57984Submission - Barrington Wind Energy Ltd. - Re: Late Filed Evidence 1 passage
Section 2
g of the second round IR's to NSPI raises concerns as a specific example of the cha1Ienges to due process that are encroaching upon Intervenors ability to usefully participate in regulatory processes. We understand that there are additiona...

AI summary The document raises concerns about due process in regulatory proceedings, citing late filings, inconsistent data provision, increasing confidentiality, and fragmented processes that hinder intervenor participation. It requests a deferral of hearing dates and highlights the need for a more coordinated approach to regulatory processes.

58003Participant responses to Preliminary Issues List for P-886 2 passages
Nancy McNeil - CME Submission re Preliminary Issues List P-886
recommended that there be a hearing for a new COSM before another rate hearing. We feel that items such as revenue requirements, rate design, cost of service and future planning should be considered. - 6. The CME notes that in the 2005 rat...

AI summary The CME recommends that a hearing for a new COSM be held before another rate hearing, emphasizing the need to address inter-related issues such as revenue requirements, rate design, and future planning. The CME also expresses concern about potential delays in addressing important issues and suggests that the Board consider long-term impacts and the best interests of Nova Scotians.

RECEIVED
RECEIVED OCT 3 1 2005 BERWICK, NOVA SCOTIA Nova Scotia Utility and Review Board October 30, 2006 By e-mail; original follows Ms Nancy McNeil, Regulatory Affairs Officer The Nova Scotia Utility and Review Board P.O. Box 1692, Unit "M", Hali...

AI summary The letter discusses the integration of multiple processes, including the Integrated Resource Plan (IRP) and the Energy Efficiency and Load Integration Report (ELIR-2) rate hearing, and emphasizes the need for a coordinated approach. It supports delaying the IRP timeline to ensure thorough consideration and calls for provincial leadership in energy and emissions policy.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →