Matter: Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q4 2025
2 passages 1 document

Infrastructure Planning across all matters →

N-1Dispatch Study Action Plan - Quarterly Update - Q4 2025 2 passages
EDOS Execution Milestones p. p. 2
EDOS Execution Milestones E Milestone Planned Status Q3 2025 Status Q4 2025 Requirements & Design 2024 Q4 100% 100% D Technical Realization 2025 Q1 65% 85% O System Integration Testing 2025 Q2 60% 90% S End-User Testing 2025 Q2 25% 50% Tra...

AI summary The EDOS Execution Milestones table outlines the progress of various phases in the implementation of the Energy Data Operating System, including requirements and design, technical realization, system integration testing, end-user testing, and training and deployment planning as of Q3 and Q4 2025.

Section 7 p. pp. 2-3
- Technical Realization 85% completed - All 18 interfaces reconnected - Data flow testing is underway - ECC PortOps solution configuration complete - Unit testing completed ready for January UAT - Communications Platform (for plants) devel...

AI summary The technical realization of the project is 85% complete, with all interfaces reconnected and data flow testing underway. Unit testing has been completed for the ECC PortOps solution and the Communications Platform, with testing scheduled to begin in January and continue through the month. The project is on track for a March 31, 2026 Go Live.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →