ( Order i Rep ort L7012-059 230-T-G(O) 70 0 70 Acess is West from the Cleveland Substation 45 40' 12.5599"N -61 14' 58.2495"W No 20235 7.04 7089013 1-2 years No Left pole is very holl...
AI summary The text presents details from a work order report related to pole replacements near the Cleveland Substation and Dowling Road. It outlines the need for replacing poles due to structural issues and includes information on the location, work order numbers, and timelines for replacement.
Line No: L7012 Work Order Report 2023S 7089013 2-4 years L7012-088 Overhead bonding wire Re-Insulate 3X12, Staple Swamp 45 40' -61 10' 15.1867"N 20.8552"W broken at top of right Down Ground pole this is reason for the failure Down ground n...
AI summary The document outlines various work orders related to the repair and replacement of overhead bonding wires and insulators at multiple locations, including issues with rust, broken wires, and structural concerns such as poles sounding hollow. Each entry includes specific coordinates, distances, and references to required letters of authorization from the Nova Scotia Department of Natural Resources.
Date: 2/4/2026 Page 6 of 10 Line No: L 701 . 2 Work ( Order 1 Rep ort L7012-110 230-T-G(O) 70 0 70 black river road. 45 40' 15.2071"N -61 6' 31.0859"W 20235 8.9 6.84 7089013 2-4 years left arm looks to be compressing/ has long weather crac...
AI summary The document details work orders for infrastructure maintenance along Black River Road, including inspections and repairs for poles and insulators. Issues such as weather cracks, compression, and rust are noted, with recommendations for installation and removal of specific components. A land occupation agreement (LOA) is mentioned as required for certain tasks.
CONFIDENTIAL (Attachment Only) 1 Request IR-116: 2 3 T02: C0070909, 70W-T52 Transformer Addition 4 5 The application notes three transformers: 70W-T51, 70W-T53, and 89W-T1. Page 365 that 6 the 2006 Bridgewater Area System Planning Study (2...
AI summary The document includes a request (IR-116) related to transformer additions and system planning in Bridgewater, Nova Scotia. It asks for details about feeders, customer counts, load data, installation dates, conversion progress, load transfer, and a 2006 planning report. The response indicates that data prior to 2022 is unavailable due to legacy limitations and provides data from 2022-2025.
REDACTED 2026 ACE Plan NSEB IR-116 Attachment 1 Page 4 of 52 Figure 1: Bridgewater Area - Transmission Switching Diagram 3 Figure 2: Existing Sub-transmission System - Bridgewater Area Figure 3: Town of Bridgewater Figure 4: Feeder Circuit...
AI summary The document contains figures and tables related to the Bridgewater Area's transmission and distribution systems, including load history, growth rates, and infrastructure details. These materials are part of the 2026 Annual Capital Expenditure (ACE) Plan submitted to the Nova Scotia Energy Board.
1.0 SUMMARY The Sub-transmission and distribution systems located in the Bridgewater area have been analyzed in this report over a ten year time frame. Results show that there is an immediate requirement for additional 12kV feeder capacity...
AI summary The report analyzes the sub-transmission and distribution systems in Bridgewater, identifying immediate needs for additional 12kV feeder and 69-12kV sub-station transformer capacity. Alternative A-2 is recommended for its lower cost and effort. Alternative B-2 is recommended to resolve a plant criteria violation at High Street Transformer 70W-T51. Additional work is required at Auburndale Sub-station and Line L-5545, and a full sub-transmission study of the Westhavers Elbow system is recommended.
2.0 EXISTING SYSTEM This study was initiated by a capacity criteria violation at the Bridgewater East Sub-station, and covers the period between 2004 and 2013. Forecasts beyond this time frame are uncertain due to the large amount of Sub-t...
AI summary The study was initiated due to a capacity criteria violation at the Bridgewater East Sub-station and covers the period from 2004 to 2013. Forecasts beyond 2013 are uncertain due to significant Sub-transmission work expected in 2012.
