N-1Q4 Report 2025
1 passage
1 Recommendation number 1 is closed. 1 & Labrador. NS Power continues to work with NLH to finalize the associated protocols. 27 Update on CCI Recommendations 28 29 During NSPML's oral argument on October 30, 2024 regarding NSPML's 2025 30...
AI summary The document discusses updates on CCI recommendations related to NSPML's Final Project Cost proceeding (M10206) and provides performance updates on the Converters and Substations and Transmission Lines of the Maritime Link. NSPML continues to work with NLH on protocols and will provide updates through its Quarterly Report.
100553Board Letter re: Accepted as filed and requesting further updates
1 passage
M12516 & M12627 – NSP Maritime Link Inc. – Q3 & Q4 2025 Quarterly Reports On October 15, 2025, NSP Maritime Link Inc. (NSPML) filed its Q3 2025 report, which included the Independent Engineer's Site Visit Report dated August 28, 2025, and...
AI summary NSP Maritime Link Inc. submitted its Q3 and Q4 2025 reports, including updates on project statuses and a request for confidentiality. The Board approved the confidentiality request and noted ongoing developments related to infrastructure and regulatory agreements.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →