Matter: Nova Scotia Power Inc. - CI C0082085 - 67C-T64 Transformer Replacement - $2,418,415 (U&U)Unforeseen & Unbudgeted (U&U) Capital Items:CI C0082085 - 67C-T64 Transformer Replacement - $2,418,415 $2,418,415 spent as at March 31, 2026 Partially Confidential
8 passages 2 documents

Infrastructure Planning across all matters →

N-1CI C0082085 67C-T64 Reactive Transformer Replacement - Report - Redacted 6 passages
Preamble p. p. 7
CI Number: C0082085 Title: 67C-T64 Transformer Replacement Start Date: 2025/07 In-Service Date: 2025/10 Final Cost Date: 2026/12 Function: Transmission Forecast Amount: $2,418,415

AI summary The document outlines a transformer replacement project under CI Number C0082085, with a forecasted cost of $2,418,415. The project is scheduled to start in July 2025, be in service by October 2025, and have a final cost date of December 2026. It serves the transmission function.

DESCRIPTION: p. p. 7
DESCRIPTION: This project was for the replacement of the failed 67C-T64 transformer at the 67C Whycocomagh Substation. As the sole electrical supply for the Whycocomagh area, the existing 67C-T64 138–26.4 kV, 15/20/25 MVA transformer was r...

AI summary This project involved replacing a failed 67C-T64 transformer at the 67C Whycocomagh Substation with an equivalent unit from a future project to maintain service reliability. The failure was due to a non-repairable phase-to-phase fault, and a mobile transformer was temporarily used until the replacement was installed in October 2025.

Why do this project? p. p. 7
Why do this project? 67C-T64 experienced an unexpected failure, leaving the substation without a permanent source of supply. The unit was assessed and determined to be beyond repair, making full replacement the only viable option to restor...

AI summary The 67C-T64 unit experienced an unexpected failure, rendering the substation without a permanent power supply. The unit was deemed beyond repair, necessitating full replacement to ensure long-term reliability and system integrity.

Why do this project now? p. p. 7
Why do this project now? 67C-T64 experienced an unexpected failure, leaving the substation without a permanent source of supply requiring immediate replacement. The replacement was prioritized because winter load was approaching and mobile...

AI summary The substation 67C-T64 failed unexpectedly, requiring immediate replacement to ensure a permanent power supply. The replacement was prioritized due to approaching winter load and the need for mobile transformer flexibility. The work was completed in October 2025 to ensure asset readiness for winter.

Document No: XXX-XX-XXXX-XXXX p. p. 7
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Transmission Line Infrastructure Required fields: Estimate Classification Project Name: 67C-T64 Transformer Replacement Started or Preliminary Class 5...

AI summary This document outlines a checklist and maturity matrix for estimating the cost of a transformer replacement project. It includes sections on project scope, location, technology selection, planning, and regulatory approvals, with classifications for different stages of project definition.

Inclusions p. p. 7
Inclusions For the purposes of this document, the term power transmission line infrastructure industries is assumed to include greenfield or brownfield sites for overhead, buried and submarine transmission of electrical power in the infras...

AI summary The document defines 'power transmission line infrastructure industries' and excludes certain facilities like process plants and substations. It highlights that power transmission is part of the infrastructure industry and references definitions from the Construction Industry Institute.

N-2NSPI (NSEB) RIR 1 to 4 - Redacted 2 passages
Section 1
CI C0082085 – 67C-T64 Transformer Replacement (NSEB M12899) NSPI Responses to NSEB Information Requests

AI summary The document outlines NSPI's responses to information requests from NSEB regarding the CI C0082085 – 67C-T64 Transformer Replacement project under matter number M12899.

NON-CONFIDENTIAL
NON-CONFIDENTIAL 1 Request IR-4: 2 3 (a) What, if any, protections are being put in place to ensure a similar fault does not 4 happen to the new transformer? 5 6 (i) Why were these protections not implemented for the old transformer? 7 8 R...

AI summary The document discusses a request regarding protections for a new transformer and why similar protections were not implemented for the old transformer. The response refers to another request (IR-2 (b)) for further details.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →