Topic/Matter Intersection

Topic:"Intervenor Participation" in M12412

Matter: Nova Scotia Independent Energy System Operator (IESO Nova Scotia) - Proposed expenditure and revenue requirements for test year ending March 31, 2026
5 passages 5 documents

Intervenor Participation across all matters →

N-5NSIESO (Doane Grant Thornton) RIR 1 to 37 - Redacted 1 passage
Response IR – 21 p. p. 27
Response IR – 21 - a) We do not have a specific breakdown of the portion of the costs that may be allocable to - Intervenors. Energy Board staff provided a global estimate of approximately $200,000 - for a full regulatory proceeding, inclu...

AI summary The response provides a global estimate of approximately $200,000 for a full regulatory proceeding, including costs for intervenors to participate. No specific breakdown of allocable costs is provided.

98900Notice of Intervention - IG 1 passage
COUNSEL
COUNSEL Stewart McKelvey Suite 600 – 1741 Lower Water Street P.O. Box 997 Halifax, NS B3J 2X2 Fax (902) 420-1417 Attention: Brianne Rudderham Email: [[email protected]](mailto:[email protected]) Attention: Nancy G...

AI summary Stewart McKelvey represents the Industrial Group in a Nova Scotia regulatory proceeding, providing contact details for counsel Brianne Rudderham, Nancy G. Rubin, K.C., Leona Clements, and Caroline Jonah. The document is dated August 8, 2025, and addressed to the Nova Scotia Energy Board (NSEB) regulatory affairs officer.

99053Notice of Intervention - SWEB 1 passage
RE: M12412 - Nova Scotia Independent Energy System Operator (NSIESO) - Proposed expenditure and revenue requirements for test year ending March 31, 2026 \
RE: M12412 - Nova Scotia Independent Energy System Operator (NSIESO) - Proposed expenditure and revenue requirements for test year ending March 31, 2026 \ SWEB Development is a developer, owner, and operator of renewable energy projects th...

AI summary SWEB Development LP requests intervenor status in M12412 regarding the NSIESO's proposed budget for 2026, arguing it could impact interconnection efficiency for their renewable projects. They highlight concerns about the budget's influence on interconnection processes and implementation of updates from M10905.

99149Notice of intervention - PHP 1 passage
NOTICE OF INTERVENTION
NOTICE OF INTERVENTION TO: The Nova Scotia Energy Board ("Board") AND TO: The Nova Scotia Independent System Operator - 1. PORT HAWKESBURY PAPER LP ("PHP") conducts its business in Nova Scotia, and is engaged in the manufacture of paper at...

AI summary Port Hawkesbury Paper LP (PHP) seeks intervenor status in a Nova Scotia Energy Board hearing, citing its significant power purchases from NSPI under the ELIADC Tariff. PHP provides contact details for the proceeding.

99150Notice of Intervention - MEUs 1 passage
NOTICE OF INTERVENTION
NOTICE OF INTERVENTION TO: The Nova Scotia Energy Board ("Board") AND TO: The Nova Scotia Independent System Operator 1. The BERWICK ELECTRIC COMMISSION, the RIVERPORT ELECTRIC COMMISSION, the TOWN OF MAHONE BAY, and the TOWN OF ANTIGONISH...

AI summary The BERWICK ELECTRIC COMMISSION, RIVERPORT ELECTRIC COMMISSION, TOWN OF MAHONE BAY, and TOWN OF ANTIGONISH (MEUs) purchase power from Nova Scotia Power Inc. under the Municipal and BUTU rates. They also face impacts from the Spill Tariff due to their ownership of the sole customer under it. The MEUs seek intervenor status in the proceeding to protect their interests.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →