NON-CONFIDENTIAL Filing Matter Number CI# Project Title Approved Budget (including contingency) Contingency ACE Plan Notes Scope 9 incident, and an explanation of other drivers (if any) of the same change. 10 11 Response IR-4: 12 13 The cy...
AI summary The text discusses a cyber incident that caused changes to a project schedule, specifically the delayed deployment of the Identity and Governance Administration (IGA) solution and Secure Infrastructure Access (SIA) capability. The cost increase was attributed to additional consulting and labor hours due to updated cybersecurity requirements and evolving cyber threats.
NON-CONFIDENTIAL - 1 The PAM portion of the IAM project was originally scheduled to run from July 2025 through 2 November 2025. - 3 - 4 Due to resource constraints, the timeline for the PAM deployment (outlined in Attachment 1 to the - 5 a...
AI summary The PAM portion of the IAM project faced delays due to resource constraints, leading to two re-baselining efforts. The timeline was adjusted in September 2025 and again in December 2025 with the inclusion of additional resources from NS Power and the vendor, as documented in a project change request.
18 Cost Element Total 12 Items that have progressed since filing: 13 14 The following items were classified as Preliminary at the time of filing but have since advanced 15 to Defined as of May 13, 2026: 16 17 1. Integrated Project Plan – D...
AI summary The text outlines the progression of several project elements, including the Integrated Project Plan, Stakeholder Consultation/Engagement/Management Plan, and Work Breakdown Structure (WBS), which have been defined as of April 30, 2026. These items were previously classified as Preliminary but have now advanced to a Defined status. The WBS has been finalized to the Milestone level for all project deliverables across PAM and IGA.