is a more complex approach to start up, but we believe once we're done with it, from our experience, it has paid off and has performed the way we would anticipate the design would deliver the benefit. [Sound File, October 22,2010,50:54 - 5...
AI summary The Board acknowledges NSPI's approach to the Tufts Cove 6 Waste Heat Recovery Project, noting that while the initial engineering design was complex, it ultimately proved effective. However, the Board emphasizes the need for more detailed preliminary engineering, especially for new technologies. NSPI's economic analyses for the project were based on assumptions from the 2007 Integrated Resource Plan.