2025. the commercial operation date (COD) until February 28, 2025. Under the interim arrangement, no credits were issued under the CSECR prior to the execution of the CSP PPA with the Project Owner. By Order dated January 30, 2025, the Boa...
AI summary The document outlines the implementation timeline for the Community Solar Program (CSP) and related regulatory actions. Key events include the Board's approval of the CSP PPA in January 2025, the execution of the first PPA in February 2025, and the Board's December 2025 order directing NS Power to inform low-income Solar Garden subscribers about transitioning to CSP. NS Power complied by notifying subscribers in January 2026, though no new CSP capacity was available at the time.