The 69kV Sub-transmission System in the Bridgewater area is supplied via the 138kV transmission system transformers identified in table #1 below. EHV Sub-station Transformer Data Sub-station Name Xfmr Manufacturer kV. Rating IMP. Age 75W -...
AI summary The 69kV Sub-transmission System in the Bridgewater area is supplied through 138kV transmission system transformers. Table 1 lists the EHV sub-stations, transformers, their manufacturers, ratings, ages, and other relevant data.
Factors Relevant to Report: - 1. Section 2 of Transmission Line L-5545 and Section 2 of Transmission Line L-5546 were built in 1957; are now 49 years old; and will either need to be rebuilt or replaced during the period covered by this rep...
AI summary The document discusses the aging infrastructure of several transmission lines (L-5545, L-5546, and L-5547), which were built in the 1950s and will require rebuilding or replacement during the period covered by the report. These lines are critical to the electricity transmission network in Nova Scotia.
2.1/ - 4. The previous Distribution Planning Report (#133-0788-W44) for the Bridgewater Area was conducted in 1988 and contained the following major recommendations: - Uprate the 69kV line from 99W to the 70W spur in 1990 (complete) - Repl...
AI summary The 1988 Distribution Planning Report for the Bridgewater Area outlined several infrastructure upgrades, some of which were completed, while others remain unfinished. The report projected higher load growth rates than what has been observed in recent years, with actual growth rates significantly lower.
.1 Load History Load data dating back to 1991 was obtained for each feeder circuit in Sub-stations 70W, 73W, and 89W (refer to Appendix A for feeder data summary). This data was checked against the available sub-station transformer load da...
AI summary Load data from 1991 for Sub-stations 70W, 73W, and 89W was analyzed to calculate historical load growth rates for High Street, Bridgewater East, and Auburndale Sub-stations, using feeder circuit, transformer, and sub-transmission line data.
Relevant Information: The load history shown in Figure 4 reflects the following: - 4kV load on 70W-203 and 70W-204 has remained fairly constant since 1995 (this will slowly be decreased as opportunities arise to convert 4kV to 12kV). - 2.6...
AI summary The text provides a historical overview of load changes on various feeder circuits in the Bridgewater East area, including load transfers and reconfigurations over time. It highlights how load has been redistributed between different circuits since 1995.
Relevant Information: - 1. The historical growth rate for the combined High Street and Bridgewater East Substations was found to be 2.11% per year. - 2. Frequent Load transfers between the High Street and Bridgewater East Sub-stations made...
AI summary The historical growth rate for the High Street and Bridgewater East Substations is 2.11% per year, with significant growth in Bridgewater on the Northeast side of the LaHave River, necessitating the combination of these sub-stations due to frequent load transfers.
Relevant Information: - 1. The historical growth rate for the Auburndale feeder circuits (25kV) was found to be 1.27% per year. - 2. The Auburndale feeder circuit 73W-412 maintains a 3 MVA reserve for the Michelin Bridgewater site. This re...
AI summary The text provides technical details on the Auburndale feeder circuits and transformer, including historical growth rates, reserve capacity, and cooling provisions. It also references a redacted 2026 ACE Plan and includes a figure related to load forecasting for the High Street sub-station.
Assumptions: - 1. The peak feeder loading for 70W occurs during the Winter months, so that the substation transformer 70W-T53 can be loaded to 133% of its top nameplate rating before being considered to be in an overloaded condition. - 2....
AI summary The text outlines assumptions regarding the capacity and loading conditions of the 70W substation transformer and mobile substation 5P-MS, predicting potential contingency capacity issues by 2014 and transformer overload by 2018 under normal and higher-than-normal load growth rates.
Assumptions: - 1. The peak feeder loading for 73W occurs during the Winter months, so that the substation transformer 73W-T1 can be loaded to 133% of its top nameplate rating before being considered to be in an overloaded condition. - 2. T...
