Types of Analysis p. p. 151
Types of Analysis Sliding Overturning Load Conditions Load Combinations FoS Usual D+H+I+Sh+U 1.5 one-third Usual (No Ice) D+Hf+Sh+U 1.5 one-third Unusual (Flood) D+Hf+Sh+Uf 1.3 one-half Unusual (Temperature) D+H+I+Sh+U+T 1.3 one-half Extre...

AI summary The text presents a table outlining various load conditions and their corresponding factor of safety (FoS) and overturning stability criteria for structural analysis, including usual, unusual, and extreme scenarios.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →