NON-CONFIDENTIAL 1 Request IR-1: 2 3 Page 1 of the application notes that the Lingan Unit 1 steam turbine consists of a dual flow 4 low pressure (DFLP) and a combined high and intermediate pressure (HIP) turbine that 5 convert steam, suppl...
AI summary The document outlines information requests regarding the refurbishment of Lingan Unit 1, including its current capacity, energy production data, emissions classification, retirement plans, alignment with NS Power's 2030 renewable targets, and actions taken to extend the unit's operational life. The requests also seek details on post-retirement roles and utilization factors.
CONFIDENTIAL (Attachment Only) 1 Request IR-3: 2 3 (a) Was an engineering assessment performed that recommended the proposed overhaul 4 of the components? If yes, please provide the report. If not, please explain why no 5 assessment was co...
AI summary The response to Request IR-3 indicates that no engineering assessment was performed for the proposed overhaul of turbine components, as the decision was based on maintenance strategy targets. Contract estimates were derived from previous project quotes and reviewed by subject matter experts. Risks covered by the 20% contingency are not explicitly detailed.