AI summary The document outlines assumptions related to the capacity limitations and load forecast for the Auburndale and Bridgewater East sub-stations, highlighting potential overloading issues and the impact of growth rates on future capacity needs.
.1 Bridgewater 69kV Sub-transmission System (Within Report Scope): There are a number of criteria violations concerning the Bridgewater Sub-transmission system that will occur before 2012 if load at the Bridgewater East & High Street Subst...
AI summary The Bridgewater 69kV Sub-transmission System is facing multiple criteria violations due to load growth at Bridgewater East, High Street, and Auburndale substations. These violations include capacity and deteriorated plant issues, with projected violations extending up to 2013.
.1 Capacity Criteria Violation at Bridgewater East (2003) There is presently a capacity criteria violation at the Bridgewater East Sub-station during periods of peak load. The recorded 2002/03 Winter peak was 17.2 MVA, which is 154% of the...
AI summary A capacity criteria violation exists at the Bridgewater East Sub-station due to peak load exceeding transformer ratings. Load has been shifted to other substations, but further offloading is hindered by infrastructure failures. Additional load from new developments is expected, necessitating transformer upgrades.
Alternate Solutions: Three potential solutions were analysed to relieve the overload on the Bridgewater East Transformer 89W-T1. These included the option to add a second transformer at Sub-station 70W; the option to replace Sub-station Tr...
AI summary Three solutions to relieve overload on the Bridgewater East Transformer 89W-T1 were analyzed: adding a second transformer at Sub-station 70W, replacing the existing transformer with a larger unit, and using tertiary windings from other transformers to create a new 12kV supply. A fourth, more costly option involving voltage conversion and transformer replacement at Auburndale was not analyzed.
Alternative A-1: Add a new Transformer at 70W and Offload 89W This option relies on the installation of a second transformer at the High Street Substation to offload the distribution circuits supplied by the Bridgewater East Substation. -...
AI summary Alternative A-1 involves installing a new transformer at the High Street Substation and making several distribution upgrades in 2004 to offload the Bridgewater East Substation. The plan includes circuit conversions, reconductoring, and infrastructure upgrades to support new loads and improve reliability.
It involves the following work: - Install mobile sub-station at 89W prior to station work in 2004 - Move 89W-T1 to stores in 2004 - Remove the existing concrete pad at 89W in 2004 - Install a new pad complete with oil containment in 2004 -...
AI summary The document outlines a series of infrastructure upgrades and expansions at Sub-station 89W between 2004 and 2010, including transformer installation, pad upgrades, and new circuits to improve capacity and support new developments in Bridgewater.
It involves the following work: - Install a new 12kV bus assembly within 99W complete with two recloser bays & U/G station exits, a switch bay, and a bay to connect a new grounding (zigzag) transformer in 2004. - Install a new grounding tr...
AI summary The text outlines a series of electrical infrastructure upgrades and installations in 2004, including new bus assemblies, transformers, distribution lines, and reconductoring efforts to support new developments and improve reliability.
Qualitative Analysis 70W: Adding a transformer at Sub-station 70W would place additional capacity as near to the geographic load centre of Bridgwater as possible, and would therefore lower costs associated with system losses. The distribut...
AI summary The document evaluates two transformer upgrade options at Sub-stations 70W and 89W in Bridgwater. Adding a transformer at 70W would reduce system losses but require additional infrastructure for long-term growth. Replacing the transformer at 89W is considered a less costly and less disruptive solution, despite being further from the load centre.
Solution: 73W-T1 has provision for an additional fan kit that would raise its' top rating to 14 MVA. This would allow the Auburndale transformer to be loaded to 15.9 MVA (14 MVA x 1.33 - 3MVA Reserve = 15.9 MVA) before again being consider...
