Topic:"Jurisdictional Questions" in M13127

Matter: Nova Scotia Power Inc. - CI C0086325 – Maritime Launch Services - $0 (U&U)
1 passage 1 document

Jurisdictional Questions across all matters →

N-1CI C0086325 – Maritime Launch Services - Application - Redacted 1 passage
Maximum Short Circuit Level at the MLS Spaceport Site p. p. 24
Maximum Short Circuit Level at the MLS Spaceport Site Supply Feeder Fault Amps MVA X/R Ratio LLL 1361 59 3.76 24C-442 LG 879 38 2.87 7.0 COST & RIGHT OF WAY RESPONSIBILITY

AI summary The document presents a table with data on the maximum short circuit level at the MLS Spaceport Site, including supply feeder details and fault information. The text also introduces a section on cost and right of way responsibility.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →