REDACTED 2022-2023 FAM Audit Action Plan Update Attachment 1 Page 1 of 18 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Row Recommendation Action Plan Response from NS Power February 2026 Update 23 Recommendation X-7: Pursue Damages NSPI sho...
AI summary The document discusses NS Power's response to Recommendation X-7, which involves pursuing damages under its agreement with Nordex. A mediation with Nordex resulted in a settlement, and as of January 2026, 29 of 34 turbines are available with no derated turbines or identified risks.