AI summary The 73W-T1 transformer can be upgraded with a fan kit to increase its capacity to 14 MVA, allowing the Auburndale transformer to handle up to 15.9 MVA before being considered overloaded. However, the addition of a new industrial customer with a peak load over 750kVA in the Bridgewater Industrial Park would necessitate the installation of the fan kit.
.5 Deteriorated Plant Criteria Violation: Line L-5545 (2013) The 2km section of Line L-5545 that runs between the Auburndale Tap and Wileville (L-5545 Section 3) was built in 1957; is now 46 years old; and has reached 110% of the average s...
AI summary A 2km section of Line L-5545, built in 1957, has reached 110% of its average service life of 42 years and is expected to require a major rebuild by 2013, based on the IOWA State Survivor Curve R-2.
.2 Bridgewater 69kV Sub-transmission System (Outside Report Scope): Two criteria violations concerning the Bridgewater 69kV Sub-transmission system are expected to occur by 2013. These are worthy of mention but do not fall within the scope...
AI summary The Bridgewater 69kV Sub-transmission system is expected to experience two deteriorated plant criteria violations by 2013, specifically on lines L-5547 and L-5546. These issues are noted but not addressed in this report as they fall outside its scope.
a) Deteriorated Plant Criteria Violation: Line L-5547 (2012) In addition to providing an alternate supply to Sub-station 89W via line L-5546, Westhavers Elbow also supplies Sub-stations 76W, 78W, 81W, and 82W via 17km of radial Line L-5547...
AI summary Line L-5547, built in 1955, has exceeded its service life and requires replacement. The line supplies multiple sub-stations and replacement must occur under live line conditions unless a new right of way is secured. Considerations include upgrading to 138kV and replacing aging 69kV transformers.
Westhavers Elbow (75W) MVA Figure 13: Westhavers Elbow Load Data (75W) It is evident that major changes/revitalization will be required to the Westhavers Elbow 69kV Sub-transmission System within the next ten to 15 years. As such, a separa...
AI summary The Westhavers Elbow 69kV Sub-transmission System is expected to require major changes or revitalization within the next 10 to 15 years. A separate sub-transmission study is recommended to evaluate the options of upgrading/rebuilding the system or gradually converting it to 138kV operation and replacing Sub-station 75W with a single 138kV Line tap.
b) Deteriorated Plant Criteria Violation: Line L-5546 (2013) The 5.7km section of Line L-5546 between the Bridgewater and Bridgewater East Sub-stations, and the 5.9km Section of L-5546 between the Bridgewater East and Westhavers Elbow Sub-...
AI summary A 5.7km and 5.9km section of Line L-5546, constructed in 1957, is composed of wooden poles and fixtures that are now 46 years old and require a major rebuild or replacement by 2013 due to deterioration.
Comments: The simplest solution to this violation would involve the rebuild of the 5.7km section of line between the Bridgewater and Bridgewater East sub-stations followed by the abandonment of the section between the Bridgewater East and...
AI summary The text discusses two potential solutions to address a violation involving power line infrastructure: rebuilding a section of line between Bridgewater and Bridgewater East sub-stations and abandoning another section, or constructing a new line tap to reduce load on the 69kV system and abandon an existing subtransmission line.
Sub-transmission Lines L-5546 & L-5547 In order to ascertain the true condition of lines L-5546 and L-5547 it will be necessary to have these lines surveyed prior to 2010.
AI summary To determine the actual condition of sub-transmission lines L-5546 and L-5547, a survey of these lines must be conducted before 2010.
5.0 RECOMMENDATIONS
AI summary This section outlines the recommendations made by the Nova Scotia Energy Board following the analysis and review of various proceedings, including considerations related to energy efficiency, infrastructure planning, and regulatory compliance.
REDACTED 2026 ACE Plan NSEB IR-116 Attachment 1 Page 38 of 52 Station Name Transformer I.D. Transformer Rating (MVA) Feeder kV (L-L) Feeder # Load 2002 Peak Amps Load 2002 Feeder MVA Calc 2002 Total MVA I.D. Α В C - 1 kV(L-L) MVA MW MVAR M...
AI summary The document presents a table detailing electrical transformer and feeder data, including ratings, load information, and calculations for various stations. It includes details such as transformer IDs, ratings, feeder voltage, load peak amps, and calculated MVA values for the year 2002.
Replace 89W-T1 with a New 15/20/25 MVA Transformer in 2004. This has a NPC $74,701 less than Alt A and $139,257 less than Alt C. Alt B is the 'least effort' and 'least cost' solution to the capacity problems within Bridgewater. Although 89...
AI summary The text discusses replacing the 89W-T1 transformer with a new 15/20/25 MVA transformer in 2004, noting cost savings compared to alternatives. Alt B is described as the least effort and least cost solution to capacity issues in Bridgewater, despite 89W being further from the load centre than 70W but on the same side of the LaHave river with significant load growth.
Add Capacity to 70W and Offload 89W This option requires a second transformer at 70W to offload 89W circuits. This location has a HV bus, switch, transformer pad, and low voltage bus already in place, although two of the bays in the LV bus...
AI summary This section outlines the plan to add capacity at 70W by installing a new transformer and reconfiguring existing circuits to offload 89W. It includes upgrading distribution lines, replacing a failed submarine cable, and modifying circuits to serve new developments and redistribute load.
Use 99W-T62 Tertiary to Offload 89W This alternative makes use of the fact that there is 12.5kV (delta) available from the tertiary windings of the power transformers within the Bridgewater EHV Sub-station 99W. In 2004, it involves install...
AI summary The proposal involves using the 12.5kV tertiary windings at Bridgewater EHV Sub-station 99W to offload 89W-301 by upgrading infrastructure, reconfiguring circuits, and replacing cables, ultimately reducing the load on 89W-T51 to 11MVA.
REDACTED 2026 ACE Plan NSEB IR-116 Attachment 1 Page 42 of 52 Test 4 Not Applicable (6,156.0) ####### 25,075.0 1,228,675.0 (1,239,750.0) (6,150.0) ####### 25,075.0 1,179,228.0 (6,126.0) (6,236.0) 6,520.1) (6,520.1) (6,520.1) (6,520.1) (6,5...
AI summary The document is a redacted page from an attachment to the 2026 Annual Capital Expenditure (ACE) Plan, referencing the Nova Scotia Energy Board (NSEB) Integrated Resource Plan (IR-116). It contains a table with numerical data, likely related to financial or resource planning, but the content is partially obscured.
Line No: L7001 Work Order Report Line No: L 700 1 Work Order l Rep ort Str# Str Type / Frm Type Pole Lgth L Pole Lgth C Pole Lgth R Access GPS Lat GPS Long Scoping Required Scheduled Grd Clr Min Grd Clr Work OrderID Field Priority Flagged...
AI summary The document details two work orders for electrical infrastructure maintenance in Nova Scotia. L7001-001 involves reinsulating a power line near a storage site, while L7001-003 requires replacing deteriorated spar arms and addressing structural issues on a pole along Old Woods Rd.
2026 ACE Plan NSEB IR-117 Attachment 1 Page 2 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Line No: L7001 Work Order Report L7001-017 230-T-G(O) 70 0 70 1M Stream N45-23- 39.80 W63-20-05.10 45 23' 37.1937"N -63 20' 7.2537"W No 2026S 10...
AI summary The text contains a redacted work order report detailing maintenance and repair tasks for electrical infrastructure in Nova Scotia. It includes locations, conditions, and required actions for various poles and insulators, with some entries indicating deterioration and the need for replacement and re-insulation.
2026 ACE Plan NSEB IR-117 Attachment 1 Page 3 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Line No: L7001 Work Order Report L7001-034 230-T-G(O) 75 0 75 Ingelwood Farm fields across railbed/walking trail. 45 21' 52.2991"N -63 21' 8.601...
