Topic:"Infrastructure Planning" in M12742

Matter: Nova Scotia Power Inc. - 2025 Annual FAM Report  (Fuel Adjustment Mechanism)
5 passages 3 documents

Infrastructure Planning across all matters →

N-1Annual FAM Report 2025 - Redacted 2 passages
Plant Maintenance p. p. 2
Plant Maintenance OM&G Expense by Operating Group Actual 2025 Actual 2024 Actual 2023 Actual 2022 Actual 2021 Actual 2020 Actual 2019 Budget 2025 Budget 2026 Pt. Aconi 21.0 19.8 11.5 15.3 12.2 12.4 14.8 19.1 12.7 Trenton 11.2 11.8 11.7 12....

AI summary The document presents a table showing OM&G expenses by operating group from 2020 to 2025, including actual and budget figures, along with specific maintenance and refurbishment projects under various operating groups such as Hydro, Combustion Turbine, and Fuel, Energy & Risk Management.

Major Projects - 2025 p. p. 2
Major Projects - 2025 PHB- SD UU Wennberg South Screw Re. PH Biomass POA LP HIP Turbine Refurb. Pt. Aconi POA Boiler Refurbishment Pt. Aconi POA PE Cell 4 phase 3 development Pt. Aconi POA Boiler Refractory Refurb. Pt. Aconi POA Coal Galle...

AI summary The text lists a series of major projects for 2025, including turbine refurbishments, boiler repairs, and infrastructure upgrades at various locations such as Pt. Aconi, Trenton, and Tufts Cove, indicating ongoing efforts in power plant maintenance and modernization.

N-2NSPI (NESB) RIR 1 to 17 - Redacted 2 passages
Major Projects - 2025 p. p. 3
Major Projects - 2025 Project Station PHB- SD UU Wennberg South Screw Re. PH Biomass POA LP HIP Turbine Refurb. Pt. Aconi POA Boiler Refurbishment Pt. Aconi POA PE Cell 4 phase 3 development Pt. Aconi POA Boiler Refractory Refurb. Pt. Acon...

AI summary The document lists major projects planned for 2025, including turbine and boiler refurbishments at various stations across Nova Scotia, such as Pt. Aconi, Pt. Tupper, Trenton, and Tufts Cove, as well as routine equipment replacements and infrastructure upgrades.

Major Projects - 2026 ACE p. p. 3
Major Projects - 2026 ACE Project Station POA Water Treatment Trailer Pt. Aconi LIN3 DCS Migration 2026 Lingan TUS Air System Upgrade Combustion Turbine (Includes LMs) LIN 8th Stage Blade Replacement 2026 Lingan WIN - DIG Gearbox Repl WTG1...

AI summary The document lists various major projects scheduled for 2026 across different locations in Nova Scotia, including water treatment, turbine upgrades, refurbishments, and infrastructure improvements related to energy and utility operations.

101683NSEB (NSPI) IR-1 to IR-17 - Redacted 1 passage
Request IR-4:
Request IR-4: - Reference: Tab A2NC - a) In cell F9, please explain the ~55% increase in output at Lingan 2, relative to 2024. - b) Is the overall reduction in gas production and increase in solid fuel production relative to 2024 due to th...

AI summary The text includes three questions from Request IR-4, asking for explanations regarding increased output at Lingan 2, changes in gas and solid fuel production linked to SO2 certificate of variance, and discrepancies in hydro capacity figures between noted and reported values in the 2025 system outlook.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →