N-1Annual Report
8 passages
NON-CONFIDENTIAL 1 TABLE OF CONTENTS 2 3 1.0 INTRODUCTION 3 4 2.0 STATUS OF RECOMMENDATIONS AND DIRECTIVES 6 5 2.1 FERC Order 20238 6 2.2 Hosting Capacity Table 12 7 2.3 Connect and Manage Approach 13 8 2.4 Curtailment15 9 3.0 DISTRIBUTION...
AI summary The document outlines the structure of a proceeding, including sections on the status of recommendations and directives, distribution network upgrade cost refund regulation, and reporting requirements for non-CNMP distribution, generation, and battery activities.
6 Figure 2: Update Hosting Capacity Table Synapse Recommendation / Board Decision Directive Synapse Sub-Recommendations Synapse Recommendation: 6. Update the hosting capacity table by March of 2024 Board Directive: Update the NS Power host...
AI summary The document outlines a directive for NS Power to update its hosting capacity table by March 2024 and conduct technical workshops in late 2024. The updated table should include a coordinated dynamic hosting capacity analysis and facilitate flexible interconnection services.
fund amount will prevent large projects from causing significant pressure on rate base in the short term, while encouraging the development and execution of distribution connected generation projects. This recommendation assumes that the G...
AI summary Synapse recommends a cost refund regulation for distribution network upgrades, requiring full initial funding by the Interconnection Customer. Refunds of 50% of costs (up to $100k annually) begin after the Generating Facility's in-service date, contingent on its continued operation. The proposal was revised by NS Power to cap refunds at 20 years with a lump-sum payout for remaining balances.
annual rate equal to the Distribution Provider's WACC, with a total refund term not exceeding 20 years. Any outstanding payment after 20 years will be paid as lump sum to the Interconnection Customer. The initial investment in Distribution...
AI summary The document outlines a 20-year refund term for Distribution Network Upgrades, with a 50% refund over time as recommended by Synapse. The initial investment must be borne by the Interconnection Customer to avoid ratepayer costs. This aligns with Synapse's Final Report and acknowledges benefits from small-scale renewables. References include M10905, a Board Review of NS Power's interconnection processes.
In its comments of June 16, 2025, Synapse primarily focused on the straw proposal for refunds of - distribution network upgrades and recommended modifications to the straw proposal. Synapse - stated: While NS Power's straw proposal provide...
AI summary Synapse critiques NS Power's proposal for refunding 50% of distribution network upgrade costs, arguing it requires interconnection customers (ICs) to pay upfront for upgrades benefiting multiple parties. Synapse recommends a 50/50 split between rate-basing and ICs, with a threshold for class 2 projects to allocate costs proportionally and enable refunds based on future IC usage.
3.1 Broader System Benefits and Extension of Useful Life As set out in the original straw proposal, Distribution Network Upgrades (NU) are defined as any upgrade to existing distribution infrastructure that serves other customers on the ne...
AI summary The text discusses Distribution Network Upgrades (NU) and their broader system benefits, including direct and indirect contributions to system-level efficiencies and asset life extension. These benefits are considered in the Company's capital expenditure, interconnection, and planning processes.
1 Figure 5: Illustrative Example 2: Advancement Charge for a Planned Upgrade
AI summary Figure 5 presents an illustrative example of calculating an advancement charge for a planned upgrade in a Nova Scotia regulatory proceeding. It highlights the methodology for determining charges related to infrastructure upgrades, involving key entities and regulatory considerations.
Network Upgrade Cost: • Reconductoring estimated at $500,000
AI summary The text mentions a reconductoring cost of $500,000 related to network upgrades. This is a specific cost associated with upgrading the electrical network infrastructure.