AI summary The document outlines two work orders related to infrastructure maintenance on power lines in Nova Scotia. Both involve replacing deteriorating spar arms and reinsulating power lines, with specific environmental considerations for work in the Cobequid Bay area.
2026 ACE Plan NSEB IR-117 Attachment 1 Page 4 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Line No: L7001 Work Order Report L7001-054 230-T-G(O) 70 0 70 Samsons X-mas tree lot 45 19' 41.1475"N -63 21' 8.7492"W No 2026S 11.4 10.29 0000...
AI summary The document discusses a work order report for the replacement of a 70' 230-T-G(0) structure at Samsons X-mas tree lot due to failing insulator grout, hollow poles, and weather-cracked spar arms. It includes environmental considerations related to species at risk.
2026 ACE Plan NSEB IR-117 Attachment 1 Page 5 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Line No: L7001 Work Order Report L7001-071 230-Da-3(O)(0-60 Deg) 70 65 70 1M Stream with Atv Bridge N45-17-51.20 W63-21-25.8 45 17' 47.2483"N -6...
AI summary The document outlines work order reports for power line maintenance tasks in Nova Scotia, including details about damaged infrastructure such as weather cracks on idler spars, woodpecker holes in poles, and deteriorating insulator grout. The reports include recommendations for repairs and replacements.
2026 ACE Plan NSEB IR-117 Attachment 1 Page 6 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Line No: L7001 Work Order Report L7001-083 230-T-G(O) 70 0 70 Access Woods Road off Pleasant Valley Road Highway 289 45 16' 46.3171"N -63 22' 45...
AI summary The document contains work order reports for two locations detailing infrastructure issues, including cracked spar arms, rotten pole tops, deteriorating grout in insulators, and ant infestations. Each report includes specific coordinates, work order numbers, and proposed actions such as replacement and reinsulation.
Transmission Vegetation Management Costs from 2016 to 2025 by Voltage. Year 2022 L-5532 1 216.77 2,765 6,923.70 2022 L-5533 1 91.87 1,084 1,657.44 2022 L-5535 1 122.60 944 1,917.12 2022 L-5541 1 54.85 4 2.57 2022 L-5561A 1 2,562.87 2,692 4...
AI summary The document provides a detailed breakdown of transmission vegetation management costs from 2016 to 2025 by voltage level. It includes line numbers, quantities, and associated costs for various projects. The request is made in the context of distribution capital investments and the need for yearly data on primary overhead distribution lines.
5 (b) Please refer to Attachment 1 for the All‑Events Annual Outage Data from 2018–2025. The 6 annual results include all outage events from 2018–2025 for every feeder in all phases of 7 the vegetation management program, regardless of whe...
AI summary The document discusses outage data from 2018–2025, the impact of a cyber incident on data availability regarding vegetation management, and the lack of detailed breakdowns in the annual storm budget. It also notes that the New Distribution ROW program is not related to storm response.
1 which slowed down productivity. A continued focus on contractor efficiency is also 2 expected to help reduce the unit cost. Actual Phase 10 KM Feeder Geographic Location Plan KM Complete Change Description 100C-421 Havre Boucher 15 23 10...
AI summary The text discusses the impact of productivity slowdowns and the expected reduction in unit costs through improved contractor efficiency. It also includes a table showing the progress of various feeder projects, with some projects being removed due to priority shifts.
as time, cost, volume, or quality. 7 8 (b) Please explain how the utility will measure the actual business impact following the 9 deployment of this project. 10 11 Response IR-145: 12 13 (a) A specific business case report was not develope...
AI summary The response outlines expected benefits of a project, including streamlining execution, reducing truck rolls, and improving resource planning through enhanced data visibility and automation. Federal funding is noted to provide these benefits at a significantly reduced cost